You are on page 1of 6

Activity ID Activity Name Original Duration Start Finish Total Float Longest Path Qtr 3, 2023 Qtr 4, 2023

Original Duration Start Finish Total Float Longest Path Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul

ITEM VILLA OVERWATER - ABU DHABI ISLAND 322 20-Jun-23 20-Jun-24 0 20-Jun-24, ITEM

ITEM.1 MILESTONE 322 20-Jun-23 20-Jun-24 0 20-Jun-24, ITEM

A1680 Start Project 0 20-Jun-23 0 Start Project, 20-Jun-23


A1690 Finish Project 0 20-Jun-24 0 Finish Project,

ITEM.7 SITE WORK 16 20-Jun-23 13-Jul-23 0 13-Jul-23, ITEM.7 SITE WORK

ITEM.7.1 MOBILIZATION 16 20-Jun-23 13-Jul-23 0 13-Jul-23, ITEM.7.1 MOBILIZATION


A1700 Site Mobilization 16 20-Jun-23 13-Jul-23 0 Site Mobilization

ITEM.5 ENGINEERING WORKS 62 13-Jul-23 20-Sep-23 244 20-Sep-23, ITEM.5 ENGINEERING WORKS

ITEM.5.4 MATERIAL SUBMITTAL 62 13-Jul-23 20-Sep-23 244 20-Sep-23, ITEM.5.4 MATERIAL SUBMITTAL
ITEM.5.4.1 FLOORING 39 13-Jul-23 25-Aug-23 267 25-Aug-23, ITEM.5.4.1 FLOORING
A2920 Porcelain Tiles 1200mmx1200mm – Calacatta Gold CP02 3 13-Jul-23 17-Jul-23 198 Porcelain Tiles 1200mmx1200mm – Calacatta Gold CP02
A2930 Porcelain Tiles 1200mmx1200mm -Reve Noissette Glossy 3 13-Jul-23 17-Jul-23 198 Porcelain Tiles 1200mmx1200mm -Reve Noissette Glossy
A2940 Porcelain Tiles 1200mmx1200mm Reve perle matte finish 3 13-Jul-23 17-Jul-23 198 Porcelain Tiles 1200mmx1200mm Reve perle matte finish
A2950 Porcelain Tiles 1200mmx1200mm - Onyx White Glossy finish 3 13-Jul-23 17-Jul-23 267 Porcelain Tiles 1200mmx1200mm - Onyx White Glossy finish
A2960 Porcelain Tiles 1200mmx1200mm - Lincoln JL 04 LUC (glossy) 3 13-Jul-23 17-Jul-23 267 Porcelain Tiles 1200mmx1200mm - Lincoln JL 04 LUC (glossy)
A2970 Porcelain Tiles 1200mmx600mm - Stontech/4.0 Stone_01, Book Match) 3 17-Jul-23 20-Jul-23 267 Porcelain Tiles 1200mmx600mm - Stontech/4.0 Stone_01, Book Match)
A2980 Porcelain Tiles 1200mmx600mm - Rex Etoile Illusion 3 20-Jul-23 22-Jul-23 267 Porcelain Tiles 1200mmx600mm - Rex Etoile Illusion
A2990 Porcelain Tiles 600mmx600mm 3 24-Jul-23 26-Jul-23 267 Porcelain Tiles 600mmx600mm
A3000 Porcelain Tiles 600mmx600mm Antislip 3 27-Jul-23 29-Jul-23 267 Porcelain Tiles 600mmx600mm Antislip
A3010 Porcelain Tiles 300mmx600mm 3 29-Jul-23 02-Aug-23 267 Porcelain Tiles 300mmx600mm
A3020 Granite Absolute Black 3 02-Aug-23 05-Aug-23 267 Granite Absolute Black
