Professional Documents
Culture Documents
TECHNIQUE (PERT)
PROJECT EVALUATION REVIEW TECHNIQUE, (PERT)
Being a critical path method, PERT has got similarities with CPM.
8
Time Estimates in PERT
9
Properties of Normal Distributions
10
11
Properties of Normal Distributions
A - 5 6 7 6 0.33 0.1089
B A 4 5 18 7 2.33 5.428
C A 4 15 20 14 2.67 7.1289
D B 3 4 5 4 0.33 0.1089
E B, C 5 16 21 15 2.67 7.1289
F C 10 14 18 14 1.33 1.7689
G D,E,F 11 15 19 15 1.33 1.7689
Solution:
• Expected Project time = 50 Days
• Critical Activities= A-C-E-G
• Non-Critical Activities= B-D-F
• Z0(37)=-3.23 0.062 %
• Z0(20)=0 50 %
• Zo(57)=1.742= 95.9%
Example no 3 Draw Arrow Network and perform the PERT calculations
for the following schedule of the Project.
Determine probability at 50 days
Activity IPA Optimistic Most Likely Pessimistic
A - 1 2 3
B A 3 6 15
C A 4 10 16
D A 2 4 6
E B 4 7 10
F B,C 3 5 7
G C,D 1 3 11
H E,F 4 5 18
I G,H 1 2 9
Assignment Problems
THANK YOU !