You are on page 1of 6

G+P+6 residential and Retail building (Update in Progress) Classic Schedule Layout 22-Jan-24 15:03

Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float

(New EPS) 616 24-May-23 20-May-25 25-May-23 23-May-25 3

616 24-May-23
G+P+6 residential and Retail building (Update in Progress) 18012024 20-May-25 25-May-23 23-May-25 3

Project Engineering and Construction 616 24-May-23 20-May-25 25-May-23 23-May-25 3


A1000 Project Start Milestone 0 24-May-23 25-May-23 2
A2900 Project finish miestone 0 20-May-25 23-May-25 3
NOC/Permit 0 24-May-23 24-May-23 25-May-23 25-May-23 2
Major Milestone 533 24-May-23 12-Feb-25 07-Apr-25 07-Apr-25 46
Preliminaries 174 24-May-23 14-Dec-23 25-Nov-23 18-Jun-24 158
Engineering 348 24-May-23 06-Jul-24 26-May-23 15-May-25 264
MEP material submittal and approval-1 80 15-Dec-23 19-Mar-24 18-Jun-24 19-Sep-24 158
Prequalification Submission and approvals from DCD and SIRA 107 24-May-23 27-Sep-23 26-May-23 16-Aug-24 276
Material Submittal and Approval from DCD and SIRA 90 10-Jun-23 25-Sep-23 26-Jun-23 04-Jun-24 214
Shop Drawing Submission and Approval from DCD and SIRA 106 24-Jun-23 27-Oct-23 13-Jul-23 29-Oct-24 313
MEP shop drawing submission and approval 72 04-Jan-24 28-Mar-24 13-Aug-24 28-Sep-24 158
Procurement 116 14-Jul-23 26-Nov-23 24-Aug-23 03-Nov-24 292
Provisional Sums Item 348 24-May-23 06-Jul-24 23-Sep-23 15-May-25 264
Nomination 148 24-May-23 14-Nov-23 23-Sep-23 19-Nov-24 316
Quote & Vendor 108 24-May-23 28-Sep-23 23-Sep-23 15-Apr-24 169
PS-1000 Garbage Disposal 6 24-May-23 30-May-23 23-Sep-23 29-Sep-23 103
PS-1010 Light Fixture 6 31-May-23 06-Jun-23 30-Sep-23 06-Oct-23 103
PS-1020 Kitchen Cabinet 6 07-Jun-23 13-Jun-23 07-Oct-23 13-Oct-23 103
PS-1030 Wardrobes 6 14-Jun-23 20-Jun-23 14-Oct-23 20-Oct-23 103
PS-1040 Sanitarywares 6 21-Jun-23 27-Jun-23 21-Oct-23 27-Oct-23 103
PS-1050 Gym and Kid Area Equipment 6 30-Jun-23 06-Jul-23 28-Oct-23 03-Nov-23 103
PS-1060 Landscaping 6 07-Jul-23 13-Jul-23 04-Nov-23 10-Nov-23 103
PS-1070 Swimming Pool 6 14-Jul-23 20-Jul-23 11-Nov-23 17-Nov-23 103
PS-1080 Plunge Pool 6 21-Jul-23 27-Jul-23 18-Nov-23 24-Nov-23 103
PS-1090 Signage 6 28-Jul-23 03-Aug-23 30-Dec-23 06-Jan-24 133
PS-1100 Column Guards, Humps,Traffic Mirrors,Wheel Stopper 6 04-Aug-23 10-Aug-23 08-Jan-24 13-Jan-24 133
PS-1110 Lifts 6 11-Aug-23 17-Aug-23 15-Jan-24 20-Jan-24 133
PS-1120 Mirrors 6 18-Aug-23 24-Aug-23 22-Jan-24 27-Jan-24 133
PS-1130 Aluminum, Glazing and Metal Works 6 25-Aug-23 31-Aug-23 12-Mar-24 18-Mar-24 169
PS-1140 Sauna & Steam 6 01-Sep-23 07-Sep-23 19-Mar-24 25-Mar-24 169
PS-1150 Facade Lighting 6 08-Sep-23 14-Sep-23 26-Mar-24 01-Apr-24 169

Page 1 of 6 TASK filter: All Activities


© Oracle Corporation
G+P+6 residential and Retail building (Update in Progress) Classic Schedule Layout 22-Jan-24 15:03
Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float

