TIMELINES FOR CGS HOSPITAL WORKS

SL No. DESCRIPTION DATE OF START- LOI +1 DAY


1 Dismentalling of stores adjascent to Cat IPD 1-Jul-23
2 Dismentalling of Swimming pool 5-Jul-23
3 Dismentalling of Pavers 7-Jul-23
4 Excavation for walls & PCC 7-Jul-23
5 Brick work of Cat IPD and toilets 10-Jul-23
6 Excavation for column & PCC 16-Jul-23
7 PCC and steel work for Column 18-Jul-23
8 Casting 22-Jul-23
9 MEP works of toilet and shifting of existing lines 15-Jul-23
10 Gypsum Plaster works and tiling 22-Jul-23
11 Roofing 1-Aug-23
12 Pool structure and MEP works 15-Jul-23
13 False ceiling works 25-Aug-23
14 Pool Tiling works 1-Sep-23
15 Cat IPD flooring 11-Sep-23
16 Skylight work 1-Oct-23
17 Door and window work 1-Oct-23
18 Painting works 5-Oct-23
19 Wood works- Complete 10-Oct-23
20 Pathways development works 1-Oct-23
21 Final Handing over 1-Nov-23
Total days
DATE OF COMPLETION No. of Days for Activity
7-Jul-23 7
15-Jul-23 11
10-Jul-23 4
15-Jul-23 9
20-Jul-23 11
20-Jul-23 5
25-Jul-23 8
28-Jul-23 7
22-Jul-23 8
10-Aug-23 20
31-Aug-23 31
25-Aug-23 42
10-Sep-23 17
20-Sep-23 20
30-Sep-23 20
10-Oct-23 10
10-Oct-23 10
25-Oct-23 21
20-Oct-23 11
30-Oct-23 30
10-Nov-23 10
133 days
CGS- Execution Timelines

Start Date Duration


S.no. Activity Description Date of End Date (In Week-1 Week-2 Week-3 Week-4 Week-5 Week-6 Week-7 Week-8 Week-9 Week-10 Week-11 Week-12 Week-13 Week-14 Week-15 Week-16 Week-17 Week-18 Week-19 Week-20 Week-21 Week-22
Start- LOI+1 Weeks)
Day
Dismentalling of stores adjascent to
1 1-Jul-23 7-Jul-23 1
Cat IPD

2 Dismentalling of Swimming pool 5-Jul-23 15-Jul-23 1.6

3 Dismentalling of Pavers 7-Jul-23 10-Jul-23 0.6

4 Excavation for walls & PCC 7-Jul-23 15-Jul-23 1.3

5 Brick work of Cat IPD and toilets 10-Jul-23 20-Jul-23 1.6

6 Excavation for column & PCC 16-Jul-23 20-Jul-23 0.7

7 PCC and steel work for Column 18-Jul-23 25-Jul-23 1.1

8 Casting 22-Jul-23 28-Jul-23 1.0

MEP works of toilet and shifting of


9 15-Jul-23 22-Jul-23 1.1
existing lines

10 Gypsum Plaster works and tiling 22-Jul-23 10-Aug-23 2.9

11 Roofing 1-Aug-23 31-Aug-23 4.4

12 Pool structure and MEP works 15-Jul-23 25-Aug-23 6.0

13 False ceiling works 25-Aug-23 10-Sep-23 1.4

14 Pool Tiling works 1-Sep-23 20-Sep-23 2.9

15 Cat IPD flooring 11-Sep-23 30-Sep-23 2.9

16 Skylight work 1-Oct-23 10-Oct-23 1.4

17 Door and window work 1-Oct-23 10-Oct-23 1.4

18 Painting works 5-Oct-23 25-Oct-23 3.0

19 Wood works- Complete 10-Oct-23 20-Oct-23 1.6

20 Pathways development works 1-Oct-23 30-Oct-23 4.3

21 Final Handing over 1-Nov-23 10-Nov-23 1.4