Primavera P6 Project Assignment

 Define EPS
XYZ

 Define calendar
 General Holidays

 26th January
 15th August
 14th November
 2nd October
 25th December

 Weekly holidays

 Saturday
 Sunday

Weekly hours/day 8hrs

 Define Project
 Residential Buildings

 Define WBS
1
Syed Osman Rayees
(Civil Engineer)
Ph.no.:- +91 7207 147 581
 Foundation
 Sub-Structure
 Super-Structure
 Finish Work

 Define Milestone
 Project Start
 Project End
 Foundation work start
 Foundation work end
 Sub-Structure work start
 Sub-Structure work end
 Super-Structure work start
 Super-Structure work end
 Finish work start
 Finish work end

 Define Activities

1. Site survey (Foundation)

2. Boundary stones fixing(Foundation)

3. Permissions for construction (Foundation)

4. Site clean (Foundation)

5. Compound wall (Foundation)

6. Recruit manpower for project (Foundation)

7. Site marking (Sub-Structure)

2
Syed Osman Rayees
(Civil Engineer)
Ph.no.:- +91 7207 147 581
8. Excavation (Sub-Structure)

9. Purchase materials (Sub-Structure)

10. Footing P.c.c (Sub-Structure)

11. Centering work for footings (Sub-Structure)

12. Tie-Beam P.C.C (Sub-Structure)

13. Centering work for Tie-Beam (Sub-Structure)

14. Pouring concrete in Footings (Sub-Structure)

15. Pouring concrete in Tie-Beam (Sub-Structure)

16. Centering work for Neck Columns (Sub-Structure)

17. Pouring concrete in Neck Columns (Sub-Structure)

18. Water sump (Sub-Structure)

19. Back Fill (Sub-Structure)

20. Plinth Beam P.C.C (Sup-Structure)

21. Centering work for Plinth Beam (Sup-Structure)

22. Pouring concrete in Plinth Beam (Sup-Structure)

23. Grade Slab (Sup-Structure)

24. Centering work for Flr. Columns (Sup-Structure)

25. Pouring concrete in Flr. Columns (Sup-Structure)

26. Centering work for stair case (Sup-Structure)


3
Syed Osman Rayees
(Civil Engineer)
Ph.no.:- +91 7207 147 581
27. Pouring Concrete in stair case (Sup-Structure)

28. Centering work for Flr. Beams (Sup-Structure)

29. Centering work for slab (Sup-Structure)

30. Electrical Work for Slab (Sup-Structure)

31. Pouring concrete in Flr. Beams & Flr. Slab (Sup-Structure)

32. Curing (Sup-Structure)

33. Removing Slab Shuttering (Sup-Structure)

34. Brick work (Sup-Structure)

35. Fixing frames of doors & windows (Sup-Structure)

36. Fixing electrical pipes in walls (Finish)

37. Plumbing work (Finish)

38. Plastering 1st cote (Finish)

39. Plastering 2nd cote (Finish)

40. Bath room tiles work (Finish)

41. Kitchen room tiles work (Finish)

42. Rooms Flooring (Finish)

43. Wall Putty (Finish)

44. White wash (Finish)

45. Paint (Finish)


4
Syed Osman Rayees
(Civil Engineer)
Ph.no.:- +91 7207 147 581
46. Wiring interior (Finish)

47. Fixing all electrical switches and boards (Finish)

48. A/C works (Finish)

49. Fixing plumbing items (Finish)

50. Wood works for doors/windows/ventilators (Finish)

51. Glass work (Finish)

 Define Relationships
 F-S
 S-S
 F-F
 S-F

 Create layout

 WBS Layout
 Department Layout
 Responsibility Layout
 Activities layout
 Budgeted cost layout

