4 STOREY BUNGALOW Classic Schedule Layout 28-Dec-22 00:13

Activity ID Activity Name Original Start Finish Resources Budgeted Tota l Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
Duration Cost
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

NEWPROJ-2 4 STOREY BUNGALOW 262 03-Jan-23 20-Nov-23 $10,800.00 20-Nov-23, NEWPROJ-2 4 STOREY BUNGALOW

NEWPROJ-2.7 Preliminaries 261 03-Jan-23 18-Nov-23 $0.00 18-Nov-23, NEWPROJ-2.7 Preliminaries

NEWPROJ-2.7.1 Site Investigation 14 03-Jan-23 18-Jan-23 $0.00 18-Jan-23, NEWPROJ-2.7.1 Site Investigation
A2540 Site Investigation and Setting out 14 03-Jan-23 18-Jan-23 $0.00 Site Investigation and Setting out
NEWPROJ-2.7.3 Site Clearance 5 19-Jan-23 25-Jan-23 $0.00 25-Jan-23, NEWPROJ-2.7.3 Site Clearance
A1010 Site Clearance 5 19-Jan-23 25-Jan-23 $0.00 Site Clearance
NEWPROJ-2.7.4 Hoarding 247 19-Jan-23 18-Nov-23 $0.00 18-Nov-23, NEWPROJ-2.7.4 Hoarding
A1020 Install Hoarding 4 19-Jan-23 24-Jan-23 $0.00 Install Hoarding
A2560 Dismantle Hoarding 4 14-Nov-23 18-Nov-23 $0.00 Dismantle Hoarding

NEWPROJ-2.6 Substructure 31 26-Jan-23 03-Mar-23 $0.00 03-Mar-23, NEWPROJ-2.6 Substructure

NEWPROJ-2.6.1 Foundation 31 26-Jan-23 03-Mar-23 $0.00 03-Mar-23, NEWPROJ-2.6.1 Foundation


NEWPROJ-2.6.1.1 Pad Footing 17 26-Jan-23 15-Feb-23 $0.00 15-Feb-23, NEWPROJ-2.6.1.1 Pad Footing
A1040 Excavation 5 26-Jan-23 31-Jan-23 $0.00 Excavation
A1050 Formwork 4 01-Feb-23 04-Feb-23 $0.00 Formwork
A1060 Rebar 4 07-Feb-23 10-Feb-23 $0.00 Rebar
A1070 Concrete 4 11-Feb-23 15-Feb-23 $0.00 Concrete
NEWPROJ-2.6.1.2 Concrete Stump 14 16-Feb-23 03-Mar-23 $0.00 03-Mar-23, NEWPROJ-2.6.1.2 Concrete Stump
A1080 Formwork 4 16-Feb-23 20-Feb-23 $0.00 Formwork
A1090 Rebar 4 21-Feb-23 24-Feb-23 $0.00 Rebar
A1100 Concrete 4 25-Feb-23 01-Mar-23 $0.00 Concrete
A1110 Filling 2 01-Mar-23 03-Mar-23 $0.00 Filling

NEWPROJ-2.5 Superstructure 144 03-Mar-23 28-Aug-23 $0.00 28-Aug-23, NEWPROJ-2.5 Superstructure