A3030 LVT flooring Luxury Vinyl Tiles 3 05-Aug-23 09-Aug-23 267 LVT flooring Luxury Vinyl Tiles
A3040 GTI MAX- multi-layered interlocking loose lay vinyl tile 3 09-Aug-23 12-Aug-23 267 GTI MAX- multi-layered interlocking loose lay vinyl tile
A3050 Timber Flooring 3 12-Aug-23 16-Aug-23 267 Timber Flooring
A3060 Hand Tufted Carpet 3 16-Aug-23 19-Aug-23 267 Hand Tufted Carpet
A3070 Threshold -Granite (20mm thick) 3 19-Aug-23 22-Aug-23 267 Threshold -Granite (20mm thick)
A3080 S.S. Floor Transition Piece 3 23-Aug-23 25-Aug-23 267 S.S. Floor Transition Piece
ITEM.5.4.2 SKIRTING 16 17-Jul-23 03-Aug-23 287 03-Aug-23, ITEM.5.4.2 SKIRTING
A3090 Wooden Skirting 5 17-Jul-23 22-Jul-23 198 Wooden Skirting
A3110 Porcelain Skirting Through Body 4 22-Jul-23 26-Jul-23 287 Porcelain Skirting Through Body
A3120 Vinyl Skirting 3 27-Jul-23 29-Jul-23 287 Vinyl Skirting
A3130 PVC Skirting 4 29-Jul-23 03-Aug-23 287 PVC Skirting
ITEM.5.4.3 WALL 53 17-Jul-23 14-Sep-23 250 14-Sep-23, ITEM.5.4.3 WALL
A3100 Porcelain Tiles 2800mmx1200mm – Calacatta Gold CP02 3 17-Jul-23 20-Jul-23 198 Porcelain Tiles 2800mmx1200mm – Calacatta Gold CP02
A3140 Porcelain Tiles 2800mmx1200mm -Reve Noissette Glossy 3 20-Jul-23 22-Jul-23 198 Porcelain Tiles 2800mmx1200mm -Reve Noissette Glossy
A3150 Porcelain Tiles 2800mmx1200mm - Reve perle matte finish 3 24-Jul-23 26-Jul-23 198 Porcelain Tiles 2800mmx1200mm - Reve perle matte finish
A3160 Porcelain Tiles 2800mmx1200mm - Reve choco matte finish 3 27-Jul-23 29-Jul-23 198 Porcelain Tiles 2800mmx1200mm - Reve choco matte finish
A3170 Porcelain Tiles 2800mmx1200mm - Etoile tropical 3 29-Jul-23 02-Aug-23 198 Porcelain Tiles 2800mmx1200mm - Etoile tropical
A3180 Porcelain Tiles 2800mmx1200mm - Onyx White Glossy finish 3 02-Aug-23 05-Aug-23 198 Porcelain Tiles 2800mmx1200mm - Onyx White Glossy finish
A3190 Porcelain Tiles 2800mmx1200mm - Golden porphyry 3 05-Aug-23 09-Aug-23 198 Porcelain Tiles 2800mmx1200mm - Golden porphyry
A3200 Porcelain Tiles 2800mmx1200mm – Reve Bleu 3 09-Aug-23 12-Aug-23 198 Porcelain Tiles 2800mmx1200mm – Reve Bleu
A3210 Porcelain Tiles 2800mmx1200mm - Stontech/4.0 Stone_01 3 12-Aug-23 16-Aug-23 212 Porcelain Tiles 2800mmx1200mm - Stontech/4.0 Stone_01
A3300 Metal Cladding 3 12-Aug-23 16-Aug-23 198 Metal Cladding

