Professional Documents
Culture Documents
EVENT NETWORK
THE GANTT CHART
- is a popular tool for planning and scheduling simple projects;
- serves as an aid of the manager to schedule project activities and then to monitor progress
overtime by comparing the planned progress to the actual work progress;
- once completed, the chart indicate which activities were to occur, their planned duration
and when they were to occur.
Other information from the chart includes:
1. The ongoing activities on any date can be seen from the diagram by using a straight
edge or ruler vertically on the desired date intersecting the arrows representing the
activities. The arrows intersected by the straight edge or ruler are the activities
supposed to be ongoing on that date. By reviewing the individual project program, the
number of men machines and materials supposed to be used on the project on such
date can be determined.
2. The request for time extension of the project can be determined by looking at the
diagram. If the delay is due to reasons beyond the control of man such as rain, flood
and typhoon and such delay is along the critical path, the request should be
considered. But if the delay is along a lax path, the time extension request should not
be granted if the delay incurred is less than the total float of the activity that has been
delayed.
The consequence of employment fluctuation and equipment utilization adds to the cost of the
project. This is a problem where the only solution is to keep employment at an acceptable level.
The use of activity float to level resource requirement is illustrated in the following hypothetical
project. The following figure is a time scaled CPM network with man power loading chart.
B- 4 days
E- 5 days
C- 7 days
A- 11 days
At this point activity A with 11 days is already finished, activity D and F has
a remaining balance of 1 day of their target time duration.
11) Assume 30 men as a target level of workers per day try to flatten all humps over and raise
all dips under 30 of the Time Scaled Network and Manpower Loading of Figure 7-8.
12) Try first the activities with Free Float and schedule at the peak periods. These activities
may be re-scheduled by moving them to a period where resources requirements are low.
13) For the first four days activity, there are 40 men and to bring this down to a level of 30
men, one of the starting activities will have to delayed.
14) The Float Status of the four activities involved will be as follows:
a) Activity A has 6 days Free Float between EF of A and ES (17 – 11 = 16) see Figure 7-
8.
b) Activity B has 5 days Free Float between EF of D and ES (17 – 12 = 5) see Figure 7-
8.
c) Activity E has 7 days Free Float between EF of E and ES of H, (12 – 5 = 7) see Figure
7-8.
d) Activity C is critical. Thus, activity C has the priority to use the limited resources.
15) Activity B has no Free Float, hence, will not be moved unless there is no more alternative.
16) If the activity E will be delayed by 4 days, the utilization of manpower for the first 4 days
will be 25 days only.
17) By delaying activity A by 4 days, the manpower utilization for the first 4 days is 30.
Therefore, we choose to delay activity A by 4 days.
18) The 5th day has a manpower requirements of 45. By further analysis, we have the following
alternatives:
a) Delay activity A by one more day
b) Delay activity D by one day which is logical because the men under this activity is not
yet working
c) Stop activity E for one day but is not advisable because the men are already working.
19) By alternative (a) still have 35 men required for the 5th day. Alternative (b) is recommended
for it satisfy the 30 men target manpower per day.
20) Figure 7-9 is the result of partially leveled schedule. From the 8th to 15th day, the manpower
requirements exceed 30. Therefore, the best alternative combination is to delay the start
of activity K to the 22nd day. Delay the start of activity one by one and delay B to start on
the 16th day.
21) Figure 7-11 shows the total leveled schedule. As a rule “It is not possible to bet a
completely leveled schedule for a real project.”
22) The problem would be complicated if there are more than one resources that has to be
leveled. It is therefore practical to have a gradual build-up in work force followed by an
equal tapering drop at the end of the project.
EQUIPMENT CONSTRAINTS
If the equipment fluctuate or goes up and down, some equipment would be idle for some time
and if rented for a short periods, the rental might be too high due to fixed expenses for moving
in and out of the project.
To handle activities competing for the same resources, it is usually performed in a series rather
than the following simple construction case. The construction of an office building with two
separate units is to be undertaken concurrently and that the project is to be considered finished
after completion of the two units.
The five phases of construction using equipment are shown on the following table:
There is one constraint in the construction. The availability of a crane. Excavation will be done
by clamshell and the positioning of the prefab panels by crane. Only one crane will be available
at the project site at all times. Manpower is unlimited. The problem is to make a schedule having
the shortest project duration.
If the resources is unlimited, the construction of the two units could be done concurrently and
finished in 30 weeks. The sequence of the activities is in accordance with the technological
requirements and the critical path is along the activities of unit B (Fig.7-12)
Considering the equipment constraint and the excavation of foundation plus the positioning of
the prefab panels are the activities that requires the services of a crane. The following
alternatives can be drawn up in the revision of the schedule.
ANALYSIS:
1. Making a graphical analysis of alternative-1, we have Fig. 7-13. The project duration is
36 weeks, which is 4 weeks longer than 32 weeks when there is no constraint (Fig. 7-12)
2. For alternative-2, we have Fig 7-14. The project duration is 38 weeks longer by 6 weeks
3. Making the graphical analysis of alternative-3 and alternative-4, we have Fig. 7-15 and
7-16 respectively.
4. By comparison, alternative four of Fig. 7-16 has the shortest time duration of 34 weeks
and therefore, is recommended in the execution of the work.
In the above illustration, it could be seen that an arbitrary selection of a possible sequence fives
us no assurance of good schedule. On the contrary, a complete enumeration of all the possible
schedules for a more complex projects is time consuming and therefore is not advisable
Optimistic Time
- is the estimated minimum time an activity will take;
- is the expected activity duration when all the breaks are right. Its probability is
about 1 in 100 or 1% represented by letter a (see figure).
Most Likely Time or Probabilistic Time
- is the estimated normal length of time an activity takes;
- is the time expected that will most frequently be required for an activity if it were
done again and again under identical conditions represented by letter m (see
figure).
Pessimistic Time
- is the estimated maximum time that will be required under the worst condition.
- Its probability is about -1 in 100 or 1% represented by letter b (see figure).
FREQUENCY DIAGRAM
However, to compute probabilities, there is a need to understand some particular
terms used in Statics such as:
- Frequency distribution
- Normal curve or normal probability curve
- Standard deviation
- Normal deviate or probability factor