Professional Documents
Culture Documents
Network-Planning Models
PERT
PERT
• PERT is used to plan projects with uncertain time estimates.
• Instead of a single time estimate, three time estimates are used:
• Minimum – Optimistic Time - a
• Maximum – Pessimistic Time - b
• Most likely – Most Likely Time – m
Z = ---------------------
√
A project has the following activities and time estimates for these
activities.
Time estimates (Weeks)
Activity a m b Immediate
predecessor
A 1 4 7 -
B 2 6 7 A
C 3 4 6 D
D 6 12 14 A
E 3 6 12 D
F 6 8 16 B,C
G 1 5 6 E,F
• Calculate the expected time and variance for each activity.
• Draw the critical path diagram
• Show the early start, early finish, late start and late finish times
• Show the critical path
• What is the probability that the project can be completed in 34
weeks?
Activity Expected time Activity variance
A
B
C
D
E
F
G
• Compute ES,EF,LS,LF for all activities
• Find out the critical path
• Find out the length of the critical path
• Compute the sum of variances of activities on the critical path.
• Compute the value of Z
• Find out the probability of completing it by the given time.