Professional Documents
Culture Documents
ASSIGNMENT - TUTORIAL
Prepared for
Name Student ID
PEM2455B1/2
Sejati Perabut produces a variety of furniture products. Mr Alan, the production manager has
developed an aggregate forecast as shown in Table Q1a. Using information given in Table Q1b,
One unit of A is made of two units of B, three units of C and two units of D. B is composed of
one unit of E and two units of F. Item A, C, D and F have one week lead time while item B and E
have lead time of two weeks. Lot-for-lot (LFL) lot sizing is used for item A, B, C and D. Item E
required fixed order quantity (FOQ) of 50 units whereas for item F, the FOQ is 220. Item D has
an inventory of 50 units while the other items have zero inventory. There is a schedule receipt of
item E on WW2 with the quantity of 20 units. The schedule shipment until WW10 is
summarized in Table Q2. Draw a product structure and prepare material requirement planning
for all items.
QUESTION 3
Golden Coin Sdn Bhd is planning a new product project which consist of ten activities. The time
required for each activity and immediate predecessor are summarized in Table Q3.
1. Draw a network diagram and list the available path including duration for each path.
2. Identify the critical path and project duration.
3. Determine the slack for each activity.
4. Elucidate what will happen to project duration if activity G and H are delays for 3 days.
QUESTION 1 (i)
Period 1 2 3 4 5 6 Total
Forecasted
Demand (D) 50 45 55 60 50 40 300
Regular
Output (O) 40 40 40 40 40 40 240
Overtime 8 8 8 8 8 4 44
Subcontract 4 12 16
Hire/Layoff
(O)-(D) -2 3 -3 0 -2 4
Inventory
Begin 0 0 1 0 0 0
End 0 1 0 0 0 0
Average 0 0.5 0.5 0 0 0 1
Backlog 2 0 2 2 4 0 10
Costs
Reg
prodn-normal
(80$/unit) 3200 3200 3200 3200 3200 3200 19200
OT
(120$/unit) 960 960 960 960 960 480 5280
Backorders
(20$/unit) 40 0 40 40 80 0 200
Subcontracting
(RM 140/unit) 0 0 560 1680 0 0 2240
Hire
(RM b/wkr)
Layoff
(RM c/wkr)
Inventory
(RM 10/unit) 0 5 5 0 0 0 10
TOTAL 26930
QUESTION 01 (ii)
Period 1 2 3 4 5 6 Total
Forecasted
Demand (D) 50 45 55 60 50 40 300
Regular
Output (O) 40 40 40 40 40 40 240
Overtime 8 8 8 8 8
Subcontract 2 4 12 2
Hire/Layoff
(O)-(D) 0 3 -3 0 0 0 0
Inventory
Begin 0 0 3 0 0 0
End 0 3 0 0 0 0
Average 0 1.5 1.5 0 0 0
Backlog
Costs
Reg
prodn-normal
(80$/unit) 3200 3200 3200 3200 3200 3200 19200
OT
(120$/unit) 960 960 960 960 960 0 4800
Backorders
(20$/unit)
Subcontracting
(RM 140/unit) 280 0 560 1680 280 0 2800
Hire
(RM b/wkr)
Layoff
(RM c/wkr)
Inventory
(RM 10/unit) 0 15 15 0 0 0 30
TOTAL 26830
QUESTION 02 (i)
QUESTION 02 (ii)
Begin
Week number inv 1 2 3 4 5 6 7 8 9 10
Quantity 0 100 50 200
Begin
Week number inv 1 2 3 4 5 6 7 8 9 10
(2)10 (2)20
Quantity 0 0 (2)50 0
Begin
Week number inv 1 2 3 4 5 6 7 8 9 10
(3)10 (3)20
Quantity 0 0 (3)50 0
Begin
Week number inv 1 2 3 4 5 6 7 8 9 10
(2)10 (2)20
Quantity 0 0 (2)50 0
Begin
Week number inv 1 2 3 4 5 6 7 8 9 10
(4)10 (4)20
Quantity 0 0 (4)50 0
No Path Duration
1 A,B,D,G,J 18
2 A,B,E,G,J 17
3 A,B,F,H,J 26
4 A,B,F,I,J 25
5 A,C,F,H,J 27
6 A,C,F,I,J 26
A,C,F,H,J
Project Duration = 2+5+8+5+7=27
iii. The slack for each activity.
iv. What will happen to project duration if activities G and H are delayed for 3 days?
The following task after G and H, which is J, will also be delayed. Due to tasks H and J being on the
critical path, the project duration will increase. The project duration will increase from 27 to 30