NEWPROJ-2.5.1 Ground Floor 36 03-Mar-23 15-Apr-23 $0.00 15-Apr-23, NEWPROJ-2.5.1 Ground Floor
NEWPROJ-2.5.1.3 Ground Column 12 03-Mar-23 17-Mar-23 $0.00 17-Mar-23, NEWPROJ-2.5.1.3 Ground Column
A1180 Formwork 4 03-Mar-23 08-Mar-23 $0.00 Formwork
A1190 Rebar 4 08-Mar-23 13-Mar-23 $0.00 Rebar
A1200 Concrete 4 13-Mar-23 17-Mar-23 $0.00 Concrete
NEWPROJ-2.5.1.1 Ground Beam & Slab 12 17-Mar-23 31-Mar-23 $0.00 31-Mar-23, NEWPROJ-2.5.1.1 Ground Beam & Slab
A1120 Formwork 4 17-Mar-23 22-Mar-23 $0.00 Formwork
A1130 Rebar 4 22-Mar-23 27-Mar-23 $0.00 Rebar
A1140 Concrete 4 27-Mar-23 31-Mar-23 $0.00 Concrete
NEWPROJ-2.5.1.4 Staircase 12 31-Mar-23 15-Apr-23 $0.00 15-Apr-23, NEWPROJ-2.5.1.4 Staircase
A1210 Formwork 4 31-Mar-23 05-Apr-23 $0.00 Formwork
A1220 Rebar 4 05-Apr-23 11-Apr-23 $0.00 Rebar
A1230 Concrete 4 11-Apr-23 15-Apr-23 $0.00 Concrete
NEWPROJ-2.5.2 First Floor 36 15-Apr-23 02-Jun-23 $0.00 02-Jun-23, NEWPROJ-2.5.2 First Floor
NEWPROJ-2.5.2.3 First Floor Column 12 15-Apr-23 03-May-23 $0.00 03-May-23, NEWPROJ-2.5.2.3 First Floor Column
A1700 Formwork 4 15-Apr-23 20-Apr-23 $0.00 Formwork
A1710 Rebar 4 20-Apr-23 27-Apr-23 $0.00 Rebar
A1720 Concrete 4 27-Apr-23 03-May-23 $0.00 Concrete
NEWPROJ-2.5.2.1 First Floor Beam & Slab 12 03-May-23 19-May-23 $0.00 19-May-23, NEWPROJ-2.5.2.1 First Floor Beam & Slab
A1640 Formwork 4 03-May-23 10-May-23 $0.00 Formwork
A1650 Rebar 4 10-May-23 15-May-23 $0.00 Rebar
A1660 Concrete 4 15-May-23 19-May-23 $0.00 Concrete
NEWPROJ-2.5.2.4 Staircase 12 19-May-23 02-Jun-23 $0.00 02-Jun-23, NEWPROJ-2.5.2.4 Staircase
A1730 Formwork 4 19-May-23 24-May-23 $0.00 Formwork
A1740 Rebar 4 24-May-23 29-May-23 $0.00 Rebar
A1750 Concrete 4 29-May-23 02-Jun-23 $0.00 Concrete
NEWPROJ-2.5.3 Second Floor 36 02-Jun-23 15-Jul-23 $0.00 15-Jul-23, NEWPROJ-2.5.3 Second Floor
NEWPROJ-2.5.3.3 Second Floor Column 12 02-Jun-23 16-Jun-23 $0.00 16-Jun-23, NEWPROJ-2.5.3.3 Second Floor Column
A1820 Formwork 4 02-Jun-23 07-Jun-23 $0.00 Formwork
A1830 Rebar 4 07-Jun-23 12-Jun-23 $0.00 Rebar
A1840 Concrete 4 12-Jun-23 16-Jun-23 $0.00 Concrete
NEWPROJ-2.5.3.1 Second Floor Beam & Slab 12 16-Jun-23 01-Jul-23 $0.00 01-Jul-23, NEWPROJ-2.5.3.1 Second Floor Beam & Slab
A1760 Formwork 4 16-Jun-23 21-Jun-23 $0.00 Formwork
A1770 Rebar 4 21-Jun-23 26-Jun-23 $0.00 Rebar
A1780 Concrete 4 26-Jun-23 01-Jul-23 $0.00 Concrete

