Professional Documents
Culture Documents
After Leveling
Before Leveling
15 10
8
10
6
4
5
2
0 0
Mon. 1 Mon. 2 Mon. 3 Mon. 4 Mon. 5 Mon. 1 Mon. 2 Mon. 3 Mon. 4 Mon. 5
A (3wks) 2000 $
B (2wks) 800$
Before Crashing
A (2wks) 3200 $
B (2wks) 800$
After Crashing
www.ProjacsAcademy.com 4
Crashing Case Study
5
The link between activity E and
activity H is a preferential relation
that could be removed
6
Resulting in shortening the
Project duration by 2 days
7
Activity B is the cheapest to crash on
The critical path. It will be crashed by
2 days
8
Activity C is the second cheapest
Activity to crash at US$ 1,200/Day.
It will be crashed by 3 days
9
When activity G which is the next
Activity to be crashed is crashed by
1 day, the whole network became
Critical.
10
To reach the final required date of Cost of crashing
August 26, 2006, both activities G and The project by 10
H had to be crashed each by 2 days. days
11
Project Time/Cost Curve
130,000
128,000
126,000
Project Cost
124,000
122,000
120,000
118,000
116,000
25 27 29 31 33 35 37
Project Duration (Working Days)
12
Crashing Example- 1
Duration, Days Costs, $
Activity Dependency Normal Crash Normal Crash
A --- 6 4 6000 8000
B A 4 3 5000 5750
C ---- 8 7 8000 8500
D B&C 6 5 6000 8000
Which activities would you crash if your project budget was only $27000? What is the
new project duration?
What is the cost for a full compression? What is the project duration in this case?
13
Ex. Normal Time & Cost
0 6 6 10
A B
du=6 du=4 ES EF
0 6 6 10
0 0 Key
start
LS LF
0 8 10 16 TF
C D
du=8 Finish
du=6
Normal:
2 10 10 16
0 Duration= 16 days
2 Cost= 25 000 $
14
Ex. Cost Slope – First run
Cost R
Duration, Days Costs, $
Slope A
N
Activity Dependency Normal Crash Normal Crash
K
A --- 6 4 6000 8000 1000 $/day 2
B A 4 3 5000 5750 750 $/day 1
C Non-
---- 8 7 8000 8500 500 $/day
Critical
D B&C 6 5 6000 8000 2000 $/day 3
15
Ex. First Compression
1 5 6 8
1 8 9 14
ES EF
C D
du=8 Finish
du=6
Key
1 8 9 14
0 0 LS LF
TF
Note: All activities are now critical and should be considered for further crashing
16
Ex. Cost Slope – 2nd run
R
Duration, Days Costs, $ Cost A
Slope N
Activity Dependency Normal Crash Normal Crash
K
One day
A --- 6 4 6000 8000 1000 $/day 2
remains
B A 4 3 5000 5750 750 $/day
Fully
C ---- Compressed
8 7 8000 8500 500 $/day 1
D B&C 6 5 6000 8000 2000 $/day 3
17
Ex. 2nd Compression
1 4 5 7
C D
du=7 Finish
du=6
1 7 8 13 ES EF
0 0
Key
LS LF
TF
18
Ex. Cost Slope – 3rd run
R
A
Duration, Days Costs, $ Cost
N
Activity Dependency Normal Crash Normal Crash Slope
K
A --- 6 4 6000 8000 1000 $/day
Fully Compressed
B A 4 3 5000 5750 750 $/day
Fully Compressed
C ---- 8 7 8000 8500 500 $/day
Fully Compressed
D B&C 6 5 6000 8000 2000 $/day 1
19
Ex. 3nd Compression
1 4 5 7
start
1 7 8 12
C D
Finish ES EF
du=7 du=5
Key
1 7 8 12
0 0 LS LF
TF
20
Crashing Example- 2
Activit Dependenc Duration Resource Duration Cost Cost
y y Normal Man Crash Normal Crash $
(day) Power (Day) ($)
(Ma-01)
21
answer
• TP = 23 days CP = 127000
• TP = 22days CP = 128500
• TP = 21days CP = 130000
• TP = 20days CP = 134000
• TP = 19days CP = 139000
140000
135000
130000
125000
120000
19 20 21 22 23
Crashing QUIZ
• Considering the below schedule, where P, Q and T are critical activities. In order
to shorten the project duration, which activity should be crashed first, assuming
cost is important:
Activity P
Activity Q
Activity R
Activity S
P 8 6 8000$ 10000$
Q 5 4 8000$ 8500$
R 6 3 9000$ 15500$
S 3 1 5000$ 5800$
T 3 2 5000$ 6500$
24
Schedule Compression:
Fast Tracking
Tools & Techniques:
-Schedule Compression
A (3wks) 2000 $
B (2wks) 800$
A (3wks) 2000 $
B (2wks) 800$
26
Case Study
• A Contractor is required to complete a
painting job in 30 days.
• The job has been divided into 8 zones for
which each would require one painter per day
to complete the work.
• The duration for each zone has been
estimated based on work to be done.
• The Contractor has a resource limit of two
painters per day (16 man-hours/day).
The Current Status
After Resource Leveling