Professional Documents
Culture Documents
In order to prepare a detailed estimate, the estimator must have with him the following data:
1. Plans, sections and other relevant details of the work.
2. Specifications indicating the exact nature and class of materials to be used.
3. The rates at which the different items of work are carried out.
To enable an estimator to take out the quantities accurately, the drawings must themselves be
clear, true to the fact and scale, complete, and fully dimensioned. The estimator has also to bear
in mind certain principles of taking out quantities.
Agreement. The agreement is the document that formalizes the construction contract, and it is the basic
contract. It incorporates by reference all of the other documents and makes them part of the contract. It
also states the contract sum and time allowed to construct the project.
General Conditions. The general conditions define the rights, responsibilities, and relations of all parties
to the construction contract.
Working Drawings. The actual plans (drawings, illustrations) from which the project is to be built are the
working drawings. They contain the dimensions and locations of building elements and materials required,
and delineate how they fit together.
Specifications. Specifications are written instructions concerning project requirements that describe the
quality of materials to be used and their performance.
Addenda. The addenda statement is a drawing or information that modifies the basic contract documents
after they have been issued to the bidder, but prior to the taking of bids. They may provide clarification,
correction, or changes in the other documents.
For projects built with the design-build and construction manager deliver systems, the contract
documents are more limited than for project built with the design-bid-build delivery system because the
contractor is involved in the design and selection of the specifications for the project. These documents can
be as simple as an agreement with a conceptual description of the project.
Unit I. Introduction to Quantity Surveying and Estimating, Data for Estimate, Purpose of
Estimating, Accompaniments of an Estimate, Qualities of an Estimator, Spot Items,
Contingencies, ,
A good working knowledge of the construction technology and methodology is required to be able to
write spot items, making it easy to visualise and price accurately.
In a bill of quantities, the measurement unit will be stated as ‘Item’, although quantities may be given if they
are considered more appropriate. Items that have quantities are generally much easier for
an estimator to price. Typically, spot items will be set out in progression from locationto location in
the building, as this makes monitoring and estimating easier and clearer.
Contingencies are downside risk estimates that make allowance for the unknown risksassociated
with a project.
Typically, contingencies refer to costs, and are amounts that are held in reserve to deal with
unforeseen circumstances. However, they may also refer to other aspects of the project, for
example, the programme may include a contingency where it is important that a
specific completion date is achieved.
A contingency may also refer to part of a contingency plan, which is a plan that can be enacted
to mitigate project risks, such as adverse weather, an industrial dispute, supplier failure, and so
on.
Monetary contingencies are typically referred to in relation to the overall client for a project.
However, other parties in the supply chain are also likely to include contingencies in their cost
planning.
While it is advisable for clients to hold a contingency, they might no wish to share this information
with the rest of the project team, who may see a contingency as a license to exceed the budget in
the knowledge that the client has a reserve that can be spent.
Contingencies are often expressed in terms of percentages. The percentage contingenciesapplied
are at their greatest in the early stages of the project when there are the greatest number of
possible risks. But they can then be reduced as better particulars about the projectbecome
available and some risks have passed or been overcome.
An example of how a contingency might be reduced during a project is set out below:
▪ At the preliminary business plan stage, total cost estimates might include a 15% contingency.
▪ In the elemental cost plan this might reduce to 10% of fees and construction costs.
▪ On awarding the contract, 5% of the contract value might be included as contingency in the cost
plan.
In addition to a contingency, the client is likely to hold retention. Retention is a percentage (often
5%) of the amount certified as due to the contractor on an interim certificate, that is deducted from
the amount due and retained by the client. The purpose of retention is to ensure that
the contractor properly completes the activities required of them under the contract. Retention can
also be applied to nominated sub-contractors, and the main contractor may also
apply retention to domestic sub-contractors.
Typically, Contingency refer to a cost, and is a percentage of a contract value set aside for
unforeseen circumstances or unpredictable changes in the scope of the work. The cost
contingency which is included in a cost estimate, bid, or budget may be classified as to its general
purpose, which is what it is intended to provide for. For a class 1 construction cost estimate,
usually needed for a bid estimate, the contingency may be classified as an estimating and
contracting contingency. This is intended to provide compensation for "estimating accuracy based
on quantities assumed or measured, unanticipated market conditions, scheduling delays and
acceleration issues, lack of bidding competition, subcontractor defaults, and interfacing omissions
between various work categories".
Confusion can arise regarding two items that may appear in standard forms of building
contract– prime cost sums (PC or PC sums) and provisional sums (PS). They both relate
to estimates made for certain costs in the absence of exact figures.
A prime cost sum is an allowance, usually calculated by the cost consultant, for
the supply of work or materials to be provided by a sub-contractor or supplier that will be
nominated by the client - that is, a supplier that is selected by the client to carry out an element of
the works and imposed on the main contractor after the main contractor has been appointed.
The main contractor is entitled to add mark up and attendance costs to the allowance. If the main
contractor's actual costs then turn out to be higher, the contract sum is increased, and if the main
contractor's actual cost is lower, the contract sum is reduced.
A provisional sum is an allowance, usually estimated by a cost consultant, for a specific element of
the works that is not yet defined in enough detail for tenderers to accurately price.
