Critical path analysis is a method for scheduling complex projects that involves identifying the critical path of activities that must be completed on time to finish the project on schedule. It determines the earliest and latest possible dates for activities, calculates float to identify how much delay activities can tolerate, and calculates the minimum overall project duration. The key steps are performing forward and backward passes to calculate early and late dates, determining float, and identifying critical activities with zero float on the critical path.
Critical path analysis is a method for scheduling complex projects that involves identifying the critical path of activities that must be completed on time to finish the project on schedule. It determines the earliest and latest possible dates for activities, calculates float to identify how much delay activities can tolerate, and calculates the minimum overall project duration. The key steps are performing forward and backward passes to calculate early and late dates, determining float, and identifying critical activities with zero float on the critical path.
Critical path analysis is a method for scheduling complex projects that involves identifying the critical path of activities that must be completed on time to finish the project on schedule. It determines the earliest and latest possible dates for activities, calculates float to identify how much delay activities can tolerate, and calculates the minimum overall project duration. The key steps are performing forward and backward passes to calculate early and late dates, determining float, and identifying critical activities with zero float on the critical path.
• Method of scheduling projects-developped after World War II • Multi-task complex projects to ensure that the scheme is completed in minimum time • E.g used in Apollo moonshot project, development of the Concorde • Help you identify the activities that must be completed on time in order to complete the whole project on time. • Show you which tasks can be delayed and for how long without impacting the overall project schedule. • Calculate the minimum amount of time it will take to complete the project. • Tell you the earliest and latest dates each activity can start on in order to maintain the schedule • The CPM involves 4 main steps: • - A forward pass to determine activities early- start times; • - A backward pass to determine activities late- finish times; • - Float calculations; and • - Identifying critical activities. • Forward pass : Early Start (ES) + duration • Backward Pass : Late Finish (LF) - duration • Float is the amount of time an activity can slip without causing the project to be delayed • Float = Late Start (LS) – Early Start (ES) • Activities on the Critical Path have a float of zero. Ex 1: (i) Draw the network diagram for the following activities; (ii) Calculate project duration; (iii) Calculate float for each activity; and (iv) Identify the critical path.
Activity Dependence Duration
A _ 4 B A 3 C _ 3 D _ 5 E _ 2 F E 2 G D 4 H D 6 J B, C, D 2 K F, G 6