Pert and CPM
Pert and CPM
JASPAL SINGH
(EX IES)
Nbt
mm
of mm
mm
am
HE
MMM
may
CONTENTS
1. PROJECT
2. PERT
3. CPM
4. CRASHING
5. UPDATING
6. AON NETWORK
PROJECT
as
Any
Project
required
Ex Manpower machine equipment
Engg deals with technology where as
project management deals with
synchronisationofthe technology with
manpower
time
cost
Project should be completed by optimum
3
use of resources that are available
There are 3 basic elements of project
management
Planning
scheduling controlling
Planning
Scheduling
activities
Controlling
scheduling
Ifit there is
any deviation from original plan
also includes
rescheduling
e Ban chart Gantt chant
Activities Duration 3
A Ending
Starting
0 I 2 3 4 5 6 7
Times
Bar chart
graphical representation of
is
activity vs time
ane's
Activities are marked on Y anis
Length of bar represents duration of
activity
of activity and end of ban represents
finish time of activity
Question
Activity nodays I 2
E I
Duration
I 2
Activities 2 and 3 can be done
concurrently
after activity 4 and 5 completed
UM
Limitations of bar chart
i Lacks degree of details
used as tool for controlling the project This
progress
Example Project laying of Pipeline
a Excavation 24days
C Back
filling 9 days
ÉÉ p
O 24 39 48
Days
n Time Uncertainity
d No cost optimisation
Each milestone can beconsidered as an
event of main
activity
of a particular activity is established but
De 3 at
A construction of foundation
E F
of An filling
P B
and bar chart is activity oriented
3 Linked ban chant
It is the modification of ban chant and
ship between activities is shown with the
help of links
It is the process of breaking the entire
Project
u r
System system
n
I
Subsystem
Subsystem
n t
components Components
Elements Elements
Construction of house
construction
finishing u
of foundation Interior
Construction of u
column construction
of beam stab
Construction of column
form work rip
n t
R If Rif of RIF
5 Network Analysis
It is graphical and logical
representation
of diff activities
It is modification of ban chant mile
back eliminate
a
Activity on awww AOA Arrow
diagram
b
Activity on node Aon Precendence
fundamentals of Network
Network consist of different activities
logically and sequentially
connected
such as required for completion of
project
It consist of
diagram on
activities being mark
arrows and event mark on node
Activity Actual performance of the
in class nuisance
for completion of an
activity resources
required
are
significance But generally they are
drawn from left to right
Description
1 2
Duration
Description A B C
Name
Types of activity
1 Serial Activity
An which can be started
activity the
only afteris completion of another
activity teamed as serial activity
A B
2 3
Say
1 y
a
t 23day day
day E 9 day
day t 5
2 Parallel Activity
Actiwhihan be carried out
activity
3
t 17day
Bsd t 19day
5d
E 5 dfyd
2 5 Ed g
tggday Ead
Series activity
A B D F A C E f
Parallel activity B 11 C DII C DH E
are
other
which marks the start on completion
of activity