Actual Level of Effort Remaining Work Milestone Page 1 of 6 Mouhajer Planning Engineer
Actual Work Critical Remaining Work summary © Oracle Corporation
Activity ID Activity Name Original Duration Start Finish Total Float Longest Path Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
A3220 Porcelain Tiles 1200mmx2400mm - Rex Etoile Illusion 3 16-Aug-23 19-Aug-23 252 Porcelain Tiles 1200mmx2400mm - Rex Etoile Illusion
A3310 Metal Mashrabiya 4 16-Aug-23 19-Aug-23 198 Metal Mashrabiya
A3230 Porcelain Tiles 2800mmx1200mm - Thunder night Glossy or matte finish 3 19-Aug-23 22-Aug-23 252 Porcelain Tiles 2800mmx1200mm - Thunder night Glossy or matte finish
A3320 Decorative paint 3 21-Aug-23 23-Aug-23 198 Decorative paint
A3240 Porcelain Tiles 300mmx600mm Antislip 3 23-Aug-23 25-Aug-23 252 Porcelain Tiles 300mmx600mm Antislip
A3330 Emulsion paint 4 24-Aug-23 28-Aug-23 198 Emulsion paint
A3250 Porcelain Tiles 300mmx600mm 3 26-Aug-23 29-Aug-23 252 Porcelain Tiles 300mmx600mm
A3340 Stainless steel sheet 3 28-Aug-23 31-Aug-23 198 Stainless steel sheet
A3260 Porcelain Tiles 2800mmx1200mm 3 29-Aug-23 01-Sep-23 252 Porcelain Tiles 2800mmx1200mm
A3350 Copper sheet 3 31-Aug-23 04-Sep-23 198 Copper sheet
A3270 Glass wall with fixtures 3 01-Sep-23 05-Sep-23 252 Glass wall with fixtures
A3360 Anti-Carbonation Paint 3 04-Sep-23 07-Sep-23 250 Anti-Carbonation Paint
A3280 Wooden panel 3 07-Sep-23 11-Sep-23 250 Wooden panel
A3290 Wooden Acoustic panel 3 11-Sep-23 14-Sep-23 250 Wooden Acoustic panel
ITEM.5.4.4 CEILING 29 12-Aug-23 14-Sep-23 198 14-Sep-23, ITEM.5.4.4 CEILING
A3370 Plain Gypsum Board Ceiling with Paint Finish 12.5mm thk 3 12-Aug-23 16-Aug-23 212 Plain Gypsum Board Ceiling with Paint Finish 12.5mm thk
A3380 Acoustic Gypsum Board 3 16-Aug-23 19-Aug-23 212 Acoustic Gypsum Board
A3400 Moisture Resistance Gypsum Board Ceiling with Paint Finish 12.5mm thk 3 04-Sep-23 07-Sep-23 198 Moisture Resistance Gypsum Board Ceiling with Paint Finish 12.5mm thk
A3410 Wooden ceiling 3 07-Sep-23 11-Sep-23 198 Wooden ceiling
A3420 Paint Emulsion 3 11-Sep-23 14-Sep-23 198 Paint Emulsion
ITEM.5.4.5 ROOF TILE 3 11-Sep-23 14-Sep-23 198 14-Sep-23, ITEM.5.4.5 ROOF TILE
A3390 Roof Tile 3 11-Sep-23 14-Sep-23 198 Roof Tile
ITEM.5.4.6 CURTIN 6 14-Sep-23 20-Sep-23 198 20-Sep-23, ITEM.5.4.6 CURTIN
A3430 Roller Blind 3 14-Sep-23 16-Sep-23 198 Roller Blind
A3440 Roller Blind (CONT’D) 3 18-Sep-23 20-Sep-23 198 Roller Blind (CONT’D)

