BASELINE SCHEDULE CONTRACTOR SCHEDULE ACTUAL DATES

LVL 10 - 16/6/24 30-03-24

POUR 1 POUR 2
LVL 9 - 5/6/24 20-03-24
LVL 8 - 25/5/24 10-03-24
LVL 7 - 12/5/24 29-02-24
LVL 6 - 29/4/24 19-02-24
LVL 5- 18/4/24 09-02-24
LVL 4 - 5/4/24 30-01-24
LVL 3 - 24/3/23 20-01-24

LVL 2- 8/3/24 10-01-24


LVL 1- 7/2/24 25-12-23

P6 - 13-12-23 24-11-23
P5 -13-11-23 29-10-23 09-11-23 09-11-23
P4 - 13-10-23 08-10-23 13-10-23 13-10-23
P3 - 12-9-23 12-09-23 14-09-23 25-09-23

P2 - 11-8-23 17-08-23 18-08-23 29-08-23

P1- 12-7-23 25-06-23