Professional Documents
Culture Documents
2. On day 51 a project has an earned value of $600, an actual cost of $650, and a
planned cost of $560. Compute the SV, CV, and CPI for the project. What is
your assessment of the project on day 51?
3. Given the project network and baseline information below, complete the form to
develop a status report for the project at the end of period 4 and the end of
period 8. From the data you have collected and computed for periods 4 and 8,
what information are you prepared to tell the customer about the status of the
project at the end of period 8?
The project appears to be doing nicely. In both periods 4 and 8 the cost variance is
positive—+$300 and +$400, respectively. This suggests a pattern of good cost
variance that is under budget.
The schedule variance is also positive—+$300 and +$400 for period 4 and period 8.
Since Task D is already 25% complete, Task B must have been completed at least one
period early.
End of Period 4
Actual % EV AC PV CV SV
Task
Complete $ $ $ $ $
A Finished 400 300 400 +100 0
B 50% 1200 1000 800 +200 +400
C 33% 500 500 600 0 -100
D 0% 0 0 0 0 0
E 0% 0 0 0 0 0
Cumulative Totals $2100 $1800 $1800 $+300 $+300
End of Period 8
Actual % EV AC PV CV SV
Task
Complete $ $ $ $ $
A Finished 400 300 400 +100 0
B Finished 2400 2200 2400 +200 0
C Finished 1500 1500 1500 0 0
D 25% 400 300 0 +100 +400
E 33% 300 300 300 0 0
F 0% 0 0 0 0 0
Cumulative Totals $5000 $4600 $4600 $+400 $+400
Note: Completion of the answer sheet requires constant reference to the baseline
figure.
4. Given the following project network, baseline, and status information, develop
status reports for periods 2,4,6,8 and complete the performance indices table.
Calculate the EACf and the VACf . Based on your data, what is your assessment of
the current status of the project? At completion?
The project is performing nicely in terms of cost. The project is currently 23 (000) under
budget and is getting $1.18 worth of work for each dollar spent. In terms of the schedule,
the SV indicates that there is $4 (000) worth of work that was supposed to have been
done by the 8th period that has not been done. This work concerns activity D which is
only 33% complete instead of the planned 55% complete. Since D is a critical activity
the project is behind schedule. The project is 75 percent complete.
In terms the future, if the project continues to earn 1.18 for each dollar spent the
forecasted cost at completion would be 175 (000). The project would therefore be
forecasted to come in 31 (000) under budget. However this may change since the project
has incurred a significant cost over-run so far for activity D which is only 33% complete.
If this pattern continues savings earned on other activities could be quickly absorbed and
the project would not come in under budget. Management needs to investigate Activity
D and take corrective action if possible. Assuming that there is no positive change in
Activity D the project will be completed 1-2 time units late.
Legend
4 C 8
2 2 ES ID EF
0 A 4
6 4 10 SL SL
1 1
LS DURLF
1 4 5
5 D 10 10 F 12
0 0 0 0
5 5 10 10 2 12
0 B 5
0 0 5 E 8
0 5 5 2 2
7 3 10
Tas % Complete EV AC SV
k PV CV
A 75% 30 25 20 5 10
B 50% 16 12 12 4 4
Cumulative Totals 46 37 32 9 14
Tas % Complete EV AC SV
k PV CV
A 100% 40 35 40 5 0
B 100% 32 24 24 8 8
Cumulative Totals 72 59 64 13 8
Status Report: Ending Period 6
Tas % Complete EV AC SV
k PV CV
A 100% 40 35 40 5 0
B 100% 32 24 32 8 0
C 75% 36 24 24 10 12
D 0% 0 0 6 0 -6
E 50% 14 10 8 4 6
Cumulative Totals 93 110 27 12
Tas % Complete EV AC SV
k PV CV
A 100% 40 35 40 5 0
B 100% 32 24 32 8 0
C 100% 48 32 48 16 0
D 33% 6 20 10 -14 -4
E 100% 28 20 28 8 0
Cumulative Totals 93 158 23 -4
(BAC −EV )
EAC f = + AC
( EV / AC )
(206−154 )
¿ +131
(154 /131 )
¿ 175
VACf = 31
5. Given the following project network, baseline, and status information, develop
status reports for periods 1-4 and complete the project summary graph (or a
similar one). Report the final SV, CV, CPI and PCIB. Based on your data, what
is your assessment of the current status of the project? At completion?
After 4 time periods the project is roughly 77% (PCIB) complete and is current
getting only 83 cents worth of work for each dollar spent. The project is currently
$10,000 over budget. There is $3,000 worth of work on critical Activity 5 that has
not been completed as planned so the project is behind schedule. Since so much of
the project has been completed the project is expected to come in over budget. The
forecast cost at completion is $78,000 which is $13,000 over budget. Whether the
project will be completed on schedule will depend upon whether Activity 5 can make
up for lost time.
Status Report: Ending Period 1 ($000)
Task % Complete EV AC PV CV SV
1 50% 6 6 4 0 +2
2 40% 6 8 3 -2 +3
3 25% 2 3 4 -1 -2
Cumulative Totals 14 17 11 -3 +3
Status Report: Ending Period 2 ($000)
Task % Complete EV AC PV CV SV
1 Finished 12 13 12 -1 0
2 80% 12 14 10 -2 +2
3 75% 6 8 8 -2 -2
Cumulative Totals 30 35 30 -5 0
After 6 time periods the project is roughly 66% complete and so far work on the
project has taken 1,600 hours less work than planned. There is 400 hours worth of
work on Activity 4 which was suppose to have been done that has not done. Since
Activity 4 is on the critical path, the project is behind schedule. If schedule is the
number priority, the project manager may want to consider investing some of the
savings on accelerating critical activities.
Status Report: Ending Period 1
Task % Complete EV AC PV CV SV
1 50% 1000 500 1000 +500 0
Cumulative Totals 1000 500 1000 +500 0
( BAC−EV )
EAC f = + AC
( EV / AC ) VACf = BAC - EACf
(2000−1300)
= +1400
(1330 /1400 )
=2105
With two-thirds of the project completed the forecast is that the project will be
$105,000 over budget at completion
Part B. You have met with your Aurora project team and they have provided you with
the following revised estimates for the remainder of the project:
Revised Estimates indicate that the project will be one month behind schedule and
$150,000 over budget
Choosing between the VACf or the VACre depends upon how much confidence you have
in the accuracy of the revised estimates. Since both activities F and G are underway, one
should be inclined to go with in this case the more conservative VACre.