PS-1160 Facade signage (Digital) 6 15-Sep-23 21-Sep-23 02-Apr-24 08-Apr-24 169


PS-1170 Screening of roof MEP Services as per authority requirement
6 22-Sep-23 28-Sep-23 09-Apr-24 15-Apr-24 169
Contract & Nomination 142 31-May-23 14-Nov-23 25-Nov-23 19-Nov-24 316
PS-1180 Garbage Disposal 40 31-May-23 18-Jul-23 09-Apr-24 24-May-24 265
PS-1190 Light Fixture 40 07-Jun-23 25-Jul-23 18-Apr-24 04-Jun-24 268
PS-1200 Kitchen Cabinet 40 14-Jun-23 01-Aug-23 04-Mar-24 19-Apr-24 223
PS-1210 Wardrobes 40 21-Jun-23 08-Aug-23 14-Feb-24 02-Apr-24 201
PS-1220 Sanitarywares 40 30-Jun-23 15-Aug-23 11-May-24 27-Jun-24 270
PS-1230 Gym and Kid Area Equipment 40 07-Jul-23 22-Aug-23 20-Aug-24 05-Oct-24 350
PS-1240 Landscaping 40 14-Jul-23 29-Aug-23 03-Oct-24 19-Nov-24 382
PS-1250 Swimming Pool 40 21-Jul-23 05-Sep-23 15-Jan-24 29-Feb-24 151
PS-1260 Plunge Pool 40 28-Jul-23 12-Sep-23 25-Nov-23 11-Jan-24 103
PS-1270 Signage 40 04-Aug-23 19-Sep-23 11-Jul-24 27-Aug-24 292
PS-1280 Column Guards, Humps,Traffic Mirrors,Wheel Stopper 40 11-Aug-23 26-Sep-23 22-Mar-24 08-May-24 190
PS-1290 Lifts 40 18-Aug-23 03-Oct-23 05-Feb-24 23-Mar-24 145
PS-1300 Mirrors 40 25-Aug-23 10-Oct-23 29-Jan-24 15-Mar-24 133
PS-1310 Aluminum, Glazing and Metal Works 40 01-Sep-23 17-Oct-23 15-May-24 01-Jul-24 219
PS-1320 Sauna & Steam 40 08-Sep-23 24-Oct-23 21-May-24 05-Jul-24 217
PS-1330 Facade Lighting 40 15-Sep-23 31-Oct-23 06-Apr-24 23-May-24 174
PS-1340 Facade signage (Digital) 40 22-Sep-23 07-Nov-23 20-Jul-24 05-Sep-24 258
PS-1350 Screening of roof MEP Services as per authority requirement
40 29-Sep-23 14-Nov-23 16-Apr-24 31-May-24 169
Material Approval 205 19-Jul-23 15-Mar-24 12-Jan-24 24-Mar-25 316
Submission 157 19-Jul-23 18-Jan-24 12-Jan-24 27-Jan-25 316
PS-1360 Garbage Disposal 55 19-Jul-23 20-Sep-23 25-May-24 27-Jul-24 265
PS-1370 Light Fixture 55 26-Jul-23 27-Sep-23 04-Jun-24 07-Aug-24 268
PS-1380 Kitchen Cabinet 55 02-Aug-23 04-Oct-23 20-Apr-24 22-Jun-24 223
PS-1390 Wardrobes 55 09-Aug-23 11-Oct-23 02-Apr-24 05-Jun-24 201
PS-1400 Sanitarywares 55 16-Aug-23 18-Oct-23 27-Jun-24 30-Aug-24 270
PS-1410 Gym and Kid Area Equipment 55 23-Aug-23 25-Oct-23 05-Oct-24 12-Dec-24 350
PS-1420 Landscaping 55 30-Aug-23 01-Nov-23 19-Nov-24 27-Jan-25 382
PS-1430 Swimming Pool 55 06-Sep-23 08-Nov-23 01-Mar-24 04-May-24 151
PS-1440 Plunge Pool 55 13-Sep-23 15-Nov-23 12-Jan-24 16-Mar-24 103
PS-1450 Signage 55 20-Sep-23 22-Nov-23 27-Aug-24 30-Oct-24 292
PS-1460 Column Guards 55 27-Sep-23 29-Nov-23 08-May-24 11-Jul-24 190