Resource Management

5
Syed Osman Rayees
(Civil Engineer)
Ph.no.:- +91 7207 147 581
 Define resources
 Cement – 330/bg
 Sand -1600/Ton
 Bricks – 5.5/No
 Polythene Sheet – 750/sheet
 Steel- 46000/Ton
 Bath room Tiles- 22/No
 Kitchen tiles- 29/No
 Bath room flooring tiles-35/No
 Granite- 35/sft
 Wood- 25/sft
 Glass-45/sft
 Total station machine-3600/d
 Surveyor-1200/d
 Supervisor-800/d
 Daily labour-550/d
 Site engineer-900/d
 Site incharge-1000/d
 Project manager-2500/d
 Design engineer-1500/d
 Civil engineer-2000/d
 Mechanical engineer-2000/d
 Electrical engineer-2000/d
 Electrician-800/d

6
Syed Osman Rayees
(Civil Engineer)
Ph.no.:- +91 7207 147 581
 Welder-800/d

 Dozer- 700/h

 Tractor- 2000/d

 Jcb- 1000/h

 Mason- 650/d

 Hr manager- 2000/d

 Purchasing manager-1500/d

 40mm metal- 130/cft

 20mm metal- 150/cft

 Bar bender- 600/d

 Centering mason- 700/d

 A/C Technician- 1000/d

 Dumper Machine 750/h

 HVAC Designer- 600/d

 Plumbing engineer- 800/d

 Plumber- 500/d

 Binding wire- 70/kg

 Electrical wire- 80/mt

 Drainage pipes-80/ft

7
Syed Osman Rayees
(Civil Engineer)
Ph.no.:- +91 7207 147 581
 Water tank 10,000 Liters- 3,000/No

 Water pipes- 55/ft

 White wash- 700/50kg

 Paints- 1200/can

 Stones (10ft)- 120/No

 Fencing wire-60/kg

 Electrical pipes- 30/ft

 A/C (Blue star)- 65000/No

 Sanitary pipes- 250/No

 Carpenter- 800/d

 Switch boards- 150/No

 White cement- 65/kg

 Painter- 700/d

 Assign resources

Resources Assignment
S.no Activity Name Resources

1 Site survey SURVEYOR, T.S MACHINE, DAILY LABOUR

2 Boundary stones fixing Daily labor, stones, fencing wire

3 Permissions for construction Project manager, management team

8
Syed Osman Rayees
(Civil Engineer)
Ph.no.:- +91 7207 147 581
4 Site clean Dozer, daily labor, jcb, S.E, supervisor

5 Compound wall Daily labor, mason, bricks, cement, sand

6 Recruit manpower for project H.R Manager

7 Site marking Daily labor, S.E, C.E

8 Excavation JCB, Tractor, daily labor, S.E, Supervisor

9 Purchase materials Purchasing Manager, P.M

10 Footing P.c.c Cement, sand, 40MM metal

Steel, bar bender, centering mason, C.E,


11 Centering work for footings supervisor, S.E

12 Tie-Beam P.C.C Cement, sand, 40MM metal, Masoon, D.L.

Steel, bar bender, centering mason, C.E,


13 Centering work for Tie-Beam supervisor, S.E

14 Pooring concrete in Footings cement, sand, 20MM metal, D.L, S.E,


supervisor, C.E, mason, Vibrator

15 Pooring concrete in Tie-Beam cement, sand, 20MM metal, D.L, S.E,


supervisor, C.E, mason, Vibrator

16 Centering work for Neck Steel, bar bender, centering mason, C.E,
Columns supervisor, S.E

17 Pooring concrete in Neck cement, sand, 20MM metal, D.L, S.E,


Columns supervisor, C.E, mason, Vibrator

18 Water sump S.E, Cement, Sand, 20MM Metal, D.L, Masoon,


Supervisor.

19 Back Fill Dozer, daily labor, S.E, supervisor

9
Syed Osman Rayees
(Civil Engineer)
Ph.no.:- +91 7207 147 581
20 Plinth Beam P.C.C Cement, sand, 40MM metal, Masoon, D.L.