Actual Level of Effort Remaining Work Milestone Page 1 of 4 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
4 STOREY BUNGALOW Classic Schedule Layout 28-Dec-22 00:13
Activity ID Activity Name Original Start Finish Resources Budgeted Tota l Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
Duration Cost
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
NEWPROJ-2.5.3.4 Staircase 12 01-Jul-23 15-Jul-23 $0.00 15-Jul-23, NEWPROJ-2.5.3.4 Staircase
A1850 Formwork 4 01-Jul-23 06-Jul-23 $0.00 Formwork
A1860 Rebar 4 06-Jul-23 11-Jul-23 $0.00 Rebar
A1870 Concrete 4 11-Jul-23 15-Jul-23 $0.00 Concrete
NEWPROJ-2.5.8 Third Floor 25 15-Jul-23 15-Aug-23 $0.00 15-Aug-23, NEWPROJ-2.5.8 Third Floor
NEWPROJ-2.5.8.3 Third Floor Column 13 15-Jul-23 01-Aug-23 $0.00 01-Aug-23, NEWPROJ-2.5.8.3 Third Floor Column
A1940 Formwork 4 15-Jul-23 21-Jul-23 $0.00 Formwork
A1950 Rebar 4 21-Jul-23 26-Jul-23 $0.00 Rebar
A1960 Concrete 4 26-Jul-23 01-Aug-23 $0.00 Concrete
NEWPROJ-2.5.8.1 Third Floor Beam & Slab 12 01-Aug-23 15-Aug-23 $0.00 15-Aug-23, NEWPROJ-2.5.8.1 Third Floor Beam & Slab
A1880 Formwork 4 01-Aug-23 05-Aug-23 $0.00 Formwork
A1890 Rebar 4 05-Aug-23 10-Aug-23 $0.00 Rebar
A1900 Concrete 4 10-Aug-23 15-Aug-23 $0.00 Concrete
NEWPROJ-2.5.4 Roof Level 11 15-Aug-23 28-Aug-23 $0.00 28-Aug-23, NEWPROJ-2.5.4 Roof Level
NEWPROJ-2.5.4.1 Roof Beam 4 15-Aug-23 19-Aug-23 $0.00 19-Aug-23, NEWPROJ-2.5.4.1 Roof Beam
A1240 Roof Beam 4 15-Aug-23 19-Aug-23 $0.00 Roof Beam
NEWPROJ-2.5.4.2 Roof Trusses 4 19-Aug-23 24-Aug-23 $0.00 24-Aug-23, NEWPROJ-2.5.4.2 Roof Trusses
A1250 Roof Truss 4 19-Aug-23 24-Aug-23 $0.00 Roof Truss
NEWPROJ-2.5.4.3 Roof Tiles 4 24-Aug-23 28-Aug-23 $0.00 28-Aug-23, NEWPROJ-2.5.4.3 Roof Tiles
A1260 Roof Tiling 4 24-Aug-23 28-Aug-23 $0.00 Roof Tiling

NEWPROJ-2.4 Architectural Works 54 29-Aug-23 02-Nov-23 $10,800.00 02-Nov-23, NEWPROJ-2.4 Architectural Works

NEWPROJ-2.4.1 Brickwork 38 29-Aug-23 14-Oct-23 $0.00 14-Oct-23, NEWPROJ-2.4.1 Brickwork