ITEM.4 CONSTRUCTION WORKS 297 20-Jun-23 23-May-24 25 23-May-24, ITEM.4 CON

ITEM.4.3 MAIN BUILDING 297 20-Jun-23 23-May-24 25 23-May-24, ITEM.4.3 M


ITEM.4.3.2 DEMOLISHING WORKS 20 25-Jul-23 16-Aug-23 35 16-Aug-23, ITEM.4.3.2 DEMOLISHING WORKS
A3460 Demolishing of existing walls , pile , Rc coulmn , beam & slab 20 25-Jul-23 16-Aug-23 35 Demolishing of existing walls , pile , Rc coulmn , beam & slab
ITEM.4.3.8 CONCRETE WORKS 140 13-Jul-23 16-Dec-23 10 16-Dec-23, ITEM.4.3.8 CONCRETE WORKS
ITEM.4.3.8.4 GROUND FLOOR 88 13-Jul-23 19-Oct-23 0 19-Oct-23, ITEM.4.3.8.4 GROUND FLOOR
ITEM.4.3.8.4.1 FOUNDATION 60 13-Jul-23 18-Sep-23 0 18-Sep-23, ITEM.4.3.8.4.1 FOUNDATION
A1010 Piles Works 50 13-Jul-23 07-Sep-23 0 Piles Works
A1020 Pile Caps 10 07-Sep-23 18-Sep-23 0 Pile Caps
ITEM.4.3.8.4.2 WALLS 5 19-Sep-23 23-Sep-23 0 23-Sep-23, ITEM.4.3.8.4.2 WALLS
A1040 Plinth Walls 5 19-Sep-23 23-Sep-23 0 Plinth Walls
ITEM.4.3.8.4.3 SLAB & BEEM 17 23-Sep-23 13-Oct-23 0 13-Oct-23, ITEM.4.3.8.4.3 SLAB & BEEM
A1050 Erection of precast Beams for ground floor 10 23-Sep-23 05-Oct-23 0 Erection of precast Beams for ground floor
A1070 Placing of HCS Slab Panels for ground floor 7 05-Oct-23 13-Oct-23 0 Placing of HCS Slab Panels for ground floor
ITEM.4.3.8.4.5 COULMNS 6 13-Oct-23 19-Oct-23 0 19-Oct-23, ITEM.4.3.8.4.5 COULMNS
A1090 Steel reinforcement & Formwork for ground floor 5 13-Oct-23 18-Oct-23 0 Steel reinforcement & Formwork for ground floor
A1100 Coulmn Casting for ground floor 1 19-Oct-23 19-Oct-23 0 Coulmn Casting for ground floor
ITEM.4.3.8.6 FIRST FLOOR 22 20-Oct-23 13-Nov-23 0 13-Nov-23, ITEM.4.3.8.6 FIRST FLOOR
ITEM.4.3.8.6.3 SLAB & BEEM 17 20-Oct-23 08-Nov-23 0 08-Nov-23, ITEM.4.3.8.6.3 SLAB & BEEM