Steel, bar bender, centering mason, C.E,


21 Centering work for Plinth Beam supervisor, S.E

22 Pooring concrete in Plinth Beam cement, sand, 20MM metal, D.L, S.E,
supervisor, C.E, mason, Vibrator

23 Grade Slab Steel, bar bender, centering mason, D.L, C.E,


supervisor, S.E Cement, sand, 20MM metal,

24 Centering work for Flr. Columns Steel, bar bender, centering mason, C.E,
supervisor, S.E

25 Pooring concrete in Flr. Columns cement, sand, 20MM metal, D.L, S.E,
supervisor, C.E, mason, Vibrator

26 Centering work for stair case Steel, bar bender, centering mason, C.E,
supervisor, S.E

27 Pooring Concrete in stair case cement, sand, 20MM metal, D.L, S.E,
supervisor, C.E, mason, Vibrator

28 Centering work for Flr. Beams S.E, supervisor, C.E, mason, Vibrator

29 Centering work for slab Steel, bar bender, centering mason, C.E,
supervisor, S.E

30 Electrical Work for Slab Electrician, E.E, D.L, electrical pipes, electrical
wire

31 Pooring concrete in Flr. Beams & cement, sand, 20MM metal, D.L, S.E,
Flr.Slab supervisor, C.E, mason, Vibrator

32 Curing D.L, S.E

33 Removing Slab Shuttering centering mason, C.E, S.E

34 Brick work Bricks, cement, sand, D.L, S.E, supervisor, C.E,


mason.

Fixing frames of doors &


S.E, C.E, Mason, Wood, D.L,
35 windows

10
Syed Osman Rayees
(Civil Engineer)
Ph.no.:- +91 7207 147 581
36 Fixing electrical pipes in walls Electrician, E.E, D.L, electrical pipes.

37 Plumbing work P.E, D.L, S.E, Supervisor, Sanitary pipes

38 Plastering 1st cote Bricks, cement, sand, D.L, S.E, supervisor, C.E,
mason.

39 Plastering 2nd cote cement, sand, D.L, S.E, supervisor, C.E, mason.

40 Bath room tiles work Tiles, white cement, cement, mason, D.L, S.E,
supervisor

41 Kitchen room tiles work Tiles, white cement, cement, mason, D.L, S.E,
supervisor

42 Rooms Flooring Masoon, D.L, S.E, Cement, Sand, room tiles.

43 Wall Putty putty bags, D.L, painter, S.E, supervisor

44 White wash White wash, D.L, painter, S.E, supervisor

45 Paint paints, D.L, painter, S.E, supervisor

46 Wiring interior Electrician, E.E, D.L, electrical wire

47 Fixing all electrical switches and Switch boards, D.L, S.E, supervisor, E.E,
boards electrician

48 A/C works A/C(Blue star), A/C Technician, HVAC Engineer,


D.L, S.E, Supervisor

49 Fixing plumbing items P.E, D.L, S.E, Supervisor, Sanitary pipes

50 Wood works for Wood, carpenter, D.L


doors/windows/ventilators

51 Glass works Glass, daily labor

11
Syed Osman Rayees
(Civil Engineer)
Ph.no.:- +91 7207 147 581
 Expenses items
 Traveling charges
 Consultation fees
 Medical Allowances
 Equipment repairing charges
 Training Charges
 Accommodation charges

Expenses Assignment
S.n
o
Expenses items Activity cost

1 Travelling charges Site Survey 15,000/-

2 Travelling charges Permission for construction 25,000/-

3 Travelling charges Excavation 5,000/-

4 Travelling charges Purchase Materials 23,000/-

5 Consultation fee for legal approval Permission for construction 50,000/-

6,00,000/
Recruit manpower for project
6 Medical allowances -

7 Equipment repairing Charges Purchase Materials 75000/-

2,35,000/
Purchase Materials
8 Training charges -

4,75,000/
Permission for construction
9 Accommodation charges -

12
Syed Osman Rayees
(Civil Engineer)
Ph.no.:- +91 7207 147 581