The Network diagram for the project , along with activity time ,is
The critical path in the network diagram has been shown. This has been done by double lines by
joining all those events where E-values and L-values are equal.
The critical path of the project is : 1-3-6 and critical activities are B,E
3000−2000
B (1 - 3) =200
15−10
2600−1800
C (2 - 4) =400
8−6
5300−4500
D (2 - 5) =200
20−16
9600−7200
E (3 - 6) =240
30−10
6000−5000
F (4 - 5) =500
14−12
4500−3300
G (5 - 6) =400
12−9
The critical activity B with cost slope of Rs 200 per week, is the least expensive and can be
crashed by 5 weeks
The critical path in the network diagram has been shown. This has been done by double lines by
joining all those events where E-values and L-values are equal.
The critical path of the project is : 1-2-4-5-6 and critical activities are A,C,F,G
The total project time is 44
The network diagram for the project, along with E-values and L-values, is
Since total project cost for 44 weeks is more than the cost for 45 weeks. So further crashing is
not desirable.
Hence, project optimum time is 45 weeks and cost is 24800.
Refrences
https://atozmath.com