Activity A B C D E F
2. Predecessor -- -- A A B D, E
Duration 10 8 14 7 6 8
Activity A B C D E F G
3. Predecessor -- -- -- A B C D
Duration 1 2 2 1 3 2 1
Activity A B C D E F
4. Predecessor -- -- B A, C A D, E
Duration 5 1 2 4 6 3
Activity A B C E F G H
5. Predecessor -- A A B, C C C F, E, G
Duration 8 10 5 12 5 7 5
Activity A B C E F G H K M
6. Predecessor -- A B C C, E F B H, F G
Duration 8 10 5 20 5 5 17 12 2
Activity A B C D E F G H I
7. Predecessor -- -- A B C, D C, D E F G, H
Duration
Activity A B C D E F G H I
8. Predecessor -- A B A C, D E D E G, H
Duration 20 10 8 11 7 6 12 13 5
Activity A B C D E F G H I
9. Predecessor -- -- -- A A B, D C C F, G
Duration 10 12 8 13 14 18 14 12 12
Activity A B C E F G H K M N
10. Predecessor -- -- B B A, C A, C F, E E K G
Duration 4 3 5 7 6 8 8 4 3 5
Activity A B C D E F G H I J
11. Predecessor -- -- A A, B C A, B F G G I
Duration 40 20 15 25 15 25 10 15 10 15
Best Wishes,
Eng. Elin Eldars
1
Ministry of Higher Education
High Institute for Engineering and Technology, New Damietta
Civil Engineering Department
ENG-408 [Project Management and Control]
Activity A B C D E F G H I J K
12. Predecessor -- -- A A, B C C C D, E F F, G H
Duration 4 3 7 6 3 2 4 5 7 2 4
Activity A B C D E F G H I
13. Predecessor -- -- A A B B A, C, E C, D, E, F F, G, H
Duration
Activity A B C D E F G H I J
14. Predecessor -- -- A, B A C A, B A, B, C, F G D, G I, H
Duration
Activity A B C D E F G H I J K L
15. Predecessor -- -- A B C D D D E, F G, I G, I H, J
Duration 5 7 6 9 4 11 8 6 8 6 2 5
Activity A B C D E F G H I J K
16. Predecessor -- A -- C A, D -- F C C B, E, F, G H, I, J
Duration 3 3 1 2 8 4 1 4 12 6 4
Activity A B C D E F G H I J K L M N
17. Predecessor -- A B B B C D, E F G, H I I J K L
Duration 1 2 4 3 2 3 5 1 4 2 3 3 5 4
From 1 2 2 3 3 3 4 4 5
19. To 2 3 4 4 5 6 5 6 6
Time 4 3 2 0 4 5 7 7 6
From 1 1 1 1 2 3 4 4 4 5 6
20. To 2 3 5 6 3 4 5 7 6 7 7
Time 10 20 2 5 0 10 0 3 0 1 8
Activity A B C D E F G
Predecessor -- -- B B C A D
21.
Duration 10 4 3 4 2 12 1
- If all other activities take the estimated amount of time, what is the maximum duration of activity D without delaying the project?
Activity A B C D E
Predecessor -- -- A, B A, B D
22. Duration 2 3 2 2 3
- After delaying one week of the start of the schedule; the manager has already finished activity A, and all the other activities are right on
schedule. Will this shorten the length of the project? Why / Why not?
Activity A B C D E F G H I J K
Predecessor -- -- A A, B A, C A A C, G H I C, F
23. Duration 2 1 2 2 3 2 1 1 1 3 4
- After delaying one week of the start of the schedule; the manager has already finished activity A, and all the other activities are right on
schedule. Will this shorten the length of the project? Why / Why not?
Activity A B C D E F G H I J K L
Predecessor -- A -- C -- E -- G H I, F, D, B E J, K
24. Duration 30 5 2 3 7 25 15 10 2 10 15 30
- If activity E is interrupted for 6 minutes, by how much will the project be delayed?
- If you use a processor, which reduces the time from 7 to 2 minutes, will the project still be delayed?
Best Wishes,
Eng. Elin Eldars