NEWPROJ-2.4.1.1 Ground Floor 8 29-Aug-23 07-Sep-23 $0.00 07-Sep-23, NEWPROJ-2.4.1.1 Ground Floor
A1270 Setting Out 3 29-Aug-23 01-Sep-23 $0.00 Setting Out
A1280 Lay Bricks 5 01-Sep-23 07-Sep-23 $0.00 Lay Bricks
NEWPROJ-2.4.1.2 First Floor 8 07-Sep-23 15-Sep-23 $0.00 15-Sep-23, NEWPROJ-2.4.1.2 First Floor
A1970 Setting Out 3 07-Sep-23 09-Sep-23 $0.00 Setting Out
A1980 Lay Bricks 5 11-Sep-23 15-Sep-23 $0.00 Lay Bricks
NEWPROJ-2.4.1.3 Second Floor 8 18-Sep-23 26-Sep-23 $0.00 26-Sep-23, NEWPROJ-2.4.1.3 Second Floor
A1990 Setting Out 3 18-Sep-23 20-Sep-23 $0.00 Setting Out
A2000 Lay Bricks 5 20-Sep-23 26-Sep-23 $0.00 Lay Bricks
NEWPROJ-2.4.1.4 Third Floor 8 26-Sep-23 05-Oct-23 $0.00 05-Oct-23, NEWPROJ-2.4.1.4 Third Floor
A2010 Setting Out 3 26-Sep-23 29-Sep-23 $0.00 Setting Out
A2020 Lay Bricks 5 30-Sep-23 05-Oct-23 $0.00 Lay Bricks
NEWPROJ-2.4.1.5 Roof Level 8 06-Oct-23 14-Oct-23 $0.00 14-Oct-23, NEWPROJ-2.4.1.5 Roof Level
A2030 Setting Out 3 06-Oct-23 09-Oct-23 $0.00 Setting Out
A2040 Lay Bricks 5 09-Oct-23 14-Oct-23 $0.00 Lay Bricks
NEWPROJ-2.4.8 Plastering 33 07-Sep-23 18-Oct-23 $0.00 18-Oct-23, NEWPROJ-2.4.8 Plastering
NEWPROJ-2.4.8.1 Ground Floor 3 07-Sep-23 11-Sep-23 $0.00 11-Sep-23, NEWPROJ-2.4.8.1 Ground Floor
A1290 Internal Plastering 3 07-Sep-23 11-Sep-23 $0.00 Internal Plastering
A1300 External Plastering 3 07-Sep-23 11-Sep-23 $0.00 External Plastering
NEWPROJ-2.4.8.2 First Floor 3 18-Sep-23 20-Sep-23 $0.00 20-Sep-23, NEWPROJ-2.4.8.2 First Floor
A2390 Internal Plastering 3 18-Sep-23 20-Sep-23 $0.00 Internal Plastering
A2410 External Plastering 3 18-Sep-23 20-Sep-23 $0.00 External Plastering
NEWPROJ-2.4.8.3 Second Floor 3 26-Sep-23 30-Sep-23 $0.00 30-Sep-23, NEWPROJ-2.4.8.3 Second Floor
A2420 Internal Plastering 3 26-Sep-23 30-Sep-23 $0.00 Internal Plastering
A2430 External Plastering 3 26-Sep-23 30-Sep-23 $0.00 External Plastering
NEWPROJ-2.4.8.4 Third Floor 3 06-Oct-23 09-Oct-23 $0.00 09-Oct-23, NEWPROJ-2.4.8.4 Third Floor
A2440 Internal Plastering 3 06-Oct-23 09-Oct-23 $0.00 Internal Plastering
A2450 External Plastering 3 06-Oct-23 09-Oct-23 $0.00 External Plastering
NEWPROJ-2.4.8.5 Roof Level 3 14-Oct-23 18-Oct-23 $0.00 18-Oct-23, NEWPROJ-2.4.8.5 Roof Level
A2460 External Plastering 3 14-Oct-23 18-Oct-23 $0.00 External Plastering
NEWPROJ-2.4.9 Painting Works 26 21-Sep-23 21-Oct-23 $10,800.00 21-Oct-23, NEWPROJ-2.4.9 Painting Works
NEWPROJ-2.4.9.1 Ground Floor 3 21-Sep-23 23-Sep-23 $2,400.00 23-Sep-23, NEWPROJ-2.4.9.1 Ground Floor
A1310 Internal Painting 3 21-Sep-23 23-Sep-23 Painter 1 $1,200.00 Internal Painting
A1320 External Painting 3 21-Sep-23 23-Sep-23 Painter 1 $1,200.00 External Painting
NEWPROJ-2.4.9.2 First Floor 3 30-Sep-23 04-Oct-23 $2,400.00 04-Oct-23, NEWPROJ-2.4.9.2 First Floor
A2470 Internal Painting 3 30-Sep-23 04-Oct-23 Painter 1 $1,200.00 Internal Painting

