Find total project cmpletion time and activity slack time using CPM method.

Activity Predecessor Duration


A 5
B A 4
C A 5
D B 6
E C 3
F D,E 4

0 A 5 5 C
0 5 5 7 5

5 B
5 4
C E
A F ACEF 17
B D ABDF 19
PROJECT COMPLETION TIME 19 DAYS
Es Activity Ef
Ls Duration Lf FORWARD PASS MOETHOD
BACKGROUND PASS METHO

10 10 E 13
12 12 3 15 15 F 19
4 19
9 9 D 15
9 9 6 15

CRITICAL PATH ABDF


ON TIME 19 DAYS
Calculate total project coompetion time using PER

a m b ET
A 10 22 28 21
B 4 4 10 5
C 4 6 14 7
D 1 2 3 2
E 1 5 9 5
F 7 8 9 8
G 2 2 2 2

Activity Predecessor
A
B
C
A
A 𝜎^2= ((𝑏
D B 2
E
F
C,D
C,D −𝑎)/6)
G E,F
ct coompetion time using PERT, also find out what is the probability of project getting complete in 35 weeks.

E.T.= (a+4m+b)/6

𝜎^2= ((𝑏
2
−𝑎)/6)
Crash

NT CT NC CC Slope (cost/d
A 2 1 6 10 4
B A 5 2 9 18 3
C A 4 3 6 8 2
D B,C 3 1 5 9 2
Crash Limit
1
3
1
2
Find critical Path and estim
Required Time Cost To shorten the Project by 3
Preceding
Activity activity NT CT NC CC
A 4 2 10000 11000
B A 3 2 6000 9000
C A 2 1 4000 6000
D B 5 3 14000 18000
E B,C 1 1 9000 9000
F C 3 2 7000 8000
G E,F 4 2 13000 25000
H D,E 4 1 11000 18000
I H,G 6 5 20000 29000
94000
Find critical Path and estimated completion time
To shorten the Project by 3 week, which task would be shortend and what would the final total projet cost
Activity PredecessoDuration
A None 4
B A 6
C A 3
D B 6
E D 14
F C 5
G E,F 2 A
H G 2
I G 3
J H,I 4
K J 2

B
A 6
4
C
3
B D E H
G J K
C F I

10 D 16 E 30
6 14

F
5
H
G 2
2
J
I 4
3
K
2
Activity PredecessoOT MLT PT
A None 2 4 6
B A 3 7 10
C A 2 3 5
D B 4 7 9
E D 12 16 20
F C 2 5 8
G E,F 2 2 2
H G 2 3 4
I G 2 3 5
J H,I 2 4 6
K J 2 2 2