an
occurrence of an event do not required
resources
any
Example
Construction of foundation completed
Concreting started
Concreting finished
Preparation of ESA en amination
started
completed
rectangular
Types of
an event
e Tail event
An event which marks the starting of
an
activity
termed
starting
of project is as initial event
Encept last event all events of network
first tail event is initial event
2 Head event
An event which marks the completion
of an activity is termed as head event
of project is termed finish event
And event
event
3 Dual Role event
Event which acts as both for different
events are dual role event
NOTE
It is virtual artificial
Dummy
superficial
activity drawn in network
only it is not the part of project to
other activities
Since this activity is not the part of
It is represented by a broken arrow
A c
1 4
B V D
Here dummy activity 2 3 indicates
that Activity D cannot be started until
activity A is finished
Grammatical Relation
uniqueness of identity
If more than one starts from
activity
2 3 A
I 2 71 7 3 4
73
I 2 5 6
Logical Relationship
Dummy is used to establish the
activity is common to two set of
Dummy
mmmm
Rules to draw network
only
event and one finish one
iBook
end
initial
event has
only outgoing ahh ow finish
t I 2 5
day t 9 day
6
t 3 3 day g
3 day
t a
3 No
activity can start until its tail
event occurs
t 2 2
A 8day
5
day I D
t 7 E
3 day
t g
4 No event can occur more than once
in the network
e a
day
B I day
A
2 day 2
t day
3 today
day
day
t 9
day
5 An arrow should represent only one
activity
6
Similarly two or more should
activity arrow
D f
A B C
E G
7 As as arrow
avoided
8 As
far as possible
crossing of arrows
be done
bridging of activity
2 7 4
7
I 6
3 5
2 7 4
3 5
BRIDGE
Time flow is
from left to
right
NOTE
for development of network dummies
required to established logical
are
and grammatical relationship But it
is
difficult to identify where dummies
dummies are provided in conservative
way
ways
A B
1 s 2 3
A B
1 2
ii
11 12
A C
Ill
12
iii
Dl
C D E
C E
2 If dummy is the
only activity
terminating
at its head event it can be
removed C
B 2
DI
1 E
3
D
o R
X P
A I a
Y Da
the relation
If dummy activity establishes
be removed
A B
1 2
y D A
z 4 5
A B
I 2
D E
3 4 g
4
If two or more activities emanate start
then
the concerned activities start from same
node
A C
i 3 7
2 a
of successors activities which are also
having other predecessors then the
concerned
same
node
A E
B s
C E
B f
Numbering of event
Numbering of event is done by talker
son's rule as follows
only
Remove all the outgoing allows of
initial event This will lead to formation
3 Number these new initial event
sequentially
Repeat step and untill all the
2 S
4 7
Ba BYE
I
f
1 5
N
t
3 6
NOTE
Skip numbering in small network
no modifications are
required
numbering
time will be required for removing
diagram and no of events as the rule
Job Immediate
B A
C A
D A
E B
f C
G D
H D
I E F G
J H Z
3 E
B
A f 6
I 2 C a I
g 8
G J
D s
M 7
s
A network
Question Draw Boa diagram for
