You are on page 1of 10

Engineering Project Management

Assignment 3
Final Year Project
Path Planning of the Autonomous Electric Vehicle
Fall 2021

Submitted by Reg No

Muhammad Arslan Amjad Qureshi 242979

Muhammad Hassan Ghafoor 242323

Muhammad Talha Saleem 262926

Muhammad Hashim 241808

Syndicate B

Supervisor: Dr Masood Raza

DEPARTMENT OF ELECTRICAL ENGINEERING

College of Electrical and Mechanical Engineering (CEME)

National University of Sciences and Technology (NUST)


Estimate Cost and Determine Budget
Immediate Duration Planned Earned Actual
Activity Description Predecessors (Weeks) Value Value Cost
(Rupees) (Rupees) (Rupees)
A Feasibility Study - 3 5000 4000 4200
B Estimate Project Cost - 3 2000 2200 2400
C Define Deliverables for FYP A 3 6000 6600 6300
D Create Schedule and Task Division B, C 4 1000 500 1000
E Raspberry Pi Implementation D 3 15000 10000 11000
F Graphical User Interface E 2 5000 6000 7000
G A-Star search Implementation E, F 3 1000 1500 2000
H Generation of Way Points G 2 3000 2000 1000
I Application of ROS H 5 300 500 1000
J Lane Changing Maneuvers H, I 4 8000 4000 4100
K Sending commands to Xavier I 1 500 200 100
L Trajectory Generation H 6 2500 1500 1000
M Localization L 1 3000 1000 1200
N Maneuver Parameters L 2 2300 1500 1800
O Path Optimizers L 3 2100 1000 1300
P CARLA Simulations N, K 3 1400 700 1000
Q UNREAL Engine AirSim N, K 4 1200 500 400
R MATLAB Simulations M 3 3500 500 300
S Project Showcase P, Q, S, J 6 5000 500 0
T Final Defense S 3 8000 1000 0

Note:-
1) Planned Value:- Planned value (PV) is the authorized budget
assigned to scheduled work. It is the authorized budget planned
for the work to be accomplished for an activity or work
breakdown structure (WBS) component, not including
management reserve.
2) Earned Value:- Earned value (EV) is a measure of work performed
expressed in terms of the budget authorized for that work.
3) Actual cost:- Actual cost is the realized cost incurred for the work
performed on an activity during a specific time period.
Variance Analysis

Immediate Duratio Planned Earned Actual Schedule Cost


Activit Description Predecesso n Value Value Cost Variance Varia
y rs (Weeks) (Rupees (Rupees (Rupees SV = EV – nce
) ) ) PV CV =
EV -
AC
A Feasibility Study - 3 5000 4000 4200 -1000 -200
B Estimate Project Cost - 3 2000 2200 2400 200 -200
C Define Deliverables for FYP A 3 6000 6600 6300 600 300
D Create Schedule and Task B, C 4 1000 500 1000 -500 -500
Division
E Raspberry Pi Implementation D 3 15000 10000 11000 -5000 -1000
F Graphical User Interface E 2 5000 6000 7000 1000 -1000
G A-Star search Implementation E, F 3 1000 1500 2000 500 -500
H Generation of Way Points G 2 3000 2000 1000 -1000 1000
I Application of ROS H 5 300 500 1000 200 -500
J Lane Changing Maneuvers H, I 4 8000 4000 4100 -4000 -100
K Sending commands to Xavier I 1 500 200 100 -300 100
L Trajectory Generation H 6 2500 1500 1000 -1000 500
M Localization L 1 3000 1000 1200 -2000 -200
N Maneuver Parameters L 2 2300 1500 1800 -800 -300
O Path Optimizers L 3 2100 1000 1300 -1100 -300
P CARLA Simulations N, K 3 1400 700 1000 -700 -300
Q UNREAL Engine AirSim N, K 4 1200 500 400 -700 100
R MATLAB Simulations M 3 3500 500 300 -3000 200
S Project Showcase P, Q, S, J 6 5000 500 0 -4500 500
T Final Defense S 3 8000 1000 0 -7000 1000

