COMPUTATIONS

FORWARD PASS COMPUTATION


FORMULA FOR FORWARD PASS:
EF = ES + D

ACTIVITY A
A-ES=0
EF=0+2=2

ACTIVITY A
B- ES=2
EF=2+4=6

ACTIVITY A
C- ES=6
EF=6+2=8

ACTIVITY A
D- ES=8
EF=8+12=20

ACTIVITY A
E- ES=8
EF=8+4=12

ACTIVITY A
F- ES=20
EF=20+3=23

ACTIVITY A
G- ES=23
EF=23+3=26

ACTIVITY A
H- ES=26
EF=26+2=28

ACTIVITY A
I- ES=28
EF=28+12=40

ACTIVITY A
J- ES=40
EF=40+4=44

ACTIVITY A
K- ES=44
EF=44+1=45

ACTIVITY A
L- ES=40
EF=40+2=42

ACTIVITY A
M- ES=45
EF=45+3=48

ACTIVITY A
N- ES=42
EF=42+10=52

ACTIVITY A
O- ES=52
EF=52+8=60

ACTIVITY A
P- ES=60
EF=60+2=62

ACTIVITY A
Q- ES=62
EF=62+8=70

ACTIVITY A
R- ES=62
EF=62+8=70
ACTIVITY A
S- ES=70
EF=70+10=80

ACTIVITY A
T- ES=80
EF=80+2=82

ACTIVITY A
U- ES=82
EF= 82+12=94

ACTIVITY A
V- ES= 94
EF= 94+2=96
BACKWARD PASS COMPUTATION
FORMULA FOR BACKWARD PASS:
LS = LF – D
FORMULA FOR FLOAT:
F = LF - EF
V-LF=96
LS=96-2=94
FLOAT FOR V
F=96 – 96 =0
U- LF=94
LS=94-12=82
FLOAT FOR U
F=94-94=0

T- LF=82
LS=94-2=92
FLOAT FOR T
F=94-82=12
S- LF=80
LS=80-10=70
F=80-80=0
R- LF=80
LS=80-8=72
F=80-70=10
Q- LF=70
LS=70-8=62
F=70-70=0
P- LF=62
LS=62-2=60
F=62-62=0
O- LF=60
LS=60-8=52
F=60-60=0
N- LF=52
LS=52-10=42
F=52-52=0
M- LF=60
LS=60-3=57
F=60-48=12
L- LF=42
LS=42-2=40
F=42-42=0
K- LF=52
LS=52-1=51
F=52-45=7
J- LF=51
LS=51-4=47
F=51-44=7
I- LF=40
LS=40-12=28
F=40-40=0
H- LF=28
LS=28-2=26
F=28-28=0
G- LF=26
LS=26-3=23
F=26-26=0
F- LF=23
LS=23-3=20
F=23-23=0
E- LF=20
LS=20-4=16
F=20-12=8
D- LF=20
LS=20-12=8
F=20-20=0
C- LF=8
LS=8-2=6
F=8-8=0
B- LF=6
LS=6-4=2
F=6-6=0
A- LF=2
LS=2-2=0
F=2-2=0

CRITICAL PATH
A,B,C,D,F,G,H,I,L,N,O,P, S, Q,U,V

PRECEDENCE TABLE
ACTIVITY DURATIO PREDECESSO
ACTIVITY DESCRIPTION
MARK N R
A MOBILIZATION 2
B PURCHASE OF MATERIALS 4 A
C SITE CLEARING AND GRADING 2 A,B
D LAY-OUT AND EXCAVATION 12 B,C
E PREPARATION OF FORMS AND REBARS 4 B,C
F CONCRETING OF FOOTINGS 3 D,E
G CONCRETING OF COLUMNS 3 E,F
H CONCRETING OF WALL FOOTINGS 2 E,F,G
I INSTALLATION OF CHB WALLSINTERIOR & EXTERIOR() 12 E,G,H
J ROUGHING-IN OF PLUMBING AND ELECTRICAL 4 G,I
K CONCRETING OF SLAB ON FILL 1 I,J
L CONCRETING OF ROOF BEAMS 2 G,I
M INSTALLATION DOOR JAMBS AND WINDOW FRAMES 3 I,J,K
N INSTALLATION OF ROOF FRAMING SYSTEMS AND ROOFING 10 I,L
O PLASTERING AND FLOOR TOPPING WORKS 8 I,K,N
P INSTALLATION OF DOORS AND WINDOWS 2 M,N,O
Q TILE WORKS 8 N,O,P
R CEILING WORKS (FRAMING & CEILING) 8 N,O,P
S CLOSET AND CABINET WORKS 10 N,O,P,Q
T INSTALLATION OF PLUMBING AND ELECTRICAL FIXTURES 2 O,Q,R,S
U PAINTING WORKS 12 N,O,P,Q,R,S,T
V CLEAN-UP AND DEMOBILIZATION 2 U