the project
having following
activity relationship
follows D but proceeds f
C
1
C but proceeds H
follows B
5 D follows A
7
2 6 I
IG
D
g
7
B
f
n
j C
a
Question In a construction project events
havenor identified as A B C D E
A G H J K L M
1 A is start event
B Occurs after A
2
strains the occurrence of G
after B beforeH k and restrains E
4 D occurs
5 f succeeds C proceeds
and restrain A
8 L occurs
after J but before k
D K M
A B O L
a r
r a
i
i N
activities
P and W where P is plastering and
W is white washing done
one set
by
of lab opus
If the entire work
diagram
ing relationship
when P and W is available for all section
2 P is available for 1 section and w is
available for one section only
4 When P and W are available for one
section
only
Activity
P
I
Pz
Pz
Wi p
Wa P2 k
W3 Pz
P Pa P
W Wz Wz
p s
W
P2 Wa
T
P
Pre
Activity activity
Pa p
P Pat P
We P
Wa Pak P
Wz P Pa P
p Pa Pas
Wa W3
We
Pz
Pz
W P
Wr Pat W K P
Wy P Wa Pa W P
Pr
Jw
Pz
N a
WZ
Wz
N
Activity Pre activity
Pa P
B Pat P
W P
Wa With PI P
Nz Post Wath Pa P D
W We
i
I
Pa P
Question A project consists of 3 operations
for
completed
operation
ation
Solution Pre
Activity activity
Er E
E3 El
EET
CI
2 Eat Ct Be
Cz E3 Cath Ra fi C
th
B C E
B2 2 Bit Ez G R
Bz 3h B2 E3C2 Ezekiel
E Ez E3
G Cz Cz
B B2 Bz
C B
1 2 3
3 7 A B
7
a
I
p B3
I 2 q 10
5 6
Az 137 104
Cz
4 8
day4 7 24 18 9
Let 24th 2
ish 3
In 51 hr
14 ta 22hr
8 At
3hr
BI
3hr g B2
r
y fathoms22hr
E
I 2
8hr 5 Cz 6 9 s 10
8hr D 3hr
By 6hr
ID
y Ph
0
q
Me
8hr 4 8
t 30
E3
azan
876hr
gh
programme chart
a Linear
a 1 2 and 3 1 2 and 4
only only
c 3 and a only 1 2 3 and 4
2019
Solution d
Techniques for project time plan
are critical path method precedence
network analysis and line of balance
technique
Linear programme chart is used
manimisation cost minimisation and
for profit
resources allocation
solution b
solution d
PERT
Programme Evaluation and
Technique
scheduling and controlling the project
project is time involved in it which depend
upon the estimate of different activities
about completion of
activity
idea about completion time of an
activity is known
Peut follows probabilistic approach and it
involved in completion of activity 3 time
estimate are considerable
ideal condition
required for completion of activity
analysing
worst condition contigencies are not
considered
for completion of activity in normal
condition
Time estimate can be represented in the
form offrequency distribution curve
edistribution
Pfaq
curve
Frequency
Of
no
activity
BBB jemadar
Me
É
I I
EE
K
ay
Cir ma E
Pessimistic
NOTES
Properties
of frequency distribution curve
1
Mean time I X t Xa t Xn
3
Variance 62 2 D E Xi X
Standard deviation r Xi x
All these are parameters of spread or
dispersion
Probability Distribution
In frequency distribution we me
analysis
behaviour but in probability
group
an the distribution
distribution we analysis
of probability values of diff all possible
outcomes
Deuray
distribution
a
f
distribution
curve is
unity
A j y du
Ex dn
NOTE
