LEGENDS:

Precedence Relations and Durations for Nine Activity Project


ES – Early Start ACTIVITY DESCRIPTION PREDECESSO DURATIO
RS N
EF – Early Finish Site Clearing --------- 4
A
LS – Late Start B Removal of trees --------- 3
General Excavation A 8
LF – Late Finish C
Grading General Area A 7
D
Excavation for trenches B, C 9
E
Placing formwork and reinforcement for concrete B, C 12
- Critical Activities
F
Installing Sewer Lines D, E 2
G
Installing other utilities D, E 5
H
Pouring Concrete F, G 6
I

0 4 4

0 0 4

4 8 12

4 0 12

4 3 7

9 5 12

12 12 24

12 0 24

21 5 26

H
25 4 30

21 2 23

28 7 30

24 6 30

24 0 30

30 0 30

FINISH

30 0 30

12 9 21

E
ES EF
16 4 25

0 0 0

START

0 0 0
LS LF
4 7 11

18 14 25

ES EF ES EF