Page 2 of 6 TASK filter: All Activities


© Oracle Corporation
G+P+6 residential and Retail building (Update in Progress) Classic Schedule Layout 22-Jan-24 15:03
Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float

PS-1470 Lifts 55 04-Oct-23 06-Dec-23 23-Mar-24 27-May-24 145


PS-1480 Mirrors 55 11-Oct-23 13-Dec-23 16-Mar-24 18-May-24 133
PS-1490 Aluminum, Glazing and Metal Works 55 18-Oct-23 20-Dec-23 01-Jul-24 03-Sep-24 219
PS-1500 Sauna & Steam 55 25-Oct-23 27-Dec-23 06-Jul-24 07-Sep-24 217
PS-1510 Facade Lighting 55 01-Nov-23 04-Jan-24 23-May-24 26-Jul-24 174
PS-1520 Facade signage 55 08-Nov-23 11-Jan-24 05-Sep-24 08-Nov-24 258
PS-1530 Screening in Roof 55 15-Nov-23 18-Jan-24 01-Jun-24 03-Aug-24 169
Approval 126 21-Sep-23 15-Mar-24 18-Mar-24 24-Mar-25 263
PS-1540 Garbage Disposal 40 21-Sep-23 15-Nov-23 29-Jul-24 20-Sep-24 221
PS-1550 Light Fixture 40 28-Sep-23 22-Nov-23 07-Aug-24 02-Oct-24 224
PS-1560 Kitchen Cabinet 40 05-Oct-23 29-Nov-23 24-Jun-24 16-Aug-24 186
PS-1570 Wardrobes 40 12-Oct-23 06-Dec-23 05-Jun-24 31-Jul-24 168
PS-1580 Sanitarywares 40 19-Oct-23 13-Dec-23 30-Aug-24 25-Oct-24 226
PS-1590 Gym and Kid Area Equipment 40 26-Oct-23 20-Dec-23 12-Dec-24 07-Feb-25 293
PS-1600 Landscaping 40 02-Nov-23 27-Dec-23 27-Jan-25 24-Mar-25 319
PS-1610 Swimming Pool 40 09-Nov-23 03-Jan-24 06-May-24 28-Jun-24 126
PS-1620 Plunge Pool 40 16-Nov-23 10-Jan-24 18-Mar-24 10-May-24 86
PS-1630 Signage 40 23-Nov-23 17-Jan-24 30-Oct-24 27-Dec-24 244
PS-1640 Column Guards 40 30-Nov-23 24-Jan-24 11-Jul-24 05-Sep-24 159
PS-1650 Lifts 40 07-Dec-23 31-Jan-24 27-May-24 22-Jul-24 121
PS-1660 Mirrors 40 14-Dec-23 07-Feb-24 20-May-24 12-Jul-24 111
PS-1670 Aluminum, Glazing and Metal Works 40 21-Dec-23 14-Feb-24 03-Sep-24 29-Oct-24 183
PS-1680 Sauna & Steam 40 28-Dec-23 21-Feb-24 09-Sep-24 01-Nov-24 181
PS-1690 Facade Lighting 40 05-Jan-24 29-Feb-24 26-Jul-24 20-Sep-24 145
PS-1700 Facade signage 40 12-Jan-24 08-Mar-24 08-Nov-24 08-Jan-25 215
PS-1710 Screening in Roof 40 19-Jan-24 15-Mar-24 05-Aug-24 27-Sep-24 140
Shop Drawing 125 16-Nov-23 11-Apr-24 11-May-24 08-Apr-25 306
Submission 117 16-Nov-23 02-Apr-24 11-May-24 28-Mar-25 305
Garbage Disposal 4 16-Nov-23 20-Nov-23 21-Sep-24 25-Sep-24 264
PS-SD-1000 Submission - Garbage Disposal 4 16-Nov-23 20-Nov-23 21-Sep-24 25-Sep-24 264
Light fixture 4 23-Nov-23 27-Nov-23 02-Oct-24 07-Oct-24 268
PS-SD-1010 Submission - Light Fixture 4 23-Nov-23 27-Nov-23 02-Oct-24 07-Oct-24 268
Kitchen Cabinet 4 30-Nov-23 04-Dec-23 17-Aug-24 21-Aug-24 222
PS-SD-1020 Submission- All floors 4 30-Nov-23 04-Dec-23 17-Aug-24 21-Aug-24 222

