Professional Documents
Culture Documents
Prepared By:
Tarek Assaf
200601390
Due Date: 17/12/2019
Page 1 of 18
LEBANESE AMERICAN
QBA 851 – Fall 2019
UNIVERSITY
Quantitative Methods in Business
Instructions
Page 2 of 18
1. (25 Points) The annual demand for an item is 20000 units and the ordering cost is
$200. The holding cost is $2 per unit per year and the unit purchasing cost is $10.
There are 250 working days per year.
a) Determine the optimal ordering Policy.
b) Determine the optimal order policy if the unit the lead time is 20 days.
c) Suppose that the current policy is to order exactly 2500 units each time an order is
placed. Find the annual savings if the optimal policy is adopted.
Solution:
D= 20000 units/year
Co = $200
Ch= $2/unit/year
C = $10/unit
(250 Day/year)
The optimal ordering policy is to order 2000 units every 25 days whenever the inventory
level reaches 0. This policy results in a minimum total inventory cost of $204,000 per
year, which is consisted of Unit costs of $200,000 and Total inventory of $4,000
(ordering cost 2,000 and holding cost 2,000)
Page 3 of 18
B) The POM-QM output is:
Interpretation:
T = Q/D = 2000/20000 = 1/10
T = 1/10*250 = 25
Time>Lead Time, 25>20
We have to place an order at R which is the re-order
Lead in years *D
20/250 * 20,000 = 1,600
Where the optimal ordering policy calls to order 2000 units every 20 (lead time) day
whenever the inventory level reaches 1600(L*D) units. The optimal policy results in a
minimum inventory cost of $204,000.
C)
Page 4 of 18
Q* = 2000, TCU (Q*) = 204,000
Q = 2500, TCU (2500) = CD + CoD/Q + Ch Q/2 =10*20,000 + 200*20,000/2500
+2*2500/2 = $ 204,100 more than $ 204,000
When the ordering quantity increases, the ordering cost decrease, holding cost increase,
the total cost will increase.
If we adopt the optimal policy, then we will save $204,100 – $204,000 = $ 100
2. (10 Points) The daily demand for a certain product is 400 units. The production rate is
1200 units per day and a cost of $1500 is incurred each time the machines are setup
Page 5 of 18
for production. The storage cost is $0.2 per item per day and the production cost is $5
per unit. Determine the optimal production policy quantity.
D=400 units/day
P= 1200 units/day
Co = $1500
Ch= $0.2/unit/day
C= $5/unit
Solution
The optimal production policy is to produce 3000 units every 7.5 days. This cost in a
maximum inventory of $ 2400 where the production cost per day is $2,000, with total
inventory cost is $400(annual setup cost $200 & annual holding cost $200).
3. (25 Points) Below are the data for a Time-Cost CPM Scheduling model analysis. The
time is in days and the costs include both direct and indirect costs.
Page 6 of 18
Immediate Normal Crash Normal Crash
Activity Predecessor Time Time Cost Cost
A None 3 2 $200 $400
B A 3 1 $300 $500
C B 5 3 $200 $300
D A 7 4 $200 $500
E C and D 2 1 $500 $900
a) Use the normal costs and durations to find the total duration of the entire
project, total cost, Earliest/Latest Start and Finish as well as the slack of of
each activity.
Solution:
The total duration of the project is 13 days and the total cost is $200+$300+$200+$200+
$500 = $ 1,400
The earliest and latest start date and the slack is shown in this table.
Page 7 of 18
b) Crash this project to reduce the total time to the minimum duration. Provide
the total duration and cost at each step.
Interpretation:
We can see that we have normal cost as $1,400 before crashing, so if we want to finish
the project faster and did all the crashing activities then we will pay $1,200 more so the
total cost is $1,400+ $1,200 = $2,600
Interpretation:
1st step we crash C. project time will be 12 days with cost = $1,400 + $50 = $1,450
2nd step we crash C & D. project time will be 11 days with cost = $1,450 + $150= $1,600
3rd step we crash B & D. project time will be 10 days with cost =$1,600 + $200 = $1,800
4th step we crash B & D. project time will be 9 days with cost = $1,800 + $200 = $2,000
Page 8 of 18
5th step we crash A. project time will be 8 days with cost = $2,000 + $200 = $2,200
6th step we crash E. project time will be 7 days with cost = $2,200 + $400 = $2,600
c) Find the schedule with the minimum total cost if the direct cost is $200/day.
Interpretation:
We will stop at schedule 6 (5th crash) because schedule 3,4,5,6 have the same total cost of
$3,800 but schedule 6 will make us finish the project in 8 days which is the fastest period.
Page 9 of 18
4. (25 Points) Libby Temple Manufacturing has three factories (X, Y, and W) and three
warehouses (A, B, and C). The following table shows the shipping costs between each
factory and warehouse, the factory manufacturing capabilities (in thousands of units),
and the warehouse capacities (in thousands of units).
A B C PRODUCTION
CAPACITY
X $6 $5 $3 6
Y $8 $10 $8 8
W $11 $14 $18 10
CAPACITY 7 12 5
Page 10 of 18
A) Find the starting solution using the North-West Corner method.
Page 11 of 18
Iteration 1
1st (-9) + (entering), 2nd (5)- (leaving), 3rd (5) +, 4th (7)-, 5th (1) +, 6th (6) –
Iteration 2
1st (-3) + (entering), 2nd (2)-, 3rd (6) +, 4th (1)- (leaving)
Iteration 3
1st (-1) + (entering), 2nd (7)- (leaving), 3rd (1) +, 4th (10)-
Page 12 of 18
B) Find the starting solution using the Least Cost method.
Source 1 (X)
Source 2(Y)
Source 3(W)
Destination 1(A)
Destination 2(B)
Destination 3(C)
Page 13 of 18
C) Repeat part (a) if the demand for warehouse B is now 14.
Page 14 of 18
Page 15 of 18
5. (15 Points) The Orange Top Cab company has a taxi waiting at each of four cab
stands in Evanston, Illinois. Four Customers have called and requested service.
The distances, in miles, from the waiting taxis to the customers are given in the
following table.
CUSTOMER
CAB SITE
A B C D
Stand 1 7 2 4 8
Stand 2 5 4 6 5
Stand 3 6 7 9 6
Stand 4 8 6 7 4
A)
Job 1 is Stand 1
Job 2 is Stand 2
Job 3 is Stand 3
Job 4 is Stand 4
Machine 1 is A
Machine 2 is B
Machine 3 is C
Machine 4 is D
Page 16 of 18
Assign 2 taxis for customers from point B to go to stand 1
Assign 6 taxis for customers from point C to go to stand 2
Assign 6 taxis for customers from point A to go to stand 3
Assign 4 taxis for customers from point D to go to stand 4
Page 17 of 18
B)
Thank you,
Tarek Assaf
Page 18 of 18