‫مثال‪ :2-‬من انمعهوماث أدناه انخاصت بأحذ انمشاريع‪ .

‬انمطهوب حساب مذة انمشروع انخي ححقق اقم كهفت أجمانيت ممكنت‬
‫باسخخذاو حقنيت انـ )‪ (Crashing‬أرا كانج انكهف انغير انمباشرة (‪5000 $/week= )Indirect Cost‬‬

‫‪Normal‬‬ ‫‪Crash‬‬ ‫‪ΔT‬‬ ‫‪ΔC‬‬ ‫‪Cost Slope‬‬


‫‪Preceded‬‬
‫‪Act.‬‬ ‫‪Time‬‬ ‫‪Cost‬‬ ‫‪Time‬‬ ‫‪Cost‬‬ ‫‪= ΔT/ΔC‬‬
‫‪by‬‬
‫)‪(Weeks‬‬ ‫)‪($‬‬ ‫)‪(Weeks‬‬ ‫)‪($‬‬
‫*‪A‬‬ ‫‪Start‬‬ ‫‪3‬‬ ‫‪6000‬‬ ‫‪2‬‬ ‫‪8000‬‬ ‫‪1‬‬ ‫‪2000‬‬ ‫‪2000‬‬
‫‪B‬‬ ‫‪A‬‬ ‫‪5‬‬ ‫‪12000‬‬ ‫‪4‬‬ ‫‪13500‬‬ ‫‪1‬‬ ‫‪1500‬‬ ‫‪1500‬‬
‫*‪C‬‬ ‫‪A‬‬ ‫‪5‬‬ ‫‪16000‬‬ ‫‪3‬‬ ‫‪22000‬‬ ‫‪2‬‬ ‫‪6000‬‬ ‫‪3000‬‬
‫‪D‬‬ ‫‪A‬‬ ‫‪4‬‬ ‫‪8000‬‬ ‫‪2‬‬ ‫‪10000‬‬ ‫‪2‬‬ ‫‪2000‬‬ ‫‪1000‬‬
‫*‪E‬‬ ‫‪C&D‬‬ ‫‪2‬‬ ‫‪6000‬‬ ‫‪1‬‬ ‫‪7500‬‬ ‫‪1‬‬ ‫‪1500‬‬ ‫‪1500‬‬
‫*‪F‬‬ ‫‪B&E‬‬ ‫‪3‬‬ ‫‪14000‬‬ ‫‪1‬‬ ‫‪20000‬‬ ‫‪2‬‬ ‫‪6000‬‬ ‫‪3000‬‬
‫‪Direct Cost $62000‬‬
1- Project without Crashing:
Critical Path is A-C-E-F
Act. ΔT CS
A 1 2000
Project Time = 13 weeks C 2 3000
Direct Cost = 62000 E 1 1500
Indirect Cost = 13 x 5000 = 65000 F 2 3000
Total Cost = 127000

3 8
B 5
5 10
0 3 3 8 8 10 10 13
A 3 C 5 E 2 F 3
0 3 3 8 8 10 10 13
3 7
D 4
4 8
2- crash E by 1 weeks Act. ΔT CS
Project Time = 12 weeks A 1 2000
Direct Cost = 62000+1(1500) = 63500 C 2 3000
E 0 1500
Indirect Cost = 12 x 5000 = 60000
F 2 3000
Total Cost = 123500

3 8
B 5
4 9

0 3 3 8 8 9 9 12
A 3 C 5 E 1 F 3
0 3 3 8 8 9 9 12

3 7
D 4
4 8
3- crash A by 1 weeks Act. ΔT CS
Project Time = 11 weeks A 0 2000
Direct Cost = 63500+1(2000) = 65500 C 2 3000
E 0 1500
Indirect Cost = 11 × 5000 = 55000
F 2 3000
Total Cost = 120500

2 7
B 5
3 8
0 2 2 7 7 8 8 11
A 2 C 5 E 1 F 3
0 2 2 7 7 8 8 11
2 6
D 4
3 7
4- crash F by 2 weeks Act. ΔT CS
Project Time = 9 weeks A 0 2000
C 2 3000
Direct Cost = 65500+2(3000) = 71500
E 0 1500
Indirect Cost = 9 × 5000 = 45000 F 0 3000
Total Cost = 116500

2 7
B 5
3 8
0 2 2 7 7 8 8 9
A 2 C 5 E 1 F 1
0 2 2 7 7 8 8 9
2 6
D 4
3 7
5- crash C by 1 weeks Act. ΔT CS
Project Time = 8 weeks A 0 2000
C 1 3000
Direct Cost = 71500+1(3000) = 74500
E 0 1500
Indirect Cost = 8 × 5000 = 40000 F 0 3000
Total Cost = 114500 <116500 OK B 1 1500
D 2 1000

2 7
B 5
2 7
0 2 2 6 6 7 7 8
A 2 C 4 E 1 F 1
0 2 2 6 6 7 7 8
2 6
D 4
2 6
6- crash B, C & D by 1 weeks Act. ΔT CS
Project Time = 7 weeks A 0 2000
Direct Cost = 74500+1(1500)+1(3000)+1(1000) = 80000
C 0 3000
E 0 1500
Indirect Cost = 7 × 5000 = 35000 F 0 3000
Total Cost = 115000 >114500 NOT OK B 0 1500
D 1 1000
2 6
B 4
2 6
0 2 2 5 5 6 6 7
A 2 C 3 E 1 F 1
0 2 2 5 5 6 6 7
2 5
D 3
2 5
 Since the new TC (total cost) is greater than previous TC, stop the iteration.
 The previous iteration (No. 5) solution is the best for implementation.
 Therefore, the final crashed project completion time is 8 weeks and the TC is 114,500$