Question 1 - answer
Using the information given in table 1:
a) Draw a network of the activities given in the table; identify the critical path, the total and free floats.
b) Use the network constructed in part (a) above to draw a bar (Gantt) chart. Indicate the critical path, total float
and free float on the chart.
c) Using the Gantt chart drawn in (b) and the resources shown in the table draw a resource histogram and
cumulative resource curve (“S” curve). Note – the resources given are the number of resources used per task per
week.
Table 1
Activity Predecessor Duration (wks) Resources
A - 2 2
B A 4 1
C A 6 3
D C 3 2
E D 3 2
F B 1 1
G F 4 2
H G&E 6 3
J H 3 3
K H 2 1
L K 4 3
M J&L 2 1
Session 6A – Project schedule management
a) Analysed Network
2 4 6 6 1 7 7 4 11 20 3 23 FF 3
B F G FF 3 J
5 3 9 9 3 10 10 3 14 23 3 26
0 2 2 14 6 20 26 2 28
A H M
0 0 2 14 0 20 26 0 28
2 6 8 8 3 11 11 3 14 20 2 22 22 4 26
C D E K L
2 0 8 8 0 11 11 0 14 20 0 22 22 0 26
KEY
b) Gant Chart
Wk 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
A KEY
B
C Total Float
D
E F Total and Free Float
F
G F F F Critical Path Tasks
H
J F F F Non Critical Path Tasks
K
L
M
Wk 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
A 2 2
B 1 1 1 1
C 3 3 3 3 3 3
D 2 2 2
E 2 2 2 KEY
F 1
G 2 2 2 2 F F F Total Float
H 3 3 3 3 3 3
J 3 3 3 F F F F Total/Free Float
K 1 1
L 3 3 3 3
M 1 1
`
Men/week 0 2 2 4 4 4 4 4 5 4 4 4 2 2 2 3 3 3 3 3 3 4 4 6 3 3 3 1 1
Cumulative Man Weeks 0 2 4 8 12 16 20 24 29 33 37 41 43 45 47 50 53 56 59 62 65 69 73 79 82 85 88 89 90
Session 6A – Project schedule management
c) Resource Histogram
Resource Histogram
5
Man Weeks
4
Men/week
3
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Week Number
c) ‘S’ Curve
100
90
80
Cumulative Man Weeks
70
60
50 Cumulative Man Weeks
40
30
20
10
0
Week Number