Page 3 of 6 TASK filter: All Activities


© Oracle Corporation
G+P+6 residential and Retail building (Update in Progress) Classic Schedule Layout 22-Jan-24 15:03
Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float

Wardrobes 4 07-Dec-23 11-Dec-23 31-Jul-24 05-Aug-24 201


PS-SD-1460 Submission- All floors 4 07-Dec-23 11-Dec-23 31-Jul-24 05-Aug-24 201
Sanitarywares 4 14-Dec-23 18-Dec-23 25-Oct-24 30-Oct-24 270
PS-SD-1220 Submission- sanitarywares 4 14-Dec-23 18-Dec-23 25-Oct-24 30-Oct-24 270
Gym and Kid area Equipment 4 21-Dec-23 25-Dec-23 07-Feb-25 12-Feb-25 350
PS-SD-1250 Submission- Gymf and Kid area Equipment 4 21-Dec-23 25-Dec-23 07-Feb-25 12-Feb-25 350
Landscaping 4 28-Dec-23 02-Jan-24 24-Mar-25 28-Mar-25 382
PS-SD-1260 Submission - Landscaping 4 28-Dec-23 02-Jan-24 24-Mar-25 28-Mar-25 382
Swimming Pool 4 04-Jan-24 08-Jan-24 29-Jun-24 04-Jul-24 152
PS-SD-1270 Submission - Swimming Pool 4 04-Jan-24 08-Jan-24 29-Jun-24 04-Jul-24 152
Plunge pool 4 11-Jan-24 15-Jan-24 11-May-24 15-May-24 103
PS-SD-1280 Submission - Plunge Pool 4 11-Jan-24 15-Jan-24 11-May-24 15-May-24 103
Signages 4 18-Jan-24 22-Jan-24 27-Dec-24 02-Jan-25 292
PS-SD-1290 Submission - Signages 4 18-Jan-24 22-Jan-24 27-Dec-24 02-Jan-25 292
Column Guards 4 25-Jan-24 29-Jan-24 05-Sep-24 10-Sep-24 191
PS-SD-1300 Submission- Column Guards 4 25-Jan-24 29-Jan-24 05-Sep-24 10-Sep-24 191
Lifts 4 01-Feb-24 05-Feb-24 22-Jul-24 26-Jul-24 146
PS-SD-1310 Subnmission - Lifts 4 01-Feb-24 05-Feb-24 22-Jul-24 26-Jul-24 146
Mirrors 4 08-Feb-24 12-Feb-24 13-Jul-24 18-Jul-24 133
PS-SD-1320 Submission - Mirrors 4 08-Feb-24 12-Feb-24 13-Jul-24 18-Jul-24 133
Aluminum, Glazing and Metal Works 4 15-Feb-24 19-Feb-24 29-Oct-24 02-Nov-24 220
PS-SD-1330 Submission - All Floors 4 15-Feb-24 19-Feb-24 29-Oct-24 02-Nov-24 220
Sauna & Steam 4 22-Feb-24 26-Feb-24 02-Nov-24 07-Nov-24 218
PS-SD-1420 Submission - Sauna & Steam 4 22-Feb-24 26-Feb-24 02-Nov-24 07-Nov-24 218
Facade Lighting 4 01-Mar-24 05-Mar-24 20-Sep-24 25-Sep-24 174
PS-SD-1430 Submission Facade Lighting 4 01-Mar-24 05-Mar-24 20-Sep-24 25-Sep-24 174
Facede Signage 4 09-Mar-24 13-Mar-24 08-Jan-25 13-Jan-25 258
PS-SD-1440 Submission Facade Signage 4 09-Mar-24 13-Mar-24 08-Jan-25 13-Jan-25 258
Screening in roof 4 29-Mar-24 02-Apr-24 28-Sep-24 03-Oct-24 158
PS-SD-1450 Submission Screening in Roof 4 29-Mar-24 02-Apr-24 28-Sep-24 03-Oct-24 158
Approval 102 21-Nov-23 11-Apr-24 16-May-24 08-Apr-25 255
Garbage Disposal 7 21-Nov-23 29-Nov-23 26-Sep-24 04-Oct-24 221
PS-SