‫مشروع الصرف الصحي لقرية العبد‬ Critical Path 06-Sep-23

Activity ID Activity Name Start Finish Budgeted Units 2024


Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
‫فرقة تمديد مواسير و انابيب‬ 20-Dec-23 17-Sep-24 16 54 50 52 68 78 78 39 26 15
WBS: D.EX.SN.A Zone A 25-Dec-23 17-Sep-24 6 27 24 26 42 52 52 31 26 15
SN10 Line 1 MN1 T MN2 25-Dec-23 04-Jan-24 6 4
SN15 Line 1 MN2 T MN4 04-Jan-24 04-Feb-24 23 3
SN20 Line 2-1 MN1 T MN2 25-Feb-24 28-Feb-24 3
SN25 line 1 from mh1 to mh7 04-Feb-24 25-Feb-24 17
SN35 line 4-1 from mh 4to mh 6 28-Feb-24 03-Mar-24 1 1
SN40 line 5-1 03-Mar-24 28-Mar-24 22
SN45 line 6-1 from mh 3 to mh 6 28-Mar-24 09-Apr-24 2 8
SN50 line 7-1 from mh 3 to mh 17 11-Apr-24 14-May-24 16 11
SN55 line 7-1 from mh 3 to mh 7 09-Apr-24 11-Apr-24 2
SN60 line 2-7-1 from mh 2 to mh 5 11-May-24 10-Jun-24 18 9
SN65 line 1-7-1 from mh1 to mh 1 11-Apr-24 11-May-24 16 8
SN70 line 3-7-1from mh 3 to mh 9 10-Jun-24 17-Jul-24 17 14
SN75 line 2-3-7-1 28-Jul-24 31-Jul-24 2
SN80 line 3/-3-7-1from mh 3 to mh 2 29-Aug-24 09-Sep-24 2 7
SN85 line 3-3-7-1 from mh3 to mh 4 31-Jul-24 29-Aug-24 1 24
SN90 line 2-3-3-7-1 from mh 2 to 1 09-Sep-24 09-Sep-24 0
SN95 line 4-3-7-1 from mh 4 to mh 1 09-Sep-24 17-Sep-24 7
SN100 line 5-7-1 from mh 5 to mh 3 14-May-24 10-Jun-24 15 8
SN110 line 8-7-1 from mh 8 to mh 4 10-Jun-24 12-Jun-24 3
SN115 line2-1 from mh 2 to 1 17-Jul-24 28-Jul-24 9
SN120 line 10-7-1 from mh 10 to ic 4 12-Jun-24 15-Jun-24 2
SN125 line 12-7-1 from mh 12to 4 15-Jun-24 26-Jun-24 10
SN130 line 15-7-1 from mh15 to mh 2 26-Jun-24 03-Jul-24 3 2
SN135 line 1-15-7-1 from mh1 to mh 1 03-Jul-24 04-Jul-24 2
WBS: D.EX.SN.B Zone B 25-Feb-24 10-Jul-24 5 26 26 26 26 8
SN140 line 1 from mh 7 to mh 11 25-Feb-24 27-Feb-24 2
SN145 line 1 from mh 11 to mh 12 27-Feb-24 02-Mar-24 2 0
SN150 line 1 from mh 12 to mh 26 02-Mar-24 05-Mar-24 3
SN155 line 8-1 from mh 8 to mh 4 05-Mar-24 18-Mar-24 11
SN160 line 8-1 from mh 8 to h.c.ic4 18-Mar-24 23-Mar-24 3
SN165 line 1-8-1 from mh 1 to ic-2 11-Jun-24 18-Jun-24 7
SN170 line 2-8-1from mh 2 to mh 2 18-Jun-24 23-Jun-24 3
SN175 line 11-1 from mh 11 to mh 8 23-Mar-24 25-Mar-24 2
SN180 line 1-11-1 from mh 1 to mh 5 23-Jun-24 26-Jun-24 3
SN185 line 1-1-11-1 from mh 1 to mh 1 26-Jun-24 01-Jul-24 4 0
SN190 line 3-1-11-1 from mh 3 to h.c. ic2 01-Jul-24 02-Jul-24 2
SN195 line 2-11-1 from mh2 to mh 5 02-Jul-24 06-Jul-24 3
SN200 line 4-11-1from mh 4 to mh 3 06-Jul-24 10-Jul-24 4
SN205 line 12-1 from mh 12 to mh 1 25-Mar-24 26-Mar-24 1
SN210 line 13-1 from mh 13 to mh 1 26-Mar-24 28-Apr-24 4 24
SN215 line 14-1 from mh 14 to mh 1 28-Apr-24 09-May-24 2 7
SN220 line 15-1 from mh 15 to mh 1 09-May-24 12-May-24 3
SN225 line 18-1 from mh 18 to mh 1 12-May-24 15-May-24 3
SN230 line 21-1 from mh 21 to mh 1 15-May-24 01-Jun-24 13 0
SN235 line 23-1 from mh 23 to mh 1 01-Jun-24 11-Jun-24 9
WBS: D.EX.FM.1 ‫خط الطرد‬ 20-Dec-23 26-Feb-24 10 27 21
A2970 ‫من محطة الرفع حتي غرفة الصمامات الرئيسية‬ 20-Dec-23 28-Dec-23 8
A2980 ٢ ‫من غرفة الصمامات أ حتي غرفة الغسيل‬ 30-Dec-23 04-Jan-24 2 4
A2990 ٣ ‫ حتي غرفة الغسيل‬٢ ‫من غرفة الغسيل‬ 06-Jan-24 20-Jan-24 13

Page 1 of 2 Planning Eng: Supevison Eng:


Ahmed Fahmy Mohamed Sadek
‫مشروع الصرف الصحي لقرية العبد‬ Critical Path 06-Sep-23
Activity ID Activity Name Start Finish Budgeted Units 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
A3000 ‫ حتي محطة المعالجة‬٣ ‫من غرفة الغسيل‬ 21-Jan-24 26-Feb-24 10 21

Page 2 of 2 Planning Eng: Supevison Eng:


Ahmed Fahmy Mohamed Sadek