Actual Level of Effort Remaining Work Milestone Page 2 of 6 Mouhajer Planning Engineer
Actual Work Critical Remaining Work summary © Oracle Corporation
Activity ID Activity Name Original Duration Start Finish Total Float Longest Path Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
A1580 Erection of precast Beams for first floor 7 20-Oct-23 27-Oct-23 0 Erection of precast Beams for first floor
A1590 Placing of HCS Slab Panels for first floor 10 27-Oct-23 08-Nov-23 0 Placing of HCS Slab Panels for first floor
ITEM.4.3.8.6.5 COULMNS 5 08-Nov-23 13-Nov-23 0 13-Nov-23, ITEM.4.3.8.6.5 COULMNS
A1610 Steel reinforcement & Formwork for first floor 4 08-Nov-23 11-Nov-23 0 Steel reinforcement & Formwork for first floor
A1620 Coulmn Casting for first floor 1 13-Nov-23 13-Nov-23 0 Coulmn Casting for first floor
ITEM.4.3.8.2 ROOF FLOOR 23 14-Nov-23 09-Dec-23 10 09-Dec-23, ITEM.4.3.8.2 ROOF FLOOR
ITEM.4.3.8.2.3 SLAB & BEEM 17 14-Nov-23 02-Dec-23 0 02-Dec-23, ITEM.4.3.8.2.3 SLAB & BEEM
A1630 Erection of precast Beams for roof floor 7 14-Nov-23 21-Nov-23 0 Erection of precast Beams for roof floor
A1640 Placing of HCS Slab Panels for roof floor 10 21-Nov-23 02-Dec-23 0 Placing of HCS Slab Panels for roof floor
ITEM.4.3.8.2.5 COULMNS 6 02-Dec-23 09-Dec-23 10 09-Dec-23, ITEM.4.3.8.2.5 COULMNS
A1660 Steel reinforcement & Formwork for roof floor 5 02-Dec-23 08-Dec-23 10 Steel reinforcement & Formwork for roof floor
A1670 Coulmn Casting for roof floor 1 08-Dec-23 09-Dec-23 10 Coulmn Casting for roof floor
ITEM.4.3.8.3 TOP ROOF FLOOR 7 09-Dec-23 16-Dec-23 10 16-Dec-23, ITEM.4.3.8.3 TOP ROOF FLOOR
ITEM.4.3.8.3.3 SLAB & BEEM 7 09-Dec-23 16-Dec-23 10 16-Dec-23, ITEM.4.3.8.3.3 SLAB & BEEM
A1220 Erection of precast Beams 3 09-Dec-23 12-Dec-23 10 Erection of precast Beams
A1230 Placing of HCS Slab Panels 4 13-Dec-23 16-Dec-23 10 Placing of HCS Slab Panels
ITEM.4.3.3 WALL & PARTITIONS 74 08-Nov-23 30-Jan-24 5 30-Jan-24, ITEM.4.3.3 WALL & PARTITIONS
ITEM.4.3.3.1 GROUND FLOOR 60 08-Nov-23 13-Jan-24 0 13-Jan-24, ITEM.4.3.3.1 GROUND FLOOR
A1710 Masonry and Lintels for ground floor 14 08-Nov-23 23-Nov-23 24 Masonry and Lintels for ground floor
A1720 Plaster for ground floor 15 28-Dec-23 13-Jan-24 0 Plaster for ground floor
ITEM.4.3.3.2 FIRST FLOOR 52 02-Dec-23 30-Jan-24 0 30-Jan-24, ITEM.4.3.3.2 FIRST FLOOR
A1730 Masonry and Lintels for first floor 16 02-Dec-23 20-Dec-23 0 Masonry and Lintels for first floor
A1740 Plaster for first floor 14 13-Jan-24 30-Jan-24 0 Plaster for first floor
ITEM.4.3.3.3 ROOF FLOOR 34 16-Dec-23 24-Jan-24 10 24-Jan-24, ITEM.4.3.3.3 ROOF FLOOR
A1750 Masonry and Lintels for roof floor 16 16-Dec-23 04-Jan-24 10 Masonry and Lintels for roof floor
A1760 Plaster for roof floor 14 09-Jan-24 24-Jan-24 10 Plaster for roof floor
ITEM.4.3.1 METAL WORKS 185 05-Oct-23 29-Apr-24 3 29-Apr-24, ITEM.4.3.1 METAL
ITEM.4.3.1.1 STEEL STRUCTURES 16 05-Oct-23 23-Oct-23 59 23-Oct-23, ITEM.4.3.1.1 STEEL STRUCTURES
A2590 Steel Column 7 05-Oct-23 13-Oct-23 59 Steel Column
A2600 Steel Beam 5 13-Oct-23 18-Oct-23 59 Steel Beam
A2610 Decking Slab 4 19-Oct-23 23-Oct-23 59 Decking Slab
ITEM.4.3.1.2 METAL CANOPY 7 22-Apr-24 29-Apr-24 3 29-Apr-24, ITEM.4.3.1.2 META
A2620 Metal Canopy 7 22-Apr-24 29-Apr-24 3 Metal Canopy
ITEM.4.3.5 MEP WORKS 199 13-Oct-23 23-May-24 25 23-May-24, ITEM.4.3.5
ITEM.4.3.5.1 ELECTRICAL & ETISALATE WORKS 199 13-Oct-23 23-May-24 25 23-May-24, ITEM.4.3.5.1
ITEM.4.3.5.1.2 LOW CURRENT WORK 80 13-Oct-23 10-Jan-24 113 10-Jan-24, ITEM.4.3.5.1.2 LOW CURRENT WORK
ITEM.4.3.5.1.2.1 GROUND FLOOR 68 13-Oct-23 28-Dec-23 49 28-Dec-23, ITEM.4.3.5.1.2.1 GROUND FLOOR
A1880slab pipe conduit in ground floor 2 13-Oct-23 14-Oct-23 23 slab pipe conduit in ground floor
A1890Wall pip e conduit in ground floor 4 20-Dec-23 25-Dec-23 0 Wall pip e conduit in ground floor
A1900under tiles conduit in ground floor 3 25-Dec-23 28-Dec-23 49 under tiles conduit in ground floor
ITEM.4.3.5.1.2.3 FIRST FLOOR 45 08-Nov-23 28-Dec-23 107 28-Dec-23, ITEM.4.3.5.1.2.3 FIRST FLOOR
A1830Slab pipe conduit in first floor 2 08-Nov-23 10-Nov-23 2 Slab pipe conduit in first floor
A1840Wall pip e conduit in first floor 4 20-Dec-23 25-Dec-23 106 Wall pip e conduit in first floor
A1850under tiles conduit in first floor 3 25-Dec-23 28-Dec-23 107 under tiles conduit in first floor
ITEM.4.3.5.1.2.2 ROOF FLOOR 35 02-Dec-23 10-Jan-24 113 10-Jan-24, ITEM.4.3.5.1.2.2 ROOF FLOOR