but function f x
Hence probability at point X is given
any
Total area
IT dx
Fx dx
f
x dx
Limits Areal
I 36 0.15 I
o
N X 50
fo I
36 Assumptions
36 error at 3
fp
X IO 68
I 120 95 Ap to 5 30
I 36
I 30 99.7 tp to 60
BE
of an
activity
by
te to 4than
Ip6
BE
pm Im
a
an
tell te 23 te 34 teas
2 z 4 5
the path
path
Event time
TE ti
Mei
23
in j t
10 B 13 a ai
t j 29
tei 2g
am
it UM.TEi
fi g
occur without
may
delaying project
method 10 7 J 12
peg
12 10
if 2
9
i j 15 9 6 3min flip
lo g g
i j g
ij tei j
j 16
Tri Tj tei
j min
Slack
It is the time
by which occurance of an
Mhm
Te Te
ve
slack Te 15
A
If 0
S TL TE 7 O
Ti TE 7 R
ve slack indicates Te 10
delaying project
event
B S
f S Slack O
TL TE D TL TE
mm
in occurance this event
as
delay of
C
If Slack O
S TL TE C O
TL TE Te 10 day
g 7
TE 13
day
event
Critical Path
can be completed
as
early as possible
zero
critical
path whose variance on standard
deviation is more
NOTE
variance
of any path critical path it will be
te 6
2 y
te te
tess te 6
n 3
f
te te
s
te te
te 3 test
z a 8
E
E Fffftd
path
to tm to tr
Activity 6 8 11 8.167
1 2
1 3 3 7 9 6.67
1 4 5 7 10 7.17
2 7 8 10 12 10
2 6 4 8 12 8
3 6 8 10 12 10
4 5 4 6 8 6
5 6 3 3 6 4.63
7 8 5 8 12 8.17
6 8 7 10 15 10.33
Critical path 1 4 5 6 8
TE 28.33
521 TE 6.17
2
10 7 20.16
8.17
8 TE 18
10
8
6
67,3
6 10.37
I a TL 18
TE 228.3
T 4.83620
1228.33
2 07.17 34 13.17520
7 0
7.17
635 T
TL 213.17
820 TE
S O
II 17
so
0 5 Area TE Tsi
P TS 2 Area Tsa
Area TE Area T2 Tr
5 Area TE TS 2
P Tsz 2 Area TE TS 2
The
STEP
theorem
im i
r
fue of standard deviation
STEP
ITE with
I
probability
I 0 2
L I 2 3
project in 30 days
Activity to ten tp te r
HEY
1 2 2 5 8 5 I
2 3 8 11 20 12 4
2 4 4 7 16 8
2 5 4 9 20 10
3 4 O O O O O
3 7 3 5 13 6
9 6 7 10 13 10 I
5 6 3 7 17 8
6 7 2 3 10 4 1.77
7 8 2 4 6 4 0.44
72 31
5517 8
Tu 31
y
I
8 8
T
9 6
TEES
T D FEI't g
TE 227 1235
2 27 520
5 0 8
TE 19
Te 19
Critical Path 1 2 3 4 6 7 8
Iii r I a OH 1.77 0 44
6 2.86
I 84.1 95 p
motor
97.7 1 2
2 2 1 X 95.84
84.1 97.7
I 1.80 I
1 80I Ts 35
2 86
Ts 40.15 41 days
iv Ts 30 I
days III
30 35
2 86
1.74
L P
2 2 I 2 75
P 5.79
BEBEE
BEE
pm
ot3PBA
me
PERT CPM
It is event It is an
an
oriented
activity
oriented network
are made
for each made for each
activity activity
B distribution distribution
manufacturing
industries
OP M Analysis
time of activity
tech an
activity can be
start
equal to Te
of its tail event
time
is not to
activity
head event in
equal
general
LF T Tj
out ma
effecting the completion time of
If an
project
start at its latest time
activity
LST t t ij L FT
LST Lf T t ij
Ti LST Lf T
Te 5 t 13
g bij 10
6
Te f T 15
j 5 HO 15
Lf T tij 15 LST Lf T Aj 15 10 5
15 5 15 5
by starting
and finishing of an activity can be
available over
activity duration
TE 5 TE 12
2 y
T 6 7 17
5 6 7 8 9 10 11 12 13 14 15 1617
e
Mantimeavailabletoractivity
t 2
A 15 5 10
days
ere
te
EST 5 f 17 7 10
days
441g
Fr Ti Te
tij
FT LST EST
FT LFT EFT
activity
time
5 6 7 8 9 10 11 12 13 14 15 16 17
I I
Min time available
l
le fr
k
I activities