Note: - If schedule variance negative that means the less work is


completed than planned so your project is behind schedule. If
schedule variance is positive that means more work is
completed than planned so your project is ahead of schedule
and if schedule variance is zero so your project is right on
schedule.
Performance Index
Immediat Durati PV EV AC SV CV SPI CPI
Activi Description e on
ty Predecess (Week
ors s)
A Feasibility Study - 3 5000 4000 4200 -1000 -200 0.8 0.95
B Estimate Project Cost - 3 2000 2200 2400 200 -200 1.1 0.92
C Define Deliverables for FYP A 3 6000 6600 6300 600 300 1.1 1.05
D Create Schedule and Task B, C 4 1000 500 1000 -500 -500 0.5 0.5
Division
E Raspberry Pi D 3 15000 10000 11000 -5000 - 0.66 0.91
Implementation 1000
F Graphical User Interface E 2 5000 6000 7000 1000 - 1.2 0.86
1000
G A-Star search E, F 3 1000 1500 2000 500 -500 1.5 0.75
Implementation
H Generation of Way Points G 2 3000 2000 1000 -1000 1000 0.66 2
I Application of ROS H 5 300 500 1000 200 -500 1.67 0.5
J Lane Changing Maneuvers H, I 4 8000 4000 4100 -4000 -100 0.5 0.97
K Sending commands to I 1 500 200 100 -300 100 0.4 2
Xavier
L Trajectory Generation H 6 2500 1500 1000 -1000 500 0.6 1.5
M Localization L 1 3000 1000 1200 -2000 -200 0.33 0.83
N Maneuver Parameters L 2 2300 1500 1800 -800 -300 0.65 0.83
O Path Optimizers L 3 2100 1000 1300 -1100 -300 0.47 0.77
P CARLA Simulations N, K 3 1400 700 1000 -700 -300 0.5 0.7
Q UNREAL Engine AirSim N, K 4 1200 500 400 -700 100 0.41 1.25
R MATLAB Simulations M 3 3500 500 300 -3000 200 0.14 1.67
S Project Showcase P, Q, S, J 6 5000 500 0 -4500 500 0.1 NC
T Final Defense S 3 8000 1000 0 -7000 1000 0.12 NC

Note: - SPI stands Schedule Performance Index, measures how close the project is
to planned completion to date. SPI is calculated as
SPI = EV/PV
If SPI is greater than one, the project is progressing well versus the schedule. if SPI
is equal to one, the project is on schedule as planned. If SPI is less than one, the
project is behind schedule.
CPI stands for Cost Performance Index; it is the measure of conformance of the
actual work completed (measured by its earned value) to the actual cost incurred.
CPI is calculated as
CPI = EV/AC
When CPI is greater than one, this indicates better-than-planned project
performance. When CPI is less than one, that indicates poorer-than-planned
project performance and when CPI is equal to one, it indicates performance is on
target.
Budget at Completion (BAC)
BAC = sum of all 100% planned values.
BAC = 75,800 Rs
This will be the amount that was supposed to complete our project on schedule.
Estimate at Completion (EAC)
EAC = sum of all actual cost + bottom up ETC (Estimate to Completion)
Sum of All Actual Cost = 45,100
Estimate time at completion approximation

Immediat Durati PV EV AC SV CV ETC


Activi Description e on
ty Predecess (Week
ors s)
A Feasibility Study - 3 5000 4000 4200 -1000 -200 1200
B Estimate Project Cost - 3 2000 2200 2400 200 -200 0
C Define Deliverables for FYP A 3 6000 6600 6300 600 300 0
D Create Schedule and Task B, C 4 1000 500 1000 -500 -500 600
Division
E Raspberry Pi D 3 15000 10000 11000 -5000 - 6000
Implementation 1000
F Graphical User Interface E 2 5000 6000 7000 1000 - 0
1000
G A-Star search E, F 3 1000 1500 2000 500 -500 0
Implementation
H Generation of Way Points G 2 3000 2000 1000 -1000 1000 600
I Application of ROS H 5 300 500 1000 200 -500 0
J Lane Changing Maneuvers H, I 4 8000 4000 4100 -4000 -100 5000
K Sending commands to I 1 500 200 100 -300 100 500
Xavier
L Trajectory Generation H 6 2500 1500 1000 -1000 500 800
M Localization L 1 3000 1000 1200 -2000 -200 1800
N Maneuver Parameters L 2 2300 1500 1800 -800 -300 1000
O Path Optimizers L 3 2100 1000 1300 -1100 -300 1200
P CARLA Simulations N, K 3 1400 700 1000 -700 -300 1000
Q UNREAL Engine AirSim N, K 4 1200 500 400 -700 100 900
R MATLAB Simulations M 3 3500 500 300 -3000 200 3200
S Project Showcase P, Q, S, J 6 5000 500 0 -4500 500 5000
T Final Defense S 3 8000 1000 0 -7000 1000 7000

Note: - In Estimate to completion we suppose the actual cost


that would be required to accomplish remaining the work, this
ETC will be known as bottom up because it will eventually be
added to original actual cost to formulate estimate at
completion (EAC).
EAC = sum of all actual cost + bottom up ETC (Estimate to Completion)
Sum of All Actual Cost = 45,100
Sum of All ETC = 35,800
 EAC = 45,100 + 35,800 = 80,900
 EAC – BAC = 80900 – 75800 = 5100 Rupees
Note:- 5100 more Rupees would be used to complete our Final
year Project on Path Planning of the Autonomous Electric
Vehicle.
Note:- Our Final Year Project(FYP) is still in progress and still
this far we have left with some work to do, so we took the help
of ETC(Estimate to Completion) to find the Estimate at
Completion(EAC).
Trend Analysis
1) Planned Value:-
2) Earned Value:-

3)Actual Cost:-
4)Budget at Completion(BAC):-

5)Estimate at Completion(EAC):-
Conclusion:-
In this Assignment, we analyzed our Final Year Project for the Cost
Management Plan. We computed all the values including Planned
Values, Earned Values, Actual Costs , Budget at Completion(BAC),
Estimation at Completion(EAC), Estimate to Completion(ETC) and
the Budget offset which in our case comes to be 5100 Rupees.

You might also like