1)

Activity A B C D E F G H I J K L M
Procedure - - B C A,D D A,D E G,H I G J,K L
Duration 6 5 2 2 2 1 6 5 6 2 4 3 1
(a) Draw a network diagram for this project.
(b) Find the critical path and duration of the project.
(c) Find the total, free and independent floats of various activities.

2) Find Critical path and floats of the project.


Activity A B C D E F G H I J K
Predecessors - A B C B E D,F E H G,I J
Time 13 8 10 9 11 10 8 6 7 14 18

3) Consider following project and derive critical path for it, also find total floats of project.
Activity A B C D E F G H I
Predecessor - - A,B A,B B D,E C,F D,E G,H
Duration 15 10 10 10 5 5 20 10 15

4) Find critical path of network.


Activity A B C D E F G H I J K L M N
Predecessor - - - A,B B,C A,B C D,E,F D G G H,J K I,L
Time 8 5 3 12 5 6 9 4 5 7 7 10 9 3

5) Draw Critical path for following network.


Activity A B C D E F G H I J
Predecessor - - A A B,C B,C E E D,G F,H,I
Time 15 15 3 5 8 12 1 14 3 14

6) Derive critical path.


Activity A B C D E F G H I J K L
Predecessor- - - B,C A C E E D,F,H E I,J G
Time 9 4 7 8 7 5 10 8 6 9 10 2
 Draw the networks and determine the critical path.

1)
Activity Predecessors Optimistic time Pessimistic Most likely time
A - 2 4 3
B - 8 8 8
C A 7 11 9
D B 6 6 6
E C 9 11 10
F C 10 18 14
G C,D 11 11 11
H F,G 6 14 10
I E 4 6 5
J I 3 5 4
K H 1 1 1

2)
Activity Predecessors Optimistic time Pessimistic Most likely time
A - 4 16 7
B - 1 15 5
C A 6 30 12
D A 2 8 5
E C 5 17 11
F D 3 15 6
G B 3 27 9
H E,F 1 7 4
I G 4 28 19
3)
Activity Predecessors Optimistic time Pessimistic Most likely time
A - 3 5 4
B - 4 10 8
C B 5 8 6
D A,C 9 10 15
E B 4 8 6
F D,E 3 5 4
G D,E 5 8 6
H D,E 1 4 3
I G 2 5 4
J F,I 7 10 8
K G 4 6 5
L H 8 13 9
M J,K,L 6 8 7
4)
Activity Predecessors Optimistic time Pessimistic Most likely time
A - 4 10 4
B - 1 9 2
C - 2 14 5
D A 1 7 4
E A 1 3 2
F A 1 9 5
G B,C 1 9 2
H C 4 4 4
I D 2 8 2
J E,G 6 8 7
K F.H 2 8 2
L F,H 5 5 5
M I,J,K 1 9 2
N L 6 8 7