Preliminary or approximate estimate is required for studies
of various aspects of work of project and for its administrative approval. It can decide, incase of commercial projects, whether the net income earned justifies the amount invested or not. The approximate estimate is prepared from the practical knowledge and cost of similar works. The estimate is accompanied by a report duly explaining necessity and utility of the project and with a site or layout plan. A percentage 5 to 10% is allowed for contingencies. The following are the methods used for preparation of approximate estimates. a) Plinth area method b) Cubical contents methods c) Unit base method a) Plinth area method The cost of construction is determined by multiplying plinth area with plinth area rate. The area is obtained by multiplying length and breadth (outer dimensions of building). In fixing the plinth area rate, careful observation and necessary enquiries are made in respect of quality and quantity aspect of materials and labor, type of foundation, height of building, roof, wood work, fixtures, number of storey’s etc. Cost of building= Plinth area of building x Rate per plinth area b) Cubical contents methods This method is generally used for multistoried buildings. It is more accurate that the other two methods viz., plinth area method and unit base method. The cost of a structure is calculated approximately as the total cubical contents (Volume of buildings) multiplied by Local Cubic Rate. The volume of building is obtained by Length x breadth x depth or height. The length and breadth are measured out to out of walls excluding the plinth off set. The cost of string course, cornice, corbelling etc., is neglected. The cost of building= volume of buildings x rate/ unit volume. c) Unit base method This technique is used for preparing preliminary estimates (i.e. order-of- magnitude type estimate). This estimate is generally prepared during the conceptual planning phase of a project, with less information available with the estimator. In this method, the total estimate of cost is limited to a single factor. The examples of some of the ‘per unit factor' used in construction projects are construction cost per square meter, housing cost per boarder of a hostel,construction cost per bed for a hospital, maintenance cost per hour, fuel cost per kilometer, construction cost per kilometer for a highway etc. Unit base method……. The total cost is calculated by multiplying the cost per unit factor with the number of units of the corresponding factor. For example, a preliminary estimate is required to estimate the cost of constructing a new house with floor area of 170 square meter. If the cost per square meter is Rs.26, 900 (assumed), then the cost of constructing the house will be Rs.45, 73,000 (Rs. 26,900x170). Similarly the preliminary cost estimate of constructing a given length of highway can be calculated by multiplying the unit cost i.e. construction cost per kilometer by the length of highway (in km) 2.2 Detailed estimate
After obtaining the administrative approval of the
concerned department against the rough cost estimate, the detailed estimate is prepared by P.W.D. department. As this estimate is based on the plans and sections of the building so it is the most accurateestimate. The quantities of items under various sub heads of work are calculated from the drawings and cost of each item is worked out separately according to the prevalentmarket rates and is totaled. After doing the total of all items a percentage of 3 to 5 is added for unforeseen items, change of design and provision of petty-establishment. Grand total so obtained gives the estimated cost of building. Detailed estimate….. This estimate is then submitted to the competent authority for according technical sanction. The competent authority may be Chief Engineer or Superintending Engineer of the P.W.D. department. The detailed estimate is accompanied by report, design and scope, detailed drawings, detailed specifications, justification of the rates provided and the limit for execution of the work. The work we executed according to the detailed estimate. 2.3 Revised estimate
When the cost of the estimate exceeds or likely
to increase by 10% or more, a revised estimate is required to be prepared. It is accompanied by the comparative statement showing the variations of each item of work and giving the reasons of excess. The excess may be due to change of design and scope of variation in rates etc. 2.4 Supplementary estimate
When some addition to the original work is
made a fresh detailed estimate for the additional work is prepared to supplement the original estimate and thus called supplementary estimate. This estimate is in addition to the original estimate. 2.5 Annual repair and maintenance estimate
This estimate is prepared to carry out annual
repairs or maintenance. The amount of annual repair estimate should not exceed more than 1 - 1/2% of the capital cost of the building. Annual repair are much common in road work for which annual repair estimates are prepared to carry out the work. 2.6 Extension and improvement estimate
When some changes and extensions are
required to be made in the old work, the cost of which cannot be met by the annual repair/maintenance estimate, a detailed estimate is prepared for such work which is called as Extension and Improvement estimate. 2.7 Complete estimate of work/project
• It should include following items;
1. The cost of land. 2. The cost of preliminary works such as feasibility study, investigation and surveying. 3. The cost of preparing preliminary design, drawings and estimates. 4. The cost for preparing detail design, drawing, estimate, specification and contract documents. Complete estimates…. 5. The cost of buildings including electrical installation, water supply and sanitation works. 6. The cost of providing temporary accommodation for constructional staff. 7. The cost of design and supervision charges. 8. The cost of external services. 9. The cost of maintenance and other repairs during the progress of works. 2.8 Split up of cost of building works ………..Thank you………..