Professional Documents
Culture Documents
Cost Slope= The extra cost which is required to reduce an activity by one day.
Cost Slope =[Crash cost – Normal cost]/[Normal Duration – Crash Duration]
6
G(5)
F(7)
A(5) C(7
2 4 5
1 E(6)
B(8) (6) (3)
D(8)
(6)
3
Path Activities Normal 1st crash( B 2nd Crash E 3rd Crash D
Duration by two by 3 days by 2 days
days)
Path 1 A—C--G 17 17 17 17
Path 2 B—D--G 21 19 19 17
Path 3 B—D—E--F 29 27 24 22
Path 4 A—C—E--F 25 25 22 22
Formulation of LPP
Objective Function
Maximize Profit(Z)= 60p+40q
Subject to the constraints
Raw material X 20p+12q<=2000
Raw Material Y 10p+12q<= 1200
Non negativity constraint
p,q>= 0
There are two methods of solving LPP
1. Graphical Method ( if the number of variable is 2)
2. Simplex Method