Schedules and activities of some projects are shown below:

Activity Predecessor(s) Fixed Duration


Activity Predecessor(s) Fixed Duration (days)
(days)
A 6 A 4
B 5 B 12
C 4 C A 3
D A 9 D C 3
E B 8 E D, G 2
F C 11 F A 2
G D 2 G F 10
H A, E, I 6 H F 2
I F 8 I B 3
J F 4 J I 2
K G, H 7 K F, J 3
L E, H, K 8

Activity Predecessor(s) Fixed Activity Predecessor(s) Fixed Duration


Duration (days)
(days)
A 4 A 6
B 5 B 5
C 4 C 4
D B 9 D A 9
E D 8 E D 8
F D 9 F D 11
G A 2 G B 2
H E, G 6 H C, E, G 6
I H 8 I H 8
J C 4 J C 4
K J 7 K J 7
L I, K 3 L I, K 3
M F, L 5

Activity Predecessor(s) Fixed Duration


(days)

A 5
B A 9
C A 4
D B 2
E D 3
F E, H 2
G B 11
H G 2
I G 3
J C 2
K J 4
L G, K 7
M F, I, L 2