free flood 7 2
I 5 days
I
FT Ti j LTE i tij
Tei tij Tj A
Ff Tej Tj Fr
Fe Tij Tej
event slack
activity
activity duration
earliest time
Ff TE j Tei Aj
Fs Ff t TEI TI
FI Ff LT Li Tei Ff Si
predecessors
and successors activity
F If Tj Tej
FT Ff
Analysis in CPM
To do the
analysis in CPM critical path
follows
the schedule
2
Ff Total float fr 0 If for any
activity
on schedule
are optimum
3
If total float fr 0 Activities for which
of schedule
the activities
A 2
B 2 A
C 2 F
D 6 Ay
E 6 D G H
f 1 A
G I f
H 2 G L
K 5 A
L 3 F K
Activity Duration Fr Fr Ft ti
A 2 O O O O
B 2 O O O O
C 2 O O O O
D G O O O O
E 6 O O O O
A 1 I 0 0 1
G I 2 0 1 2
H 2 O O O O
K 5 0 0 0 0
L 3 O O O O
Er E
KMS D4 E
pg
E 05 s EN
Ipay
E E
Da D
E
M E
E
my
y C B
B g g
EST EFT
Critical Path A K L H E
A B C D E
Activity
A B
8,3 914,5
1243
18,17
solution
Ag I I 13 I I
3 3 B
13 44 a
a 1
D2
Dirt
A BI G DI D Dz Dz
6B rBPtrBEtrB
4.5
2.6
Go 1.73
4.6
FEEDS
Badly
maze
a a
I go.jp
CRASHmy
Crashing
any
are time and
cost
cost is to be studied
components
1 Indirect cost
2 Direct cost
Project Cost
H M
I n
for activity
an But can be
increases
linearly maintanence changes
linearly
with time
Total
indirect I
flowage I
Total
indirect loss
cost
lovely
heads
I I I
l 1
Time
2 Direct Cost
time
co
Direct
cost
a
i
i
Cn normal cost
normal time tn
Cc Crash cost
associated
with crash time
completion of an activity
Cost slope
n
Ca
pl
Direct
cost Actuate
G t lol i
slope of D.C 1
curve assuming
it to be linear te time th
Ocs Co en
tn to
10 5
1000 Rs
6.6 day
Hence it signifies increase in direct
E Too
It g
it
ip p
as
e Indirect
cost
cost
1 Direct cost
t optimum
Time
Crashing
path
e start
washing the network along the
may
the parallel critical path In such case
MI
I mushing
c is done upto an extent
fully
Actiityationootstoot
1 3 8 5000 7 8000
2 3 5 8000 3 10000
Ghgdg TE 4
7 4
FT O 413 72 513
4 0
I 33
817
TE O
FT I TE 9
Tao 9
Te
tn 9 week
0 I 2 3 4 5 6 7 8 9
413 2
513
3m
817
C S 1 2 3000
1 3 3000
2 3 1000
17000 Rs
35000 Rs
2 first Aage
Slope Crashing
2 3 at 1 week
Tc 8 week
0 I 2 3 4 5 6 7 8 9
413 413
y 2 3
it
817
to 8 Week
16000 RS
IDC
DC 17000 HOO 0 1
18000 RS
TotBoost
TC 39000 RS
2 3 11 1 3 I week
0 I 2 3 4 5 6 7
4 3 3 3
I 77 2 7 73
7 7
7
Tc 7 week
Total cost
DRABBER 22000 RS
Total cost 36000 Rs
36k p
35 K L
Total I
o
1
cost I 1
344 4
I 1
min m 1 I 1
cost Cm I I 1
I 1 I
Time
7
optimum9
time
Activity th Cn te Ce C s
2
y
613 513
I 44
44
315 513
solution 6 6
MAT 67
TEE
2
Ft 4
613
513
act a
i
I 7
FEI
TE O
TL 20 N
815 513
2 3
FT FT O
TE 10
TL 10
8 9 10 11 12 13 14 15
01 23 4 5 67
513
s 2 3 s a
815
tn 15
days
IDC 3000 15
45000 RS
30000
TotMTc
ust 750000
2 3 at 2 week
Tc 13 week
DC 30000 1000 2
32000 RS
To toast
Tc 71000
0 I 2 3 4 5 6 7 8 9 10 11 12 13
513
1 2 3 7 a
815
2 3 11 1 3 25 K
1 2 11 1 3 4K
3 4 3K
Tc 12 week
DC 32000 2500
34500
TotalBoast
Tc 70500
0 I 2 3 4 5 6 7 8 9 10 11 12
513
613 14 513
1 12 3 a
715 y
3 Third stage
crashing
1 2 11 1 3
211 1 3 X
3
3 4
3 4 at week Tc 11 weeks
0 I 2 3 4 5 6 7 8 9 10 11