Actual Level of Effort Remaining Work Milestone Page 3 of 6 Mouhajer Planning Engineer
Actual Work Critical Remaining Work summary © Oracle Corporation
Activity ID Activity Name Original Duration Start Finish Total Float Longest Path Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
A1910Slab pipe conduit in roof floor 2 02-Dec-23 05-Dec-23 37 Slab pipe conduit in roof floor
A1920Wall pip e conduit in roof floor 4 04-Jan-24 08-Jan-24 10 Wall pip e conduit in roof floor
A1930under tiles conduit in roof floor 2 09-Jan-24 10-Jan-24 113 under tiles conduit in roof floor
ITEM.4.3.5.1.1 POWER & LIGHTING WORK 115 13-Jan-24 22-May-24 26 22-May-24, ITEM.4.3.5.1
ITEM.4.3.5.1.1.1 GROUND FLOOR 76 13-Jan-24 08-Apr-24 45 08-Apr-24, ITEM.4.3.5.1.1.1 GROU
A1970wiring in ground floor 4 13-Jan-24 18-Jan-24 17 wiring in ground floor
A1980install Distrbution bords in ground floor 3 24-Jan-24 27-Jan-24 109 install Distrbution bords in ground floor
A1990wall and ceiling fixtures in ground floor 7 01-Apr-24 08-Apr-24 44 wall and ceiling fixtures in ground flo
ITEM.4.3.5.1.1.3 FIRST FLOOR 69 30-Jan-24 16-Apr-24 44 16-Apr-24, ITEM.4.3.5.1.1.3 FIRS
A2030wiring in first floor 4 30-Jan-24 03-Feb-24 1 wiring in first floor
A2040install Distrbution bords in first floor 3 03-Feb-24 06-Feb-24 100 install Distrbution bords in first floor
A2050wall and ceiling fixtures in first floor 7 08-Apr-24 16-Apr-24 44 wall and ceiling fixtures in first floo
ITEM.4.3.5.1.1.2 ROOF FLOOR 97 03-Feb-24 22-May-24 26 22-May-24, ITEM.4.3.5.1
A2740wiring in roof floor 4 03-Feb-24 07-Feb-24 99 wiring in roof floor
A2750install Distrbution bords in roof floor 3 08-Feb-24 10-Feb-24 99 install Distrbution bords in roof floor
A2760wall and ceiling fixtures in roof floor 7 14-May-24 22-May-24 26 wall and ceiling fixtures in
ITEM.4.3.5.1.3 EXTERIOR ELECTRICAL WORK 91 10-Feb-24 23-May-24 25 23-May-24, ITEM.4.3.5.1
A2060 Preparing Electrical Manhole 5 10-Feb-24 16-Feb-24 99 Preparing Electrical Manhole
A2070 Cable works 4 16-Feb-24 21-Feb-24 99 Cable works
A2090 exterior wairing 4 09-May-24 14-May-24 25 exterior wairing
A2080 install external fixtures 8 14-May-24 23-May-24 25 install external fixtures
ITEM.4.3.5.2 PLUMPING 50 25-Jan-24 21-Mar-24 37 21-Mar-24, ITEM.4.3.5.2 PLUMPING
ITEM.4.3.5.2.2 WATER DRANIGE & SUPPLY 50 25-Jan-24 21-Mar-24 37 21-Mar-24, ITEM.4.3.5.2.2 WATER DRA
ITEM.4.3.5.2.2.1 GROUND FLOOR 43 25-Jan-24 13-Mar-24 39 13-Mar-24, ITEM.4.3.5.2.2.1 GROUND FLO
A2110 water dranige & Supply in ground floor 8 25-Jan-24 03-Feb-24 74 water dranige & Supply in ground floor
A2120Install toilate accessoreies in ground floor 4 09-Mar-24 13-Mar-24 0 Install toilate accessoreies in ground floor
ITEM.4.3.5.2.2.3 FIRST FLOOR 41 31-Jan-24 16-Mar-24 36 16-Mar-24, ITEM.4.3.5.2.2.3 FIRST FLOO
A2160water dranige & Supply in first floor 8 31-Jan-24 08-Feb-24 69 water dranige & Supply in first floor
A2170Install toilate accessoreies in first floor 5 11-Mar-24 16-Mar-24 0 Install toilate accessoreies in first floor
ITEM.4.3.5.2.2.2 ROOF FLOOR 40 06-Feb-24 21-Mar-24 37 21-Mar-24, ITEM.4.3.5.2.2.2 ROOF FLO
A2180water dranige & Supply in roof floor 8 06-Feb-24 14-Feb-24 69 water dranige & Supply in roof floor
A2190Install toilate and poll accessories in roof floor 4 16-Mar-24 21-Mar-24 0 Install toilate and poll accessories in roof
ITEM.4.3.5.2.2.4 TOP ROOF FLOOR 3 06-Feb-24 08-Feb-24 69 08-Feb-24, ITEM.4.3.5.2.2.4 TOP ROOF FLOOR
A2200water dranige in top roof floor 3 06-Feb-24 08-Feb-24 69 water dranige in top roof floor
ITEM.4.3.5.3 HVAC 62 27-Jan-24 05-Apr-24 50 05-Apr-24, ITEM.4.3.5.3 HVAC
ITEM.4.3.5.3.1 AC WORKS 62 27-Jan-24 05-Apr-24 50 05-Apr-24, ITEM.4.3.5.3.1 AC WORK
A2210 AC pipe & Ac drainge 3 27-Jan-24 31-Jan-24 2 AC pipe & Ac drainge
A2220 Install AC unites 2 04-Apr-24 05-Apr-24 50 Install AC unites
ITEM.4.3.5.3.5 VENTELATION WORKS 62 27-Jan-24 05-Apr-24 50 05-Apr-24, ITEM.4.3.5.3.5 VENTELA
A2230 Install Ducting 5 27-Jan-24 02-Feb-24 2 Install Ducting
A2240 Install ventelation 2 04-Apr-24 05-Apr-24 50 Install ventelation
ITEM.4.3.5.4 FIRE SUPPRESSION 3 06-Apr-24 09-Apr-24 50 09-Apr-24, ITEM.4.3.5.4 FIRE SUP
A2250 Fire alarm system in all building 3 06-Apr-24 09-Apr-24 50 Fire alarm system in all building
ITEM.4.3.7 THERMAL AND MOISTURE PROTECTION 13 18-Jan-24 02-Feb-24 17 02-Feb-24, ITEM.4.3.7 THERMAL AND MOISTURE P
ITEM.4.3.7.1 WET AREA & WASHROOM 11 18-Jan-24 31-Jan-24 17 31-Jan-24, ITEM.4.3.7.1 WET AREA & WASHROOM

