Professional Documents
Culture Documents
انمطهوب حساب مذة انمشروع انخي ححقق اقم كهفت أجمانيت ممكنت
باسخخذاو حقنيت انـ ) (Crashingأرا كانج انكهف انغير انمباشرة (5000 $/week= )Indirect Cost
3 8
B 5
5 10
0 3 3 8 8 10 10 13
A 3 C 5 E 2 F 3
0 3 3 8 8 10 10 13
3 7
D 4
4 8
2- crash E by 1 weeks Act. ΔT CS
Project Time = 12 weeks A 1 2000
Direct Cost = 62000+1(1500) = 63500 C 2 3000
E 0 1500
Indirect Cost = 12 x 5000 = 60000
F 2 3000
Total Cost = 123500
3 8
B 5
4 9
0 3 3 8 8 9 9 12
A 3 C 5 E 1 F 3
0 3 3 8 8 9 9 12
3 7
D 4
4 8
3- crash A by 1 weeks Act. ΔT CS
Project Time = 11 weeks A 0 2000
Direct Cost = 63500+1(2000) = 65500 C 2 3000
E 0 1500
Indirect Cost = 11 × 5000 = 55000
F 2 3000
Total Cost = 120500
2 7
B 5
3 8
0 2 2 7 7 8 8 11
A 2 C 5 E 1 F 3
0 2 2 7 7 8 8 11
2 6
D 4
3 7
4- crash F by 2 weeks Act. ΔT CS
Project Time = 9 weeks A 0 2000
C 2 3000
Direct Cost = 65500+2(3000) = 71500
E 0 1500
Indirect Cost = 9 × 5000 = 45000 F 0 3000
Total Cost = 116500
2 7
B 5
3 8
0 2 2 7 7 8 8 9
A 2 C 5 E 1 F 1
0 2 2 7 7 8 8 9
2 6
D 4
3 7
5- crash C by 1 weeks Act. ΔT CS
Project Time = 8 weeks A 0 2000
C 1 3000
Direct Cost = 71500+1(3000) = 74500
E 0 1500
Indirect Cost = 8 × 5000 = 40000 F 0 3000
Total Cost = 114500 <116500 OK B 1 1500
D 2 1000
2 7
B 5
2 7
0 2 2 6 6 7 7 8
A 2 C 4 E 1 F 1
0 2 2 6 6 7 7 8
2 6
D 4
2 6
6- crash B, C & D by 1 weeks Act. ΔT CS
Project Time = 7 weeks A 0 2000
Direct Cost = 74500+1(1500)+1(3000)+1(1000) = 80000
C 0 3000
E 0 1500
Indirect Cost = 7 × 5000 = 35000 F 0 3000
Total Cost = 115000 >114500 NOT OK B 0 1500
D 1 1000
2 6
B 4
2 6
0 2 2 5 5 6 6 7
A 2 C 3 E 1 F 1
0 2 2 5 5 6 6 7
2 5
D 3
2 5
Since the new TC (total cost) is greater than previous TC, stop the iteration.
The previous iteration (No. 5) solution is the best for implementation.
Therefore, the final crashed project completion time is 8 weeks and the TC is 114,500$