Professional Documents
Culture Documents
Problems: Chapter 12
Bill B. Cohen
December 7, 2014
MODULE 7 ACTIVITY 7.6 1
Q12-15 The following are the activity times for the project in Problem 12-14. Find
the earliest, latest, and slack times for each activity. Then find the critical path.
F G
Finish
Start
A C
B D
With the EF formula below, the earliest time t (in days) for each activity can be
determined:
= +
Given that ES is the earliest start time an activity can begin without violation of
immediate predecessor requirements and (t) is the expected activity time. Similarly, the
latest start time (LS) for each activity can be calculated through via:
LF reflects the latest finish time or the smallest of the latest start times and the slack is
= =
Activities B, D, E, and G are on the critical path since they have no slack time.
the process of designing a program that its customers can use in the job-finding
process. Some of the activities include preparing resumes, writing letters, making
and so on. Some of the information on the activities is shown in the following table:
DAYS
IMMEDIATE
ACTIVITY a m b PREDECESSORS
A 8 10 12
B 6 7 9
C 3 3 4
D 10 20 30 A
E 6 7 8 C
F 9 10 11 B, D, E
G 6 7 10 B, D, E
H 14 15 16 F
I 10 11 13 F
J 6 7 8 G, H
K 4 7 8 I, J
L 1 2 4 G, H
MODULE 7 ACTIVITY 7.6 3
I
A D
F K
Start B
H
C
E G
J
L Finish
The expected time (t) for each activity is calculated using the beta distribution weights
formula below:
+ 4 +
=
6
Given that (a) is the optimistic time, b is the pessimistic time, and m is the most realistic
estimated time to complete the activity. In addition, the variance is also calculated via:
2
= ( )
6
Given that a in the equations represents the optimistic time, and b is the pessimistic time.
The expected times (rounded to a full day) and variances for each activity are:
MODULE 7 ACTIVITY 7.6 4
EXPECTED
EXPECTED
ACTIVITY VARIANCE TIME
TIME
ROUNDED
A 10.00 0.44 10.00
B 7.17 0.25 8.00
C 3.17 0.03 4.00
D 20.00 11.11 20.00
E 7.00 0.11 7.00
F 10.00 0.11 10.00
G 7.33 0.44 8.00
H 15.00 0.11 15.00
I 11.17 0.25 12.00
J 7.00 0.11 7.00
K 6.67 0.44 7.00
L 2.17 0.25 3.00
The earliest finish time (EF) for each activity is calculated via:
= +
Given that expected activity time (t) and the earliest start time an activity can begin
without violation of immediate predecessor requirements (ES), the latest start time (LS)
for each activity is calculated through the use of the following formula:
With LF as the latest finish time or the smallest of the latest start times to finish an
activity, the slack can be calculated via the formula below with the following results:
= =
The critical paths for the projects schedule are activities A, D, F, H, J, K, and L because
they reflect no slack time. Therefore, the completion time is approximated to 69 days.
e. Determine the probability that the project will be finished in 70 days or less.
The project variance must be calculated by averaging the variances of each activity in
order to determine the probability that the project will be finished in 70 days or less. The
project variance is calculated to be 1.14. To calculate the projects standard deviation, the
square root of the average variance results in 1.06. Assuming normal distribution, the
number of standard deviations the due date lies from the expected date is calculated via:
=
()
70 69
= = 0.9433
1.06
MODULE 7 ACTIVITY 7.6 6
f. Determine the probability that the project will be finished in 80 days or less.
Taking into assumption that the values for standard deviation and expected date of
80 69
= = 10.3774
1.06
Since 10.3774 is outside the normal distribution table, there is a 100% chance that the
g. Determine the probability that the project will be finished in 90 days or less.
Again, assuming that the values for the standard deviation and expected date of
90 69
= = 19.8113
1.06
Since 19.8113 falls outside the normal distribution table, there is a 100% chance that the
Q12-21 The air pollution project discussed in the chapter has progressed over the
past several weeks, and it is now the end of week 8. Lester Harky would like to know
the value of the work completed the amount of any cost overruns or underruns for
the project, and the extent to which the project is ahead of or behind by developing
a table like Table 12.8. The revised cost figures are shown in the following table:
MODULE 7 ACTIVITY 7.6 7
PERCENT OF ACTUAL
ACTIVITY
COMPLETION COST
A 100 $20,000.00
B 100 $36,000.00
C 100 $26,000.00
D 100 $44,000.00
E 50 $25,000.00
F 60 $15,000.00
G 10 $5,000.00
H 10 $1,000.00
Taking into assumption that the total budgeted costs for each activity are the same, the
updated values of work completed are calculated using the following formula:
= ( ) ( )
The activity differences are also determined and represented in results below:
TOTAL VALUE OF
PERCENT OF ACTUAL ACTIVITY
ACTIVITY BUDGETED COMPLETED
COMPLETION COST DIFFERENCE
COST WORK
A $22,000.00 100 $22,000.00 $20,000.00 $(2,000.00)
B $30,000.00 100 $30,000.00 $36,000.00 $6,000.00
C $26,000.00 100 $26,000.00 $26,000.00 $--
D $48,000.00 100 $48,000.00 $44,000.00 $(4,000.00)
E $56,000.00 50 $28,000.00 $25,000.00 $(3,000.00)
F $30,000.00 60 $18,000.00 $15,000.00 $(3,000.00)
G $80,000.00 10 $8,000.00 $5,000.00 $(3,000.00)
H $16,000.00 10 $1,600.00 $1,000.00 $(600.00)
TOTAL $181,600.00 $172,000.00 $(9,600.00)
In comparison to the previous data in which the project did not progress as much, there
were more overruns per activity than the current state. While only activity B reflects an
overrun of $6,000 in the actual state, the only activity that met its budget is activity C.
The remaining activities have underruns for a total project underrun of $9,600.
MODULE 7 ACTIVITY 7.6 8
Q12-31 The managing partner of the Scott Corey accounting firm (see problem 12-
30) has decided the system must be up and running in 16 weeks. Consequently,
information about crashing the project was put together and is shown in the
following table:
NORMAL CRASH
IMMEDIATE NORMAL CRASH
ACTIVITY TIME TIME
PREDECESSORS COST COST
(WEEKS) (WEEKS)
A 3 2 $8,000.00 $9,800.00
B 4 3 $9,000.00 $10,000.00
C A 6 4 $12,000.00 $15,000.00
D B 2 1 $15,000.00 $15,500.00
E A 5 3 $5,000.00 $8,700.00
F C 2 1 $7,500.00 $9,000.00
G D, E 4 2 $8,000.00 $9,400.00
H F, G 5 3 $5,000.00 $6,600.00
crashed to do this at the least additional cost? What is the total cost of this?
The critical path activities for the project are A, E, G, and H and the crash cost per time
CRASH
CRASH
COST
ACTIVITY COST/TIME CRITICAL?
PER
PERIOD
WEEK
A 1800 3600 YES
B 1000 3000 NO
C 1500 6000 NO
D 500 500 NO
E 1850 5550 YES
F 1500 1500 NO
G 700 1400 YES
H 800 2400 YES
MODULE 7 ACTIVITY 7.6 9
Since activity G reflects the lowest crash cost per week of $700 to meet the new goal of
16 weeks, activity G will be used to crash the project by one week. Therefore, the total
b. List all the paths in this network. After the crashing in part a. has been done, what
is the time required for each path? If the project completion time must be another
week so that the total time is 15 weeks, which activity or activities should be
activity that is not the least cost for crashing if it is on several paths rather than to
crash several activities on separate paths when there is more than one critical path.
C F H
Start
A
E G
Finish
B D
In conclusion, if the project has to be crashed again to finish it in 15 weeks, then activity H
should be crashed by a week in addition to activity G for the purpose of providing the
shortest possible activity time regardless of the fact that this activity is not lowest in cost.
MODULE 7 ACTIVITY 7.6 11
References:
Render, B., Stair, R., and Hanna, M., (2012). Quantitative analysis for management (11th Ed).
Upper Saddle River, NJ: Prentice Hall.