Actual Level of Effort Remaining Work Milestone Page 4 of 6 Mouhajer Planning Engineer
Actual Work Critical Remaining Work summary © Oracle Corporation
Activity ID Activity Name Original Duration Start Finish Total Float Longest Path Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
A1300 Waterproofing & testing for washroom and wet area in ground floor 6 18-Jan-24 25-Jan-24 17 Waterproofing & testing for washroom and wet area in g
A2270 Waterproofing & testing for washroom and wet area in first floor 5 25-Jan-24 31-Jan-24 17 Waterproofing & testing for washroom and wet area in
A2280 Waterproofing & testing for washroom and wet area in roof floor 5 25-Jan-24 31-Jan-24 17 Waterproofing & testing for washroom and wet area in
ITEM.4.3.7.2 ROOF AND BALACONY 3 25-Jan-24 29-Jan-24 17 29-Jan-24, ITEM.4.3.7.2 ROOF AND BALACONY
A2330 Waterproofing for Plu nge pool 3 25-Jan-24 29-Jan-24 17 Waterproofing for Plu nge pool
ITEM.4.3.7.3 TOP ROOF 4 29-Jan-24 02-Feb-24 17 02-Feb-24, ITEM.4.3.7.3 TOP ROOF
A2340 Top roof Waterproofing 4 29-Jan-24 02-Feb-24 17 Top roof Waterproofing
ITEM.4.3.4 FINISHES WORKS 292 20-Jun-23 17-May-24 30 17-May-24, ITEM.4.3.4 F
ITEM.4.3.4.1 FLOOR FINISHES 38 21-Feb-24 03-Apr-24 54 03-Apr-24, ITEM.4.3.4.1 FLOOR FIN
A2350 Floor Tiles & tufted carpet finishing for ground floor 12 21-Feb-24 05-Mar-24 0 Floor Tiles & tufted carpet finishing for ground
A2360 Floor Tiles & luxury vinly finishing for first floor 14 06-Mar-24 21-Mar-24 46 Floor Tiles & luxury vinly finishing for first f
A2430 Skirting Finishes 20 12-Mar-24 03-Apr-24 54 Skirting Finishes
A2370 Floor Tiles & luxury vinly finishing for roof floor 12 21-Mar-24 03-Apr-24 50 Floor Tiles & luxury vinly finishing for ro
ITEM.4.3.4.6 DOORS AND WINDOWS & GLASS SYSTEM 50 21-Feb-24 17-Apr-24 57 17-Apr-24, ITEM.4.3.4.6 DOORS
A1410 Install Frame Door 4 21-Feb-24 26-Feb-24 90 Install Frame Door
A1420 Install Frame windows & glass system 7 21-Feb-24 29-Feb-24 90 Install Frame windows & glass system
A1430 Install and finishing Door 5 06-Apr-24 11-Apr-24 57 Install and finishing Door
A1440 Install and finishing windows & glass system 10 06-Apr-24 17-Apr-24 57 Install and finishing windows & gla
ITEM.4.3.4.2 CEILING FINISHES 70 02-Feb-24 20-Apr-24 54 20-Apr-24, ITEM.4.3.4.2 CEILIN
A2380 Gypsum Board Ceiling for ground floor 15 02-Feb-24 19-Feb-24 78 Gypsum Board Ceiling for ground floor
A2390 Gypsum Board Ceiling for first floor 16 19-Feb-24 07-Mar-24 78 Gypsum Board Ceiling for first floor
A2400 Gypsum Board Ceiling for roof floor 15 04-Apr-24 20-Apr-24 54 Gypsum Board Ceiling for roof flo
ITEM.4.3.4.4 WALL FINISHES 56 05-Feb-24 06-Apr-24 3 06-Apr-24, ITEM.4.3.4.4 WALL FINI
A2420 Prime & first coat painting 15 05-Feb-24 21-Feb-24 0 Prime & first coat painting
A2410 Porcelain Tiles 15 21-Feb-24 08-Mar-24 0 Porcelain Tiles
A2440 Wooden Pane 14 09-Mar-24 25-Mar-24 3 Wooden Pane
