Assignment: MTH601 (Fall 2020)

BS160401475
Question:

Construct a table which shows the relationship between the activities and their
predecessors.
Active Predecessors Time(Duration)
A - 3

B A 4

C A 5

D A 2

E B 3

F C.D 6

G D 4

H B 8

I E.F.G 3

J G 2
2. Calculate the following time estimates for each activity.

1. Earliest Start Time (EST)


2. Earliest Finish Time (EFT)
3. Latest Start Time (LST)
4. Latest Finish Time (LFT)

3. Calculate the total float for each activity.

Activities EST EFT LST LFT Total Float

LST-EST
A 0 3 0 3 0
B 3 7 10 14 7
C 3 8 3 8 0
D 3 5 6 8 3
E 7 10 11 14 4
F 8 14 8 14 0
G 5 9 8 12 3
H 17 15 6 14 1
I 14 17 14 17 0

4. Identify the critical path.

Possibiltes Paths Time (Days)


A-B-H 1-2-3-8 3+4+8= 15
A-B-E-I 1-3-7-8 3+4+3+3 = 13
A-C-F-I 1-2-5-7-8 3+5+6+3 = 17
A-D-G-J 1-2-4-6 3+2+4+2 = 11

5. Find the project completion time.

Project Completion time = 17 days