ACTIVITY PREDECESSOR OT MT PT 4tm OT + (OT+4MT+PT)/6 Expected
4MT+ PT Time A - 9 12 15 48 72 12 12 B - 5 9 13 36 54 9 9 C A 8 10 12 40 60 10 10 D B 7 9 17 36 60 10 10 E B 18 23 34 92 144 24 24 F A 9 9 15 36 60 10 10 G C 30 35 40 140 210 35 35 H D 35 39 49 156 240 40 40 I A 12 15 18 60 90 15 15 J E,G,H 3 3 9 12 24 4 4 K F,I,J 7 9 11 36 54 9 9
Network Diagram
D H
10 40
24 J
B 4 K
9 G
35 9
12 C 10 10
15 ES/EF/LS/LF/SLACK
ACTIVI PREDECESS Durati ES EF LS LF SLACK TIME
TY OR on A - 12 0 12 2 14 2 B - 9 0 9 0 9 0 C A 10 12 22 14 24 2 D B 10 9 19 9 19 0 E B 24 9 33 35 59 26 F A 10 12 22 14 24 2 G C 35 22 57 24 59 2 H D 40 19 59 19 59 0 I A 15 12 27 48 63 36 J E,G,H 4 59 63 59 63 0 K F,I,J 9 63 72 63 72 0