Actual Level of Effort Remaining Work Milestone Page 2 of 4 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
4 STOREY BUNGALOW Classic Schedule Layout 28-Dec-22 00:13
Activity ID Activity Name Original Start Finish Resources Budgeted Tota l Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
Duration Cost
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
A2480 External Painting 3 30-Sep-23 04-Oct-23 Painter 1 $1,200.00 External Painting
NEWPROJ-2.4.9.3 Second Floor 3 10-Oct-23 12-Oct-23 $2,400.00 12-Oct-23, NEWPROJ-2.4.9.3 Second Floor
A2490 Internal Painting 3 10-Oct-23 12-Oct-23 Painter 1 $1,200.00 Internal Painting
A2500 External Painting 3 10-Oct-23 12-Oct-23 Painter 1 $1,200.00 External Painting
NEWPROJ-2.4.9.4 Third Floor 3 18-Oct-23 21-Oct-23 $2,400.00 21-Oct-23, NEWPROJ-2.4.9.4 Third Floor
A2510 Internal Painting 3 18-Oct-23 21-Oct-23 Painter 1 $1,200.00 Internal Painting
A2520 External Painting 3 18-Oct-23 21-Oct-23 Painter 1 $1,200.00 External Painting
NEWPROJ-2.4.9.5 Roof Level 3 18-Oct-23 21-Oct-23 $1,200.00 21-Oct-23, NEWPROJ-2.4.9.5 Roof Level
A2530 External Painting 3 18-Oct-23 21-Oct-23 Painter 1 $1,200.00 External Painting
NEWPROJ-2.4.10 Tiling Works 21 04-Oct-23 27-Oct-23 $0.00 27-Oct-23, NEWPROJ-2.4.10 Tiling Works
NEWPROJ-2.4.10.1 Ground Floor 6 04-Oct-23 10-Oct-23 $0.00 10-Oct-23, NEWPROJ-2.4.10.1 Ground Floor
A1330 Floor Tiles 3 04-Oct-23 07-Oct-23 $0.00 Floor Tiles
A1340 Wall Tiles 3 07-Oct-23 10-Oct-23 $0.00 Wall Tiles
NEWPROJ-2.4.10.2 First Floor 6 13-Oct-23 19-Oct-23 $0.00 19-Oct-23, NEWPROJ-2.4.10.2 First Floor
A2050 Floor Tiles 3 13-Oct-23 16-Oct-23 $0.00 Floor Tiles
A2060 Wall Tiles 3 17-Oct-23 19-Oct-23 $0.00 Wall Tiles
NEWPROJ-2.4.10.3 Second Floor 6 21-Oct-23 27-Oct-23 $0.00 27-Oct-23, NEWPROJ-2.4.10.3 Second Floor
A2070 Floor Tiles 3 21-Oct-23 25-Oct-23 $0.00 Floor Tiles
A2080 Wall Tiles 3 25-Oct-23 27-Oct-23 $0.00 Wall Tiles
NEWPROJ-2.4.10.4 Third Floor 6 21-Oct-23 27-Oct-23 $0.00 27-Oct-23, NEWPROJ-2.4.10.4 Third Floor
A2090 Floor Tiles 3 21-Oct-23 25-Oct-23 $0.00 Floor Tiles
A2100 Wall Tiles 3 25-Oct-23 27-Oct-23 $0.00 Wall Tiles
NEWPROJ-2.4.2 Doors and Windows 25 25-Sep-23 24-Oct-23 $0.00 24-Oct-23, NEWPROJ-2.4.2 Doors and Windows
NEWPROJ-2.4.2.1 Ground Floor 3 25-Sep-23 27-Sep-23 $0.00 27-Sep-23, NEWPROJ-2.4.2.1 Ground Floor
A1350 Install external frame 1 25-Sep-23 26-Sep-23 $0.00 Install external frame
A1360 Install internal frame 1 26-Sep-23 27-Sep-23 $0.00 Install internal frame
NEWPROJ-2.4.2.2 First Floor 3 04-Oct-23 06-Oct-23 $0.00 06-Oct-23, NEWPROJ-2.4.2.2 First Floor
A2110 Install external frame 1 04-Oct-23 05-Oct-23 $0.00 Install external frame
A2120 Install internal frame 1 05-Oct-23 06-Oct-23 $0.00 Install internal frame
NEWPROJ-2.4.2.3 Second Floor 3 13-Oct-23 16-Oct-23 $0.00 16-Oct-23, NEWPROJ-2.4.2.3 Second Floor
A2130 Install external frame 1 13-Oct-23 14-Oct-23 $0.00 Install external frame
A2140 Install internal frame 1 14-Oct-23 16-Oct-23 $0.00 Install internal frame
NEWPROJ-2.4.2.4 Third Floor 3 21-Oct-23 24-Oct-23 $0.00 24-Oct-23, NEWPROJ-2.4.2.4 Third Floor
A2150 Install external frame 1 21-Oct-23 23-Oct-23 $0.00 Install external frame
A2160 Install internal frame 1 23-Oct-23 24-Oct-23 $0.00 Install internal frame
NEWPROJ-2.4.3 Ceiling 8 25-Oct-23 02-Nov-23 $0.00 02-Nov-23, NEWPROJ-2.4.3 Ceiling
NEWPROJ-2.4.3.1 Ground Floor 2 25-Oct-23 26-Oct-23 $0.00 26-Oct-23, NEWPROJ-2.4.3.1 Ground Floor
A1370 Install ceiling section 2 25-Oct-23 26-Oct-23 $0.00 Install ceiling section
NEWPROJ-2.4.3.2 First Floor 2 27-Oct-23 28-Oct-23 $0.00 28-Oct-23, NEWPROJ-2.4.3.2 First Floor
A1380 Install ceiling section 2 27-Oct-23 28-Oct-23 $0.00 Install ceiling section
NEWPROJ-2.4.3.3 Second Floor 2 30-Oct-23 31-Oct-23 $0.00 31-Oct-23, NEWPROJ-2.4.3.3 Second Floor
A1390 Install ceiling section 2 30-Oct-23 31-Oct-23 $0.00 Install ceiling section
NEWPROJ-2.4.3.4 Third Floor 2 01-Nov-23 02-Nov-23 $0.00 02-Nov-23, NEWPROJ-2.4.3.4 Third Floor
A2170 Install ceiling section 2 01-Nov-23 02-Nov-23 $0.00 Install ceiling section

