Project Management

Expected time

ACTIVITY PREDECESSOR OT MT PT 4tm OT + (OT+4MT+PT)/6 Expected


4MT+ PT Time
A - 9 12 15 48 72 12 12
B - 5 9 13 36 54 9 9
C A 8 10 12 40 60 10 10
D B 7 9 17 36 60 10 10
E B 18 23 34 92 144 24 24
F A 9 9 15 36 60 10 10
G C 30 35 40 140 210 35 35
H D 35 39 49 156 240 40 40
I A 12 15 18 60 90 15 15
J E,G,H 3 3 9 12 24 4 4
K F,I,J 7 9 11 36 54 9 9

Network Diagram

D H

10 40

24 J

B 4 K

9 G

35 9

12 C 10 10

15
ES/EF/LS/LF/SLACK

ACTIVI PREDECESS Durati ES EF LS LF SLACK TIME


TY OR on
A - 12 0 12 2 14 2
B - 9 0 9 0 9 0
C A 10 12 22 14 24 2
D B 10 9 19 9 19 0
E B 24 9 33 35 59 26
F A 10 12 22 14 24 2
G C 35 22 57 24 59 2
H D 40 19 59 19 59 0
I A 15 12 27 48 63 36
J E,G,H 4 59 63 59 63 0
K F,I,J 9 63 72 63 72 0