Dave Buster's-V5 Classic Schedule Layout 15-Apr-23 17:49

Activity ID Budgeted Total Activity Name Original Resources Start Finish Remaining Activity Leveling 2023 2024
Cost Duration Duration Priority
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
07-Aug-24, Capstone Dave & Bus
Capstone Dave & Buster's-V5
$4,961,275.71 369d 09-Mar-23 07-Aug-24 369d
06-Aug-24, Capstone.0 General R
Capstone.0 General Requirements
$1,258,831.89 369d 09-Mar-23 06-Aug-24 369d
28-May-24, Capstone.1 Site Work
Capstone.1 Site Work $183,000.60 229d 13-Jul-23 28-May-24 229d
19-Jan-24, Capstone.2 Concrete
Capstone.2 Concrete $442,521.34 126d 28-Jul-23 19-Jan-24 126d
04-Jan-24, Capstone.3 Masonry
Capstone.3 Masonry $245,567.85 85d 08-Sep-23 04-Jan-24 85d
03-May-24, Capstone.4 Metals
Capstone.4 Metals $361,949.41 171d 08-Sep-23 03-May-24 171d
28-May-24, Capstone.5 Wood & Plastic
Capstone.5 Wood & Plastic
$642,761.80 162d 16-Oct-23 28-May-24 162d
13-May-24, Capstone.6 Thermal & Moisture
Capstone.6 Thermal & Moisture
$127,914.20 106d 18-Dec-23 13-May-24 106d
21-May-24, Capstone.7 Doors & Windows
Capstone.7 Doors & Windows
$397,189.36 32d 08-Apr-24 21-May-24 32d
12-Jul-24, Capstone.8 Finishes
Capstone.8 Finishes $288,803.14 155d 11-Dec-23 12-Jul-24 155d
26-Jul-24, Capstone.9 Specialities
Capstone.9 Specialities $47,454.58 20d 01-Jul-24 26-Jul-24 20d
12-Jul-24, Capstone.10 Equipment
Capstone.10 Equipment $463,661.97 10d 01-Jul-24 12-Jul-24 10d
12-Jul-24, Capstone.11 Mechanical & Plu
Capstone.11 Mechanical & Plumbing
$143,739.19 180d 06-Nov-23 12-Jul-24 180d
07-Aug-24, Capstone.12 Electrica
Capstone.12 Electrical $357,880.38 192d 13-Nov-23 07-Aug-24 192d

Actual Level of Effort Actual Work Critical Remaining Work Page 1 of 1 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation