Professional Documents
Culture Documents
1. Kindly turn off your camera as this may add to the network bandwidth.
2. Kindly mute your microphone if you are not going to say something to
the class.
3. Please be careful of the words or language you use in the chatroom.
Do not use offensive or any foul language.
4. Please be considerate and polite to everybody in this conference.
MEETING 6:
1. Contractor’s “normal” calculated finish date in the planned schedule does not
meet the imposed finish date in the contract.
2. After starting construction and completing a certain percentage of the project,
the contractor realizes that the project is behind schedule.
3. Contractor may have a contractual monetary incentive to finish ahead of
schedule.
4. If the economy is doing well, finishing early means, to the contractor, starting
another project earlier and, thus, making more profit.
5. Accelerating a project may prove profitable to the contractor.
HOW CAN THE DURATION OF A PROJECT BE SHORTENED?
Revisit or study the schedule thoroughly to find any errors or unnecessary logic or constraints.
Fast-track the project -- Fast-tracking means starting construction before the design is completely
finished.
Conduct value engineering and constructability studies.
Value engineering (VE) - “an analysis and comparison of cost versus value of building materials,
equipment, and systems.
Constructability - “the optimum use of construction knowledge and experience in planning,
design, procurement, and field operations to achieve overall project objectives”
Utilizing Building Information Modeling (BIM).
Work overtime more hours per day and/or more days per week.
HOW CAN THE DURATION OF A PROJECT BE SHORTENED?
Labor
Materials
Equipment
Subcontractors
Other costs, such as government permits and fees, and fees for
lawyers and consultants hired for a specific task in a project
INDIRECT COSTS
1. Compute the crash cost per time period. For crash costs assumed linear over time:
(Crash cost Normal cost)
Crash cost per period
(Normal time Crash time )
3. If there is only one critical path, then select the activity on this critical path that
(a) can still be crashed,
(b) has the smallest crash cost per period.
Note that a single activity may be common to more than one critical path
A 500 1
Cheapest way to gain 1 wk
B 800 3
still is to cut A.
C 5,000 2
D 1,100 2
D8
TIME-COST EXAMPLE
B 800 2
Cheapest way to gain 1 wk
C 5,000 2 still is to cut B.
D 1,100 2
TIME-COST EXAMPLE D8
1) calculate the normal completion of the project, its cost, and the
critical path;
2) calculate and plot on a graphing paper the cost/time function for the
project and state:
• the minimum cost and the associated time;
• the shortest time and the associated cost.
EXAMPLE 2
$
EXAMPLE 2
EXAMPLE 2
Cost in $
$
13 days is the minimum completion
time for the project because no
further time reduction is available on
the critical path 1-2-5-6 (A-E-H).