Depending on the degree to which the works that the provisional sum relates to can be described
at the tender stage, prime cost sums may be referred to as 'defined' or 'undefined'.
Prime Cost (PC) items and provisional sums (PS) are two items in a standard building contract
which cause great confusion among homebuyers. Most building contracts are called “fixed price
contracts”, but the final contract sum can vary due to fluctuations in PC and PS items.
A PC item is an amount of money included in a contract sum to purchase a specified item such as
tiles, taps, doors or bathroom fittings. An agreed estimated amount is included at contract signing
but the specific products are not selected until a later stage. Under the Home Building Contracts
Act (1991) a builder must estimate the cost of such items at or above the lowest amount these
items could reasonably cost, which must not be understated.
For example, if a client selects a more expensive door than allowed by the PC item, say a door
compared with a PC amount, a variation will be required to cover the additional If the PC item
varies, so will the final contract sum.
A provisional sum is an amount of money included in the contract sum to cover work or materials,
or both, the extent of which cannot be specifically detailed when entering a contract. Typically,
builders will include a PS for sitework costs. The builder is legally required to take reasonable
steps to ensure an accurate site works cost estimate. However, in some circumstances,
unforeseen events mean that the provisional sum is exceeded, sometimes by a significant
amount. This can be added to the contract sum.
For example, a building site may seem sandy and clean with minimal siteworks
required. However, there may be large limestone rocks or tree trunks concealed below the
surface which only emerge once siteworks commence, causing a considerable cost overrun.
Buyers need to plan for these contingencies. Careful upfront thinking about tile and door selection
or other PC items can ensure that an accurate PC amount is included in the contract. Moreover
having a “buffer” amount in your financial budget to cover any unexpected provisional sum
overruns is desirable.
Prime Cost
A prime cost is defined as ‘an item that has not been selected, or whose value is not known, at the
time a domestic building contract is entered into and for the cost of supply and delivery of which
the builder must make a reasonable allowance in the contract’
What this essentially means is that these are items that may not be selected yet – usually fixtures
and fittings such as handles, stovetops and tapware – as it’s too early in the process. In order to
ensure a consistent cost, the builder will make allowances for these items without knowing the
specific cost. This allowance will include any mark-up or profit from the builder, as well as sourcing
and installation costs.
Provisional Sums
A provisional sum is defined as ‘an estimate of the cost of carrying out particular work (including
the cost of supplying any materials needed for the work) under a domestic building contract for
which a builder, after making all reasonable enquiries, cannot give a definite amount at the time
the contract is entered into.’
This translates to works that the builder cannot accurately price at the time of contract signing, like
landscaping. It still includes both the provision of materials and the labour costs.
Most simply, prime cost applies to items themselves, provisional sums refers to complete works.
Unit I. 1.8 - Provisional Quantities,
Provisional quantity
Where work can be described and given in items in accordance with the tabulated rules
of measurement but the quantity of work cannot be accurately determined, an estimate of
the quantity shall be given and identified as a ‘provisional quantity’.
Work items identified as a ‘provisional quantity’ shall be subject to remeasurement when they have
been completed. The ‘approximate quantity’ shall be substituted by the ‘firm quantity’ measured,
and the total price for that item adjusted to reflect the change in quantity. Where the variance
between the ‘provisional quantity’ and the ‘firm quantity’ measured is less than 20 per cent, the
rate tendered by the contractor shall not be subject to review. Where the variance is significant
(i.e. 20 per cent or more), the rate can be reviewed to ensure that the rate is fair and reasonable to
both the employer and contractor.
Extra work is understood to fall outside the scope of the contract, i.e. work that wasn't
contemplated and requires an extra payment on the side of the client. Additional work, on the
other hand, is generally understood to include work which is necessary to perform the contract.
Extra Work [Construction Law] Law and Legal Definition. Extra work in construction law refers to
"that work which is not required under the contract. ... A contractor is generally, entitled to charge
for extra work that consists of labor and materials not contemplated by or subsumed within the
original contract.
Extra work is work falling outside the scope of the agreed upon services, often referred to as
‘scope creeping’. It is also work that should be paid for separately and is usually charged
afterwards. Extra work and additional work are often used interchangeably but are in fact two
different things.
Extra work is understood to fall outside the scope of the contract, i.e. work that wasn’t
contemplated and requires an extra payment on the side of the client. Additional work, on the
other hand, is generally understood to include work which is necessary to perform the contract.
Such work doesn’t entitle the supplier to an additional payment, since the scope of the contract
hasn’t been changed.
Extra work may arise in the situation that a client asks to do something else as well, or to look into
more detail into that other thing too. All these questions add up and may ultimately result in
significant costs afterwards. As a supplier, it is wise to lay down a clear extra work procedure prior
to the execution of the agreement. This prevents dreadful invoices afterwards and discussions
about what does and what doesn’t amount to extra work. Also make it clear against what rates
extra work is performed, which usually is the hourly rate but may be a discounted rate too. In all
cases, be upfront about it!
The obligation to pay extra work generally arises when the client asks for it or gives permission to
its execution. At that time, the client must be aware that more work incurs more costs. This
awareness may be evident from the circumstances of the case, but still it’s wise to make this as
unquestionable as possible