Question 1
Find the duration of each project, fill in all the tables and the CPN network
Action Predecessor Duration
(weeks)
A - 2
B - 5
C - 4
D B 5
E A 8
F A 3
G B 3
H C,D 6
I C,D 3
J E 5
K F,G,H 4
L F,G,H 2
M I 12
N J,K 10
Question 2 : Find the duration of each project, fill in all the tables and the
CPN network
Action Predecessor Duration
(weeks)
A - 9
B A 4
C - 4
D - 2
E D 4
F B 7
G B 6
H G 3
I E 6
J C,D 2
K D 9
L F,H 2