5 3
1 N
715
IDC 3000 11
33000
DC 34500 3000 1
37500
TC 70500 Rs
1 2 11 1 3 4K
2 4 11 3 4 6.5 U
1 2 11 1 3 at 2 week To 9 weeks
0 1 2 3 4 5 6 7 8 9
513
413 2141I 3
413
1 s q
515
21 3000 9227600
DC 37500 4000 2
45500
TC 72500
5 fifth stage
2 4 11 3 4 at 1 week
0 I 2 3 4 5 6 7 8
413
413 111
2 3 4
1 515 g
p
Tc 24000
DC 52000 Rs
Tc 75000 RS
76k
472.5 J
Time
cost 71.5
70.5
8 9 11 12 13 15
Time
catty
days day
A B 2 10000 2 10000 0
C D O O O O O
FEZ EYE
TE
7 12
D B D
212 FT A TE 28
M3
613 11 6 TL 23
77 0
A f
713 r s
p o
47 0
T O C 94 E
f D
Tf
MATT p FE FEI
A BC E F Critical Path
0 1 2 3 45 6 7 8 9 10 11 12 13 14 15 16 17
18 1920 2 22 23
713
A 212 613
C
919 I
61131
I
B a
514 1116
th 23
days
IDC 800 23
18900 RS
Dc 39000 RS
7ng 57400 Rs
BC at week
0 I 2 3 4 5 6 78 9 10 11 1213 14 15 16
17 18 19 20 2 22
713
B s a p
514 D
1116
22
tc day S
IDC 17600 RS
DC 39000 400
39400 RS
Tc
m 57000 Rs
days
Tc 13 weeks CE 600
18
14400 RS
DC 39400 600 4
41800 Rs
O 1 2 3 4 5 67 8 9 10 11 12 13 14 15
16 17 18
7 3
212
B 513 514 613
A
g s
C
s
I s
514
g
11 6
y
CE II Df at 1 days AC II BC 11 BD 1900
CE II Df 1400
Ef 11 DF 1500
0 I 2 3 4 5 67 8 9 10 11 12 13 14 15
16 17
7 3
A
212
B
613
i C
414
s A
613
I
a
514
t 1016
to 17
days
IDC 17 800
13600 RS
days
Ef II DF 1500
0 I 23 4 56 7 8 9 10 11 12 13 14
713
A s B s C s p p
519 716
to 14 days
IDC 300 14
11200 RS
DC 43200 1500 3
47700 RS
0 I 2 3 4 5 67
days
8 9 10 11 12 13
6 3
1
414 313
A 212 s B 413
s
C s E p
414 1016
I D
Tc 13 days
IDC 13 800
10400 RS
DC 47700 1900
49600 RS
To 18
days
Tmin 56200 RS
st
ND
Ito
and
Updating
may
activities i.e it
may be running ahead of
schedule or beyond
mas schedule
in activity
major change
activity
updating
updating
A Original network
B Time computation
a
Activity 1 4 was completed as originally
planned
Activity 1 3 was executed more rapidly
originally
its
following
completion of Activity 1 3 and was
finished
at the end of nth day
required 6 more
day 1
2 7
f g
q t 3
8 7 t 6
ptg
8 5
a g
9
4
8 10
3
at 5
3 6
TL 18 TE 23
My 8
TE
72 24
7 10
t 6 y
2
FT 10
MAMA
7 20 12 1 FT I
yes t 5
TE 13 TE 20
5,4
TL 20
t t 5 to
1
FE 8 v0 t 3 O TE 29
o
17 0
y Y É Taza
M
j FT O
TE 10 3 G TE 24
72 10 71 29
Critical path 3 4 5 6 8
1
it
ME
TL
Ito go
TL 12 i g
7
82218
5
FE 3
TE 12
TL 20 FT 8 I
0
9 8
I 5 In 9
a 7 26 9
O 4 71
F 28 N 5
F 8
F 9
TE o FE 3
Question
E Ii TEEMM
0 3
2
y
Fly 5 FT 20
FEI A 0
JEEZ
FT 4 4
8 fi a at
FT'd AT
Tf L
pg Fal
Eet I
update network after todays
a 5
completed
still
2
Activity running required 6
more days
3 Activity 4 6
running still required 6 more
days
4 3 6,4 6
days
5 7
Solution
g
to
My Ms
Fe
2 5
Ft89 7 FT 3
FT an 369
10
TE
37
I 4 FE 4 8
FT O
TE10
TEI BETO É
y
I 3 Boa
T 10
9 6
Ft 5
TE 10
TL 15 FEI
Critical path 1 4 6 7
an activity on
project
activities
is done during scheduling phase
a Resource Smoothing
e In this case dem
to be limited
resource
requirement period by period
for the network given below Ithe f ig
35
C 2
a
H 2
to E 8
t
614
AG
1 2
D4 g 6 76
gB f d
solution
is
SEE