NEWPROJ-2.3 Mechanical & Electrical Works 182 27-Mar-23 07-Nov-23 $0.00 07-Nov-23, NEWPROJ-2.3 Mechanical & Electrical Works

NEWPROJ-2.3.1 Electrical Works 180 27-Mar-23 04-Nov-23 $0.00 04-Nov-23, NEWPROJ-2.3.1 Electrical Works
NEWPROJ-2.3.1.1 Ground Floor 174 27-Mar-23 28-Oct-23 $0.00 28-Oct-23, NEWPROJ-2.3.1.1 Ground Floor
A1570 1st Fix 2 27-Mar-23 29-Mar-23 $0.00 1st Fix
A1580 2nd Fix 2 07-Sep-23 09-Sep-23 $0.00 2nd Fix
A1590 3rd Fix 1 27-Oct-23 28-Oct-23 $0.00 3rd Fix
NEWPROJ-2.3.1.2 First Floor 140 15-May-23 31-Oct-23 $0.00 31-Oct-23, NEWPROJ-2.3.1.2 First Floor
A2180 1st Fix 2 15-May-23 17-May-23 $0.00 1st Fix
A2190 2nd Fix 2 18-Sep-23 19-Sep-23 $0.00 2nd Fix
A2200 3rd Fix 1 30-Oct-23 31-Oct-23 $0.00 3rd Fix
NEWPROJ-2.3.1.3 Second Floor 106 26-Jun-23 02-Nov-23 $0.00 02-Nov-23, NEWPROJ-2.3.1.3 Second Floor
A2210 1st Fix 2 26-Jun-23 28-Jun-23 $0.00 1st Fix
A2220 2nd Fix 2 26-Sep-23 29-Sep-23 $0.00 2nd Fix
A2230 3rd Fix 1 01-Nov-23 02-Nov-23 $0.00 3rd Fix

