Activities Normal Time Crash Time Normal Cost Crash Cost Imm.

Predec
(weeks)
A 4 3 2000 2600 --
B 2 1 2200 2800 --
C 3 3 500 500 --
D 8 4 2300 2600 A
E 6 3 900 1200 B
F 3 2 3000 4200 C
G 4 2 1400 2000 D,E

1. What is the project completion time?


2. What is the cost required for completing the project?
3. If we want to reduce the completion date by one week, what activity should we choose
to crash?
4. What is the maximum time that can be crashed and how much would cost increase?
Activity Pred. Time estimates (days) Crash
Opt. Most Likely Pess. cost/day
A -- 20 30 40 1500
B A 20 65 80 3500
C A 50 60 100 4000
D C 30 50 100 1900
E B 25 30 35 9500
F E .1 .1 .1 0
G D,F 25 30 35 2500
H G 10 20 30 2000
I H 20 25 60 2000
J H 8 10 12 6000
K J .1 .1 .1 0
L I,K 20 25 60 4500
1. How long does it take to complete the project?
2. What is the probability of finishing in 270 days?
3. If it is necessary to crash to 250 or 240 days, what is the cost to increase? Assuming that
the optimistic time can be used as crash time.