ACTI VI TY NORMAL TI ME CRASH TI ME AVAI LABLE DAYS COST PER DAY TO CRASH (Php)
A 8 8 0 -
B 12 10 2 6,000
C 7 6 1 2,000
D 6 2 4 6,000
E 9 7 2 4,500
F 4 2 2 7,000
Example 1.
STEP 2. Path A-B-F = 8 + 12 + 4 = 24 Days
Find the length of the Path C-D-E-F = 7 + 6 + 9 + 4 = 26 Days
activities in each
path.
Example 1.
STEP 3. Path A-B-F = 8 + 12 + 4 = 24 Days
Determine which Path C-D-E-F = 7 + 6 + 9 + 4 = 26 Days
activities are on the
critical path.
CRASH C 1 DAY
CRASH COST 1 X 2,000 2,000
THEREFORE CRASH C
Example 1. PATH DURATI ON ACTI VI TY AVAI LABLE DAYS COST PER DAY TO CRASH (Php)
STEP 5. A-B-F 24 A - NO REDUCTI ON
B 2 6,000
Continue crashing activities F 2 7,000
on the critical path until no
longer feasible.
C-D-E-F 25 C - NO REDUCTI ON
E 2 4,500
D 4 6,000
F 2 7,000
CRASH E 1 DAY
CRASH COST 1 X 4,500 4,500
THEREFORE CRASH E
PATH DURATI ON ACTI VI TY AVAI LABLE DAYS COST PER DAY TO CRASH (Php)
Example 1. A-B-F 24 A
B
F
-
2
2
NO REDUCTI ON
6,000
7,000
STEP 5.
C-D-E-F 24 C - NO REDUCTI ON
Continue crashing activities E 1 4,500
on the critical path until no D 4 6,000
longer feasible. F 2 7,000
CRASH E 1 DAY
CRASH COST 1 X 4,500 4,500
AND
CRASH B 1 DAY
CRASH COST 1 X 6,000 6,000
OR
CRASH F 1 DAY
CRASH COST 1 X 7,000 7,000
THEREFORE CRASH F
Example 1. PATH
A-B-F
DURATI ON ACTI VI TY AVAI LABLE DAYS COST PER DAY TO CRASH (Php)
23 A - NO REDUCTI ON
STEP 5. B 2 6,000
Continue crashing activities F 1 7,000
on the critical path until no
longer feasible. C-D-E-F 23 C - NO REDUCTI ON
E 1 4,500
D 4 6,000
F 1 7,000
CRASH F 1 DAY
CRASH COST 1 X 7,000 7,000
THEREFORE CRASH F
PATH DURATI ON ACTI VI TY AVAI LABLE DAYS COST PER DAY TO CRASH (Php)
Example 1. A-B-F 22 A
B
-
2
NO REDUCTI ON
6,000
STEP 5. F - NO REDUCTI ON
CRASH E 1 DAY
CRASH COST 1 X 4,500 4,500
AND
CRASH B 1 DAY
CRASH COST 1 X 6,000 6,000
PATH N=0 1 2 3 4
A-B-F 24 24 24 23 22
C-D-E-F 26 25 24 23 22
ACTI VI TY CRASHED C E F F
TOTALCRASHI NG COST 2,000 4,500 7,000 7,000
SAVI NGS 8,000 5,500 3,000 3,000
Example 2.
Given the following data,
can the project be finished
in 18 weeks instead of 33
weeks at a cost less than
Php 75,100 in direct cost?
TI ME COST
ACTI VI TY NORMAL TI ME CRASH TI ME NORMAL CRASH AVAI LABLE WEEKS COST PER WEEK TO CRASH (Php)
A 6 2 2,000 10,000 4 2,000
B 8 3 4,000 7,000 5 600
C 7 4 2,000 3,200 3 400
D 12 8 8,000 10,000 4 500
E 7 3 2,000 5,200 4 800
F 3 1 10,000 14,000 2 2,000
G 5 2 6,000 8,100 3 700
H 11 7 6,000 9,600 4 900
I 10 6 4,000 8,000 4 1,000
44,000 75,100