Actual Level of Effort Remaining Work Milestone Page 3 of 4 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
4 STOREY BUNGALOW Classic Schedule Layout 28-Dec-22 00:13
Activity ID Activity Name Original Start Finish Resources Budgeted Tota l Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
Duration Cost
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
NEWPROJ-2.3.1.4 Third Floor 71 10-Aug-23 04-Nov-23 $0.00 04-Nov-23, NEWPROJ-2.3.1.4 Third Floor
A2240 1st Fix 2 10-Aug-23 12-Aug-23 $0.00 1st Fix
A2250 2nd Fix 2 06-Oct-23 07-Oct-23 $0.00 2nd Fix
A2260 3rd Fix 1 03-Nov-23 04-Nov-23 $0.00 3rd Fix
NEWPROJ-2.3.2 Plumbing Works 176 27-Mar-23 31-Oct-23 $0.00 31-Oct-23, NEWPROJ-2.3.2 Plumbing Works
NEWPROJ-2.3.2.1 Ground Floor 161 27-Mar-23 13-Oct-23 $0.00 13-Oct-23, NEWPROJ-2.3.2.1 Ground Floor
A1610 1st Fix 5 27-Mar-23 01-Apr-23 $0.00 1st Fix
A1620 2nd Fix 3 11-Oct-23 13-Oct-23 $0.00 2nd Fix
NEWPROJ-2.3.2.2 First Floor 132 15-May-23 21-Oct-23 $0.00 21-Oct-23, NEWPROJ-2.3.2.2 First Floor
A2270 1st Fix 5 15-May-23 20-May-23 $0.00 1st Fix
A2280 2nd Fix 3 19-Oct-23 21-Oct-23 $0.00 2nd Fix
NEWPROJ-2.3.2.3 Seond Floor 104 26-Jun-23 31-Oct-23 $0.00 31-Oct-23, NEWPROJ-2.3.2.3 Seond Floor
A2300 1st Fix 5 26-Jun-23 03-Jul-23 $0.00 1st Fix
A2310 2nd Fix 3 28-Oct-23 31-Oct-23 $0.00 2nd Fix
NEWPROJ-2.3.2.4 Third Floor 67 10-Aug-23 31-Oct-23 $0.00 31-Oct-23, NEWPROJ-2.3.2.4 Third Floor
A2330 1st Fix 5 10-Aug-23 16-Aug-23 $0.00 1st Fix
A2340 2nd Fix 3 28-Oct-23 31-Oct-23 $0.00 2nd Fix
NEWPROJ-2.3.3 Air-Conditioning Works 7 28-Oct-23 06-Nov-23 $0.00 06-Nov-23, NEWPROJ-2.3.3 Air -Conditioning Works
NEWPROJ-2.3.3.1 Ground Floor 1 28-Oct-23 30-Oct-23 $0.00 30-Oct-23, NEWPROJ-2.3.3.1 Ground Floor
A1600 Install Air -Conditioning system 1 28-Oct-23 30-Oct-23 $0.00 Install Air -Conditioning system
NEWPROJ-2.3.3.2 First Floor 1 31-Oct-23 01-Nov-23 $0.00 01-Nov-23, NEWPROJ-2.3.3.2 First Floor
A2360 Install Air -Conditioning system 1 31-Oct-23 01-Nov-23 $0.00 Install Air-Conditioning system
NEWPROJ-2.3.3.3 Second Floor 1 02-Nov-23 03-Nov-23 $0.00 03-Nov-23, NEWPROJ-2.3.3.3 Second Floor
A2370 Install Air -Conditioning system 1 02-Nov-23 03-Nov-23 $0.00 Install Air -Conditioning system
NEWPROJ-2.3.3.4 Third Floor 1 04-Nov-23 06-Nov-23 $0.00 06-Nov-23, NEWPROJ-2.3.3.4 Third Floor
A2380 Install Air -Conditioning system 1 04-Nov-23 06-Nov-23 $0.00 Install Air -Conditioning system
NEWPROJ-2.3.4 Elevator 69 15-Aug-23 07-Nov-23 $0.00 07-Nov-23, NEWPROJ-2.3.4 Elevator
A1430 Install Elevator system 5 15-Aug-23 21-Aug-23 $0.00 Install Elevator system
A1480 Test run 3 04-Nov-23 07-Nov-23 $0.00 Test run
NEWPROJ-2.2 External Works 21 21-Oct-23 15-Nov-23 $0.00 15-Nov-23, NEWPROJ-2.2 External Works