A2570 Fininshing coat painting 9 21-Mar-24 30-Mar-24 0 Fininshing coat painting
A2450 Wallpaper 12 25-Mar-24 06-Apr-24 3 Wallpaper
A2460 Metal Finishing 5 25-Mar-24 30-Mar-24 3 Metal Finishing
ITEM.4.3.4.8 PANTRY - CABINET 12 20-Jun-23 08-Jul-23 310 08-Jul-23, ITEM.4.3.4.8 PANTRY - CABINET
A2560 Install and placing Pantry 12 20-Jun-23 08-Jul-23 310 Install and placing Pantry
ITEM.4.3.4.10 BUILDING SYSTEM 260 20-Jun-23 11-Apr-24 62 11-Apr-24, ITEM.4.3.4.10 BUILDIN
A2650 CCTV 6 20-Jun-23 26-Jun-23 303 CCTV
A2660 SMATV 5 20-Jun-23 24-Jun-23 317 SMATV
A2670 Audio visual System 6 20-Jun-23 26-Jun-23 316 Audio visual System
A2680 Earthing and Bonding System 5 20-Jun-23 24-Jun-23 317 Earthing and Bonding System
A2690 Building Management System 7 20-Jun-23 03-Jul-23 315 Building Management System
A2770 Telephone system accessories 5 06-Apr-24 11-Apr-24 62 Telephone system accessories
ITEM.4.3.4.7 LIFT 51 21-Mar-24 17-May-24 16 17-May-24, ITEM.4.3.4.7
A2700 Prepretion work for left 13 21-Mar-24 04-Apr-24 46 Prepretion work for left
A2710 Install left with all accesories 8 08-May-24 17-May-24 16 Install left with all accesori
ITEM.4.9 EXTERNAL WORKS 195 13-Oct-23 18-May-24 15 18-May-24, ITEM.4.9 EX
ITEM.4.9.1 MAIN ENTRANCE 174 13-Oct-23 25-Apr-24 36 25-Apr-24, ITEM.4.9.1 MAIN EN
A2630 Guard room concret 10 13-Oct-23 24-Oct-23 3 Guard room concret
A2640 Main Entrance 8 16-Apr-24 25-Apr-24 36 Main Entrance
Actual Level of Effort Remaining Work Milestone Page 5 of 6 Mouhajer Planning Engineer
Actual Work Critical Remaining Work summary © Oracle Corporation
Activity ID Activity Name Original Duration Start Finish Total Float Longest Path Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
ITEM.4.9.2 EXTERNAL DEVELOPMENT 85 13-Feb-24 18-May-24 15 18-May-24, ITEM.4.9.2 E
A2480 Repair the crack and edges with plaster 12 13-Feb-24 27-Feb-24 30 Repair the crack and edges with plaster
A2520 Matching with existing roof tile 6 09-Mar-24 15-Mar-24 43 Matching with existing roof tile
A2490 External paint for villa service area and boundary wall 15 01-Apr-24 17-Apr-24 0 External paint for villa service area
A2510 External facade wall with metal cladding 14 17-Apr-24 02-May-24 0 External facade wall with meta
A2500 External façade wall with porcelain tiles 14 03-May-24 18-May-24 0 External façade wall with
A2530 Granite Absolute BlackParking area, Water fountain area 14 03-May-24 18-May-24 15 Granite Absolute BlackPa

ITEM.2 CLOSING PROJECT 29 18-May-24 20-Jun-24 0 20-Jun-24, ITEM

ITEM.2.2 HANDOVER 29 18-May-24 20-Jun-24 0 20-Jun-24, ITEM


A2720 Test & commition 15 18-May-24 04-Jun-24 0 Test & commition
A2730 Closing Project 14 04-Jun-24 20-Jun-24 0 Closing Project

Actual Level of Effort Remaining Work Milestone Page 6 of 6 Mouhajer Planning Engineer
Actual Work Critical Remaining Work summary © Oracle Corporation