Coleman
PROJECT NETWORK
ACTIVITY SCHEDULE
At 40 ≤ T ≤ 43
➔ With the given calculations, we can conclude that there is about a 10.38% chance that
the project can be completed in 40 weeks or less which means that the 40-week
completion time cannot be achieved. It is recommended for Coleman to consider
crashing project activities, even if it’s a low chance.
s.t.
Activity Crashing decision:
The additional cost for a project goal of 38weeks is $2250
Paths:
B – C – E – F – H – J – K = 43 A – C – G – H – J – K = 32
A – C – D – I – K = 33 B – C – D – I – K = 36
A – C – D – H – J – K = 36 B – C – D – H – J – K = 39
A – C – E – F – I – K = 37 B – C – E – F – I – K = 40
A – C – E – F – H – J – K = 40 B – C – G – H – J – K = 35
APPENDICES
Potential Paths:
➔ A-C-D-I-K = 6 + 4+ 12 + 7 + 4 = 33
➔ A-C-D-H-J-K = 6 + 4 + 12 + 6 + 4 +4 = 36
➔ A-C-E-F-I-K = 6 + 4 + 10 +6 + 7 + 4 = 37
➔ A-C-E-F-H-J-K = 6 + 4 + 10 +6 + 6 + 4 + 4 = 40
➔ A-C-G-H-J-K = 6 + 4 + 8 + 6 +4 + 4 = 32
➔ B-C-D-I-K = 9 + 4 + 12 + 7 + 4 = 36
➔ B-C-D-H-J-K = 9 + 4 + 12 + 6 + 4 + 4 = 39
➔ B-C-E-F-I-K = 9 + 4 + 10 + 6 + 7 + 4 = 40
➔ B-C-E-F-H-J-K = 9 + 4 + 10 + 6 + 6 + 4 + 4 = 43
➔ B-C-G-H-J-K =9+4+8+6+4+4 = 35
The Critical Path: B – C – E – F – H – J – K
The Expected Project Completion Time: 43 weeks
The Variance of the Critical Path (σ²) = 5.67
Standard Deviation (σ): = 2.38
Using the information given in the question, it can be observed that the
probability that the work will be completed within 40 weeks is 80%.
= 40 - (0.841621 x 2.38)
= 37.61821257 or 38 days
3.
Activity Time Reduction Crashed per week
A M i=¿ 6 - 4 = 2 1900−1000
k i=
2
= 900 / 2
= 450
B M i=¿ 9 - 7 = 2 1800−1000
k i=
2
= 800 / 2
= 400
C M i=¿ 4 - 2 = 2 2700−1500
k i=
2
= 1200 / 2
= 600
D M i=¿ 12 - 8 = 4 3200−2000
k i=
4
= 1200 / 4
= 300
E M i=¿ 10 - 7 = 3 8000−5000
k i=
3
= 3000 / 3
= 1000
F M i=¿ 6 - 4 = 2 4100−3000
k i=
2
= 1100 / 2
= 550
G M i=¿ 8 - 5 = 3 10250−8000
k i=
3
= 2250 / 3
= 750
H M i=¿ 6 - 4 = 2 6400−5000
k i=
2
= 1400 / 2
= 700
I M i=¿ 7 - 4 = 3 12400−10000
k i=
3
= 2400 / 3
= 800
J M i=¿ 4 - 3 = 1 4400−4000
k i=
1
= 400
K M i=¿ 4 - 3 = 1 5500−5000
k i=
2
= 500
A 6 0
B 7 2 800
C 4 0
D 12 0
E 10 0
F 5 1 550
G 8 0
H 6 0
I 7 0
J 3 1 400
K 3 1 500
7 – 4 – 10 – 6 – 6 – 4 – 4 = 41
7 – 4 – 10 – 6 – 6 – 3 – 4 = 40
7 – 4 – 10 – 6 – 6 – 3 – 3 = 39
7 – 4 – 10 – 5 – 6 – 3 – 3 = 38