Critical Path Analysis:
Activity #02
Activity Predecessor Duration (Days)
A - 4
B A 3
C A 1
D A 2
E A 1
F B 1
G D 3
H E 3
I F 2
J C,F,G 3
K H 6
L J 2
M L 3
B F I
A J L M
D G
E H K
4 B 7 7 F 8 8 I 10
4 3 7 7 1 8 8 2 10
4 C 5
8 1 9
0 A 4 9 J 12 1 L 14
0 4 4 9 3 12 2
1 2 14
2
4 D 6
4 2 6
1 M 17
6 G 9 4
6 3 9 1 3 17
4 E 5 4
4 1 5
5 H 8 8 K 14
5 3 8 8 6 14
Critical Path Analysis: