Activity Predecessor Duration Cost/Day Total Cost A

A - 2 300 600 B
B A 3 400 1200
C
C B 3 400 1200
D B 2 200 400 D

E D 3 100 300 E
0 1 2 3 4 5 6 7 8 9 10
Field report at the end of 7 days
Activity ACWP BCWP BCWS CPI CV SPI SV
Activity Actual % Completion Incurred cost
A 600 600 600
A 100 600
B 1400 1200 1200
B 100 1400
C 500 400 800
C 33 500
D 200 200 400
D 50 200
E 0 0 0
E 0 0
Total to date 2700 2400 3000 0.88 -300 0.8 -600

CPI = BCWP/ACWP SPI = BCWP/BCWS


CV = BCWP - ACWP SV = BCWP - BCWS