NEWPROJ-2.2.1 Road Works 5 21-Oct-23 27-Oct-23 $0.00 27-Oct-23, NEWPROJ-2.2.1 Road Works
A1490 Road work 5 21-Oct-23 27-Oct-23 $0.00 Road work
NEWPROJ-2.2.2 Drainage Works 7 21-Oct-23 30-Oct-23 $0.00 30-Oct-23, NEWPROJ-2.2.2 Drainage Works
A1500 Drainage work 7 21-Oct-23 30-Oct-23 $0.00 Drainage work
NEWPROJ-2.2.3 Sewerage Works 7 21-Oct-23 30-Oct-23 $0.00 30-Oct-23, NEWPROJ-2.2.3 Sewerage Works
A1510 Sewerage work 7 21-Oct-23 30-Oct-23 $0.00 Sewerage work
NEWPROJ-2.2.5 Landscaping Works 7 03-Nov-23 10-Nov-23 $0.00 10-Nov-23, NEWPROJ-2.2.5 Landscaping Works
A1520 Landscaping work 7 03-Nov-23 10-Nov-23 $0.00 Landscaping work
NEWPROJ-2.2.6 Fencing and Gate Works 3 11-Nov-23 15-Nov-23 $0.00 15-Nov-23, NEWPROJ-2.2.6 Fencing and Gate Works
A1530 Fencing and Gate work 3 11-Nov-23 15-Nov-23 $0.00 Fencing and Gate work
NEWPROJ-2.2.8 Water Reticulation 5 30-Oct-23 04-Nov-23 $0.00 04-Nov-23, NEWPROJ-2.2.8 Water Reticulation
A1540 Water Reticulation 5 30-Oct-23 04-Nov-23 $0.00 Water Reticulation

NEWPROJ-2.1 Handover 12 04-Nov-23 20-Nov-23 $0.00 20-Nov-23, NEWPROJ-2.1 Handover

NEWPROJ-2.1.1 Cleaning and Checking 7 04-Nov-23 14-Nov-23 $0.00 14-Nov-23, NEWPROJ-2.1.1 Cleaning and Checking
A1550 Cleaning and Checking work 7 04-Nov-23 14-Nov-23 $0.00 Cleaning and Checking work
NEWPROJ-2.1.2 Handover 5 14-Nov-23 20-Nov-23 $0.00 20-Nov-23, NEWPROJ-2.1.2 Handover
A1560 Handover 5 14-Nov-23 20-Nov-23 $0.00 Handover