7 a
FT 4 F L
com2
Tf
g
F D 2 FT 6
7
TE 14
FEI
TE 3
T 5 7 14 TE 3
TE 8 KRAB
72 13
TL B
1 A B C 8
2 A B C 8
3 A B C 8
4 A B C 8
5 A B C
6 B C D E 11
7 B C D E 11
8 B C D E 11
9 C D E F 12
10 C D E F 12
11 D E F 9
12 D E F 9
13 D E f 9
14 D F 7
15 F G H 10
16 F G H 10
17 f GH 10
18 G H 6
19 G H 6
20 GH
21 H 2
22 H 2
12 11 12
10
10 9
g 7
I 6
É4
Time
In between 6 17 Resource
requirement is
B C D E f G H
high
F
G
delay by 52days
delay by days
1 B C
A 8
2 A B C 8
3 A B C 8
4 A B C 8
5 A B C 8
6 B C D E 11
7 B C D E 11
8 B C D E 11
9 C DE 8
10 C D E 8
11 DE 5
12 D E 5
13 DE 5
14 DF 7
15 FH 6
16 F H 6
17 F G H 10
18 F G H 10
19 F G H 10
20 F G H 10
21 f Ge H 10
22 F G H 10
12
10
g 8
a y
0 1 2 3 4 56 7 8 9 10 11 12 13 14 1 516 17 1819 20 2 22
Time
levelling In
b Resource resource
levelling
of
way demand
the resources become less than
during
levelling
7 H 2
A 4
C 10 11
I 4 f 2 6 215
3
37
B 2 3
g D Ga z
4
ME 6
z 5
Solution i sq
It
Tf 7
MAT
Tf
MEET 4
H2
Aa
yoga C
f fog
TEY
4
Tf O
my 6,157
FEI B 2 DBaye
TF D
Tug
G E
O Tp5
Tp
MMM
EG 5
a s
IE IE
Critical Path 1 3 4 6 7
1 A B 6
2 A B 6
3 A B G
4 A B 6
5 B HC 4
6 B HC 4
7 BHC 4
8 BHC 4
9 D H E 11
10 DH E 11
11 DH E 11
12 D H G 9
13 H f G 8
14 H f 6 8
15 Fg H 4
16 f 2
17 f 2
18 f 2
19 f 2
20 1 5
21 1 5
22 I 5
12
11
10 9
a 8
8 O 6 5
6 a
2 2
Time Days s
Activities in between 8 14
H F G D E
E G H
E and G
Delay activity by 5
day by 5
days
1 AB 6
2 AB 6
AB 6
4 AgB 6
5 B g C gH 4
6 B C H 4
7 B C H 4
8 Bg CgH 4
9 D gH 5
11 D gH 5
12 D g H 5
13 F g H 4
14 F g E
H 10
15 Fg EgH 10
16 f g E 8
17 F g G 6
18 F 6 6
19 F G 6
so I 5
21 1 5
22 I 5
E and G
by day
Time Resources
1
Activity
AB 6
g
2 Ag B 6
3 A gB 6
4 Bg A 6
5 Bg C 2
6 Bg C 2
7 B g C 2
8 Bg C 2
9 Dg E 9
10 Dg E 9
11 Dg E 9
12 Dg H 5
13 H g f 4
14 Hg f 4
15 Fg H g6 8
16 F gHgG 8
17 F g H 6 8
18 F g H 4
19 F g H 4
20 1 7
21 I g H 7
22 I g H a
I 6
O 4
0 I 2 3 45 67 8 9 10 111213 1415161718 19 20 4 22
Time Days s
increase
by doing of demand decrease
9 17 DE F G H Already delayed
of E can be increased by 2
5
by day
E s
6 e 3 labour E 6
day s day
3
day a a labour Duration of G
4 3 labour 4
day day
critical Activity 0
4 3 labour Duration of activity
days
6 2 labour D I6
day day
A g B 6
A g B 6
3 A g B 6
4 B g C 6
5 B g C 2
6 B g C 2
7 B g C 2
8 D g E 2
9 D g E 6
10 D g E 6
11 D g E 6
12 D gH g E 8
13 H gF g E g D 7
14 H 3 F g E g DA 7
15 F iHg G 7
16 F H gG 7
17 g g G
FH 7
18 Fg HgG 4
19 FH
g 4
20 I H 7
21 I H 7
22 I H 7
A ON AON
A p
I s B ff
c a
i ii
AOA AON
iii A B
A B
T B
B
A
in A
A
A
V C
7 C
B
B
ui A B
I
C D
AOA
A B
C N D
AON
3 7
12
G 16
a
Do I 8 B 9
20
J
2 22
for
na
3 f g
9
as
It
0 8 8
1 08 a q Ey q k
622
TE5
If
2
I
Fff
If 97 16
pp
A
ft 7
TL
egg
5 Fff
Gx egg
g
22
JE
ftp.go
off 02
IfF 3 Ff 0
s
6
f
Tff
a
11
g
71 22
I 7 ft
g TE 8 FFDa Fed f
Feel s
f D
E FA O
z f
Ff O
7
na
FEI IE 6
Solution I I AI
f Fa Fz
G Ga 63
Hi H2 Hz
3
TEO TE TE 10
fi P2
G 7
I
It 573
If
19 Te 19
ma
42 Pg
D2
Tp 12 TE 12 103 763
I v 7 39
HI g 1
TE H TE 3
PREVIOUSYEARQUESTION
ESE
Bat
S