Professional Documents
Culture Documents
PERT
Slide 1
Chapter 5
PERT/CPM
Slide 2
PERT/CPM
Slide 3
Project Network
Slide 4
Determining the Critical Path
Slide 5
Determining the Critical Path
Slide 6
Determining the Critical Path
Slide 7
Uncertain Activity Times
Slide 8
Uncertain Activity Times
Slide 9
Example: ABC Associates
H
A E
I
C F
Start Finish
K
B G
Slide 11
Example: ABC Associates
Earliest/Latest Times
Activity ES EF LS LF Slack
A 0 6 0 6 0 *critical
B 0 4 5 9 5
C 6 9 6 9 0*
D 6 11 15 20 9
E 6 7 12 13 6
F 9 13 9 13 0*
G 9 11 16 18 7
H 13 19 14 20 1
I 13 18 13 18 0*
J 19 22 20 23 1
K 18 23 18 23 0*
• The estimated project completion time is the Max EF
at node 7 = 23. Slide 13
Example: ABC Associates
Slide 14
Example: ABC Associates
= 1.414
Slide 15
PERT/Cost
Slide 16
PERT/Cost
Slide 17
Example: How Are We Doing?
G I
A 3 4
9
F H
B 4 5
Start Finish
8
D
3
J
E 8
4
C
10
Slide 18
Example: How Are We Doing?
Earliest/Latest Times
Activity ES EF LS LF Slack
A 0 9 0 9 0
B 0 8 5 13 5
C 0 10 7 17 7
D 8 11 22 25 14
E 8 12 13 17 5
F 9 13 13 17 4
G 9 12 9 12 0
H 12 17 12 17 0
I 12 16 21 25 9
J 17 25 17 25 0
Slide 19
Example: How Are We Doing?
Slide 20
Example: How Are We Doing?
C 11
1 12
Slide 22
Example: How Are We Doing?
Corrective Action
Note that the project is currently experiencing a
$900 cost underrun, but the overall completion time is
now 25.5 weeks or a .5 week delay. Management
should consider using some of the $900 cost savings
and apply it to activity G to assist in a more rapid
completion of this activity (and hence the entire
project).
Slide 23
Critical Path Method
Slide 24
The End
Slide 25