The time and cost estimates of different activities of a project and their
precedence relationship are as given below:
B - 4 3 5000 8000
C A 3 2 4000 5000
D B 8 3 1000 6000
E B 14 6 9000 13000
F C, D 8 4 7000 8000
Overhead costs amount to Rs. 1,000 per week. It is stipulated that the
contractor will have to pay a penalty of Rs. 2,000 per week for completing
the project beyond 16 weeks.
Find out the cost slope for every activity using normal and crash data
for time and cost.