PROPOSE PROJECT: THREE STOREY ADMIN BUILDING (OFFICE WITH AVR/THEATHER ROOM)
LOCATION: PRMSU OVAL
LIST OF ACTIVITIES
ACTIVITIES:
1. MOBILIZATION
2. CLEARING AND GRABBING
3. SURVEY
4. LAYOUT
5. EXCAVATION WORKS
6. REINFORCING STEEL WORKS
7. FORMS AND SCAFFOLDING
8. FOUNDATION WORKS
9. CONCRETE WORKS
10. MASONRY WORKS
11. PLUMBING WORKS
12. STRUCTURAL STEEL WORKS
13. PLUMBING FIXTURES
14. TINSMITHRY
15. ELECTRICAL WORKS
16. INSTALLATION OF DOORS
17. PLASTERING
18. CEILING WORKS
19. TILE WORKS
20. INSTALATION OF GLASS WALL
21. PAINTING WORKS
22. DEMOBILIZATION
LIST OF ACTIVITIES
ACTIVITY DURATION JOB DESCRIPTION
1-2 2 Mobilization
2-3 4 Clearing and Grabbing
3-4 1 Survey
4-5 4 Layout
5-6 7 Excavation Works
4-7 44 Reinforcing Steel Works
7-9 42 Forms and Scaffolding
6-8 19 Foundation Works
8-10 91 Concrete Works
8-9 80 Masonry Works
9-11 28 Plumbing Works
10-11 21 Structural Steel Works
9-11 28 Plumbing Fixtures
11-12 28 Tinsmithry
11-13 28 Electrical Works
12-14 21 Installation of Doors
13-15 30 Plastering
15-16 30 Ceiling Works
14-16 30 Tile Works
16-17 42 Installation of Glass Wall
17-18 20 Painting Works
18-19 2 Demobilization
Paths Days
1) 1-2-3-4-5-6-8-10-11-12-14-16-17-18-19 292
2) 1-2-3-4-5-6-8-10-11-13-15-16-17-18-19 301
3) 1-2-3-4-5-6-8-9-11-12-14-16-17-18-19 288
4) 1-2-3-4-5-6-8-9-11-13-15-16-17-18-19 297
5) 1-2-3-4-5-6-8-9-11-12-14-16-17-18-19 288
6) 1-2-3-4-5-6-8-9-11-13-15-16-17-18-19 297
7) 1-2-3-4-7-9-11-12-14-16-17-18-19 264
8) 1-2-3-4-7-9-11-13-15-16-17-18-19 273
9) 1-2-3-4-7-9-11-12-14-16-17-18-19 264
10) 1-2-3-4-7-9-11-13-15-16-17-18-19 273