Professional Documents
Culture Documents
1. The table below provide information on activities, predecessors, normal duration, normal cost, crash duration,
and crash cost for a project.
A - 50 50.000 35 72.500
B A 40 60.000 35 70.000
C A 20 45.000 10 55.000
D B 50 65.000 40 72.500
E C 60 85.000 45 115.000
a. Draw a network diagram from the preceding information, then define the critical path !
b. Calculate cost slope for each activity !
c. Use the information contained above to compress one time unit per move using the least cost method.
Reduce the schedule until you reach the crash point of the network.
For each move identify what activity(s) was crashed, the adjusted total cost, and explain your choice if
you have to choose between activities that cost the same.
d. Draw a project cost-duration graph !
e. What is the optimum cost-time schedule for the project ?