Professional Documents
Culture Documents
PRESENTED BY:
CPM
• Developed by El Dupont for Chemical Plant Shutdown
Project
Three Phases of PERT/ CPM
The three phases of PERT/ CPM are:
• Planning
• Scheduling
• Control-Monitor
1. Planning
• The process of identifying all the activities necessary
to successfully complete the project.
Node: Connector:
Network
START/
END
Milestone
Dummy
A,1 Activity/Event
Critical
Activity-on-Node (AON)
ACTIVITY ACTIVITY
A B
Activity-on-Arrow (AOA) 2
A D F
Activity A Activity B
Event 1 Event 2 Event 3 2 3 4
1 B 5 G 6
6 2
C
E
4 5
3
STEP 1
CREATE TABULATION
DURATION
ACTIVITY PREDECESSOR
(days)
A - 2
B - 6
C - 4
D A 3
E C 5
F A 4
G B,D,E 2
STEP 2
Graph Logical Networking
A,2 F,4
D,3
C,4 E,5
STEP 3
IDENTIFY CRITICAL PATH
A,2 F,4
D,3
AF =2+4 =6
ADG = 2+3+2 =7 C,4 E,5
BG = 6+2 =8
CEG= 4+5+2 = 11 days
Forward Pass Procedure ES EF
Activity
L
EFi = ES i + D i LS F
0 A
2 2 F
6
ES i= Maximum EFi of
predecessor(s) 2 D 5
9
0 0 0 6 11 11 11
START B G END
4
0 4 9
C E
Backward Pass Procedure ES EF
Activity
L
LS i = LF i - D i LS F
0 A
2 2 F
6
LF i = Maximum LS i of
successor(s) 4 6 2 D 5 7 11
6 9
0 0 0 6 9 11 11 11
START B G END
0 0 3 9 11
4 9 11 11
0 4 9
C E
4
0 4 9
SUMMARY
SLACK ON
PREDECESSO DURATION
ACTIVITY ES EF LS LF TIME CRITICAL
R (week)
(LS-ES) PATH?
A - 2 0 2 4 6 4 NO
B - 6 0 6 3 9 3 NO
C - 4 0 4 0 4 0 YES
D A 3 2 5 6 9 4 NO
E C 5 4 9 4 9 0 YES
F A 4 2 6 7 11 5 NO
G B,D,E 2 9 11 9 11 0 YES
PERT
m eaning
m a b te s^2
ACTIVITY PREDECESSOR
(days) (days) (days) (days) (days)
A - 2 1 4 2 0.250
B - 6 5 8 6 0.250
C - 4 2 8 4 1.000
D A 3 1 5 3 0.444
E C 5 4 7 5 0.250
F A 4 3 6 4 0.250
G B,D,E 2 1 5 2 0.444
Critical Path: C-E-G ES EF
Activity
0 6 L
2 2
A F LS F
6 2 5 7 11
4 D
6 9
0 0 0 6 9 11 11 11
START B G END
0 0 3 9 11
4 9 11 11
0 4 9
C E
4
0 4 9
P E RT
Probability Concept
Standard Deviation
P E RT
Probability that the project will be completed in 12 days
P E RT
z=0.76
ψ(z)= 0.7764
z=0.77
ψ(z)= 0.7794
Event-oriented Activity-oriented
Non-repetitive Repetitive
https://asana.com/resources/critical-path-method
https://slideplayer.com/slide/8567593/
https://dokumen.tips/documents/7-project-planning-and-sc
heduling-ppt-ibse-2019-3-18-project-planning-a.html?page=
33