1 Dismentalling of stores adjascent to Cat IPD 1-Jul-23 2 Dismentalling of Swimming pool 5-Jul-23 3 Dismentalling of Pavers 7-Jul-23 4 Excavation for walls & PCC 7-Jul-23 5 Brick work of Cat IPD and toilets 10-Jul-23 6 Excavation for column & PCC 16-Jul-23 7 PCC and steel work for Column 18-Jul-23 8 Casting 22-Jul-23 9 MEP works of toilet and shifting of existing lines 15-Jul-23 10 Gypsum Plaster works and tiling 22-Jul-23 11 Roofing 1-Aug-23 12 Pool structure and MEP works 15-Jul-23 13 False ceiling works 25-Aug-23 14 Pool Tiling works 1-Sep-23 15 Cat IPD flooring 11-Sep-23 16 Skylight work 1-Oct-23 17 Door and window work 1-Oct-23 18 Painting works 5-Oct-23 19 Wood works- Complete 10-Oct-23 20 Pathways development works 1-Oct-23 21 Final Handing over 1-Nov-23 Total days DATE OF COMPLETION No. of Days for Activity 7-Jul-23 7 15-Jul-23 11 10-Jul-23 4 15-Jul-23 9 20-Jul-23 11 20-Jul-23 5 25-Jul-23 8 28-Jul-23 7 22-Jul-23 8 10-Aug-23 20 31-Aug-23 31 25-Aug-23 42 10-Sep-23 17 20-Sep-23 20 30-Sep-23 20 10-Oct-23 10 10-Oct-23 10 25-Oct-23 21 20-Oct-23 11 30-Oct-23 30 10-Nov-23 10 133 days CGS- Execution Timelines
Start Date Duration
S.no. Activity Description Date of End Date (In Week-1 Week-2 Week-3 Week-4 Week-5 Week-6 Week-7 Week-8 Week-9 Week-10 Week-11 Week-12 Week-13 Week-14 Week-15 Week-16 Week-17 Week-18 Week-19 Week-20 Week-21 Week-22 Start- LOI+1 Weeks) Day Dismentalling of stores adjascent to 1 1-Jul-23 7-Jul-23 1 Cat IPD
2 Dismentalling of Swimming pool 5-Jul-23 15-Jul-23 1.6
3 Dismentalling of Pavers 7-Jul-23 10-Jul-23 0.6
4 Excavation for walls & PCC 7-Jul-23 15-Jul-23 1.3
5 Brick work of Cat IPD and toilets 10-Jul-23 20-Jul-23 1.6
6 Excavation for column & PCC 16-Jul-23 20-Jul-23 0.7
7 PCC and steel work for Column 18-Jul-23 25-Jul-23 1.1
8 Casting 22-Jul-23 28-Jul-23 1.0
MEP works of toilet and shifting of
9 15-Jul-23 22-Jul-23 1.1 existing lines
10 Gypsum Plaster works and tiling 22-Jul-23 10-Aug-23 2.9
11 Roofing 1-Aug-23 31-Aug-23 4.4
12 Pool structure and MEP works 15-Jul-23 25-Aug-23 6.0
13 False ceiling works 25-Aug-23 10-Sep-23 1.4
14 Pool Tiling works 1-Sep-23 20-Sep-23 2.9
15 Cat IPD flooring 11-Sep-23 30-Sep-23 2.9
16 Skylight work 1-Oct-23 10-Oct-23 1.4
17 Door and window work 1-Oct-23 10-Oct-23 1.4
18 Painting works 5-Oct-23 25-Oct-23 3.0
19 Wood works- Complete 10-Oct-23 20-Oct-23 1.6
20 Pathways development works 1-Oct-23 30-Oct-23 4.3