Professional Documents
Culture Documents
City of Olongapo
GORDON COLLEGE
Olongapo City Sports Complex, Donor Street
East Tapinac, Olongapo City
Tel. No. (047) 224-2089 loc. 314
KRISTINE B. TORRES
BSA 2-B
MANAGEMENT SCIENCE - 001
Activity Immediate
Time
Activity Predecessor(s)
(weeks)
A 3 none
B 4 A
C 2 B
D 5 B
E 4 C
F 3 D
G 2 E,F
A b C E
G
D F
2. USING THE NETWORK DIAGRAM CONSTRUCTED IN PROBLEM 1.
ABCEG 3+4+2+4+2= 15
ABDFG 3+4+5+3+2= 17
A C E
B D F
(b) Identify the critical path.
ACE 6+3+6= 15
BDF 5+3+9= 17
BDE 5+3+6= 14
B D F H
A J
C E G I
5. USING THE INFORMATION GIVEN, CALCULATE THE EXPECTED TIME
FOR EACH OF THE PROJECT ACTIVITIES.
Expected time =
Optimistic Time Estimate+ 4 ( Most likely time Estimates )+ Pessimistic Time Estimates
6
3+4 ( 6 ) +9 3+4 ( 4 )+5
A= ¿6 F= ¿4
6 6
3+4 (5 )+ 7 3+4 ( 6 ) +8
B= ¿5 G= ¿5.83
6 6
4+ 4 ( 7 )+ 12 5+4 (6 ) +10
C= ¿ 7.33 H= ¿ 6.5
6 6
4+ 4 ( 8 )+ 10 5+4 ( 8 ) +11
D= ¿ 7.67 I= ¿8
6 6
Activity A B C D E F G H I J
Expected 6 5 7.33 7.67 10.17 4 5.83 6.5 8 3
Time
( )
2
2 p−o
σ = Where: p = pessimistic activity time estimate
6
o = optimistic activity time estimate
2
σ of A= ( ) ()
9−3 2 6 2 2
6
=
6
=1 = 1
2
σ of F= ( ) ()
5−3 2 2 2
6
=
6
=0.33332 = 0.11
( ) () ( ) ()
2 2 2 2
7−3 4 8−3 5
σ 2 of B= = =0.66662 = 0.44 σ 2 of G= = =0.83332 = 0.69
6 6 6 6
σ of D=( ) = ( ) =1 = 1 σ of I =( ) = ( ) =1 = 1
2 2 2 2
2 10−4 6 2 2 11−5 6 2
6 6 6 6
Activity A B C D E F G H I J
Variance 1 0.44 1.78 1 3.36 0.11 0.69 0.69 1 0
4 A,C,E,F,H,J 6.94 37
(a) Calculate the probability that the project will be completed in 38 weeks.
(b) Calculate the probability that the project will be completed in 42 weeks.