PEC3603 Portfolio of Evidence
LI Moahloli 67261582
1. INTRODUCTION
The Department of Public Works and Infrastructure’s focus is on public land and building
assets and infrastructure and the way in which they can be stimulated and sustain
economic growth in the built environment.
As one of the three Building Works Inspector at Free State Department of Public Works
and Infrastructure at the Lejweleputswa District in Welkom, I am involved in most of the in
the region. My role in the project is either as a quality control inspector for building works
or as a project manager/ leader. The project are either maintenance work or appointment
of contractors
Maintenance work involves procuring construction material and construction work is done
by In-house personnel which involves works inspectors (Building, Electrical and
Mechanical), administration and also Artisans (Building, plumbing, carpentry, painting,
tiling, electrical and mechanical). All the directorates in the section work as a team.
Other projects tender documents are compiled and contractors are then appointed to do
the works. In this instance, my role is as project manager and a quality control inspector.
In my five years of service at Public Works and Infrastructure I have been involved in a
total of seven (10) projects of which 6 have been completed, one (1) is in progress and
three (3) are in the planning stage.
2
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
2. JOB ROLE
2.1. Render basic inspection services of work done on minor new and existing structure
on a project basis. Including:
2.1.1. Check new maintenance work undertaken on project sites are compliant with
regulations and legislations
2.1.2. Quality control of works undertaken
2.1.3. Compile estimate and repairs and costs for minor new work
2.1.4. Maintain electronic records of outstanding and finalized work
2.1.5. Develop a bill of quantities
2.2. Analyse and compile relevant documentation for work to be done on minor new
and existing structures, through inter alia the following:
2.2.1. Development and interpretation of plans and sketches
2.2.2. Draw-up quotations documents and compile specifications, bill of quantities
and bid documents and sit in for Bid-specification meetings
2.2.3. Participate in the adjudication process and provide recommendations on
quotations
2.2.4. Liaise with relevant stakeholders in respect to technical aspects
2.3. Oversee/ manage the activities of contractors on project sites through inter alia the
following:
2.3.1. Inspect the work done by contractors and if it is in compliance with the
relevant standards
2.3.2. Advice and guide contractors in respect of relevant legislations and
regulations
2.3.3. Compile and process payment documents
2.3.4. Compile and process variation orders and request for extension of deadlines
2.3.5. Ensure effective administration
2.3.6. Develop progress reports on projects
3. PROJECT PROCESSES
State owned buildings are identified by Property management units. Then as a building
inspector my job is to do a condition assessment of the building, this is to check the extent
of damage the building has incurred over the years. My job is to identify whether the
damage in the building requires day-to-day maintenance or construction work needs to be
done. The condition assessment report consist of a photo report of the building; building
assessment where the rating of the building is done, the rating is from very poor to
excellent; assessment cost estimate, this is the estimate cost of the work required to be
done on the building; and a classification and budget estimate, this section is to classify
the budget of the building if it is either emergency maintenance, schedule maintenance or
minor capital work therefore a new project.
This report is then submitted and a budget will be allocated for the building which an
assessment was one and then the next step begins.
3
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
3.2. Analyse and compile relevant documentation for work to be done
After budget allocation, the next step is compiling relevant documentation for the work to
be done. At this stage there are two project types to be considered:
After delivery of material, I then draw up a scope of work for the project and construction
works program using MS Projects or Excel.
Then site handover meeting is arranged and all stakeholder are invited to the meeting.
Then construction team starts the work. I will then setup progress meeting, issue
instructions on site, approve quality of work, compile EOT’s if they are required. Then
when the project is complete, will issue a Practical Completion certificate and compile and
submit a closeout report.
Capital works (Tendered Projects)
I will then present the tender document to Bid Specification Committee which will all sit in a
meeting to look through the tender document and to assist if any mistakes are found and
where assistance is needed be given.
The tender document will then be advertised and a contractor is then appointed to do the
works on site. As the Project Manager I will then, hand the site over to the contractor and
manage the project. I will then oversee the contractors work, approve the works program,
assist in compiling a safety file, assist in quality control of the works, compile and process
payment documents, variation orders and EOT’s if needed, measure works on site for
payments, Chair progress meeting and later issue practical completion for projects and
compile closeout reports.
4
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
4. PROJECT INITIATION PHASE
Plan each task with the team to cover the scope of work to meet overall goal
Draw up Bill of Quantities and specification for the works
Estimate the project cost including P’s & G’s, Escalations and contingencies
Compile Tender document to align with the scope of work and project type
Attend Bid Specification Meetings to finalise tender document
Advertise the tender and appoint contractor
Compile a works program for In-House Massification projects
Receive material delivered by supplier
7. PROJECT CLOSURE
5
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
8. PROJECTS INVOLVED IN
On-going Projects
Completed Projects
6
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
9. PROJECTS - Upgrade of Welkom Lejweleputswa Regional Office Guardroom
Scope of work
The work consisted of Upgrading the Guardroom from a metal structure to a brick and
mortar structure, installation of a new Toilet with basin, new kitchen unit, energy saving
lights, tiling, ceiling and external works such as paved area, gutters and down pipes and
sealing of roof. The project was to improve the working conditions of the security officers at
the department.
CONTRACT INFORMATION
Contractor: KAHELA TRADING ENTERPRISE
Site Handover Date: 31 November 2019
Contract Period: 5 Months
Completion Date: 31 April 2020
Work Sequence
Demolition of Metal Structure
Cleanout of site after demolition
Setting out for foundation
Building of foundation brickwork
Laying of wire mess
Pouring of concrete slab
Brickwork, Door frames and windows
Plumbing
Plastering
Flooring tiles
Doors and Locks
Paint work
Electrical work (Wall boxes, conduits wiring on walls)
Ceiling and kitchen unit installation
Management Documentation
Variation Order for Additional Works was compiled and processed
EOT was applied for and approved
7
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
Pictures
8
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
9
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
10
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
11
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
12
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
13
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
14
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
15
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
10. PROJECTS - Renovations and Upgrade of Bothaville Agriculture Offices
Scope of work
The work consisted of Upgrading of one of the houses into office space for the Department
of Agriculture. This project was to create office space for Agriculture. The building was an
old asbestos building. The asbestos roof was then removed, and IBR roof sheets were
installed. Among other things, a Hybrid Solar System was installed and Back-up water
supply to adhere to the green energy initiative implemented by the National Department of
Public Works.
CONTRACT INFORMATION
Contractor: KAMOHELO YA MPHO
Site Handover Date: 18 November 2020
Contract Period: 11 Months
Completion Date: 30 October 2021
Work Sequence
Site Establishment
Removal and Installation of Roof
Preparation of works
Removal of bath and sanitary fittings
Installation of fibre cement ceiling to replace damaged asbestos
Electrical work
Carpentry (Doors and partitioning)
Plumbing including Back-up water storage
Paint work
Solar Installation
Management Documentation
A variation order was compiled and submitted for extra woks
EOT was applied for due to delay because of COVID19 regulations
16
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
Pictures
17
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
18
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
19
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
20
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
21
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
22
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
23
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
11. PROJECTS - Renovations and Upgrade of Odendaalsrus Agriculture Offices
Scope of work
The work consisted of Upgrading and Renovations of office space for the Department of
Agriculture. This project was to renovate the offices for Department of Agriculture to
improve their service delivery since the offices were not operational for about 3 years.
Among other things, a Hybrid Solar System was installed and Back-up water supply with a
booster pump to adhere to the green energy initiative implemented by the National
Department of Public Works.
CONTRACT INFORMATION
Contractor: SEKOTO TS PLUMBING
Site Handover Date: 18 November 2020
Contract Period: 11 Months
Completion Date: 30 October 2021
Work Sequence
Site Establishment
Demolition of ceilings, doors, wall tiles, floor tiles, old sanitary fittings
Tracing of existing electrical conduits
Electrical rewiring
Beam filling (Brick work)
Carpentry (Ceilings, doors)
Electrical light switches, fittings and sockets installation
Plumbing work and kitchen units
Flooring
Paint work
Solar Installation
Management Documentation
A variation order was compiled and submitted for Omission of old works and
Addition of new works
EOT was applied for due to delay (Rain, late payments, late approval of VO, etc.)
24
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
Pictures
25
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
26
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
27
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
28
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
29
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
30
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
31
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
32
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
33
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
34
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
12. PROJECTS - Renovations and Upgrade of Welkom Agriculture Offices
Scope of work
The work consisted of Upgrading of one of the offices for Department of Agriculture.
Kopano complex was an old hospital. The upgrade and renovations was to remove the
hospital feel to make the office space more suitable for office use.
CONTRACT INFORMATION
Contractor: In-House Massification Project
Site Handover Date: 07 July 2022
Contract Period: 07 Months
Completion Date: 24 January 2023
Work Sequence
Demolition of ceilings, doors, wall tiles, floor tiles, old sanitary fittings, walls, pipes
Brick work building up door frames
Roofing
Carpentry (Ceilings)
Electrical light switches, fittings and sockets installation
Plumbing work and kitchen units
Flooring
Carpentry (doors, kitchen units)
Paint work
Management Documentation
EOT was applied for due to delay (Rain, delay in moving office equipment, etc.)
35
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
Pictures
36
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
37
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
38
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
39
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
40
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
41
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
42
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
43
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
44
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
45
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
46
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
13. Record of Modules Complete and Outstanding
47
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
14. WORKS PROGRAMS AND DRAWINGS
Work Program - Renovations and Upgrade of MDR to Education Offices
Drawing - Upgrade of Welkom Lejweleputswa Regional Office Guardroom
48
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
PEC3603 Portfolio of Evidence
LI Moahloli 67261582
15. TENDER DOCUMENT
20
PEC3603 Portfolio of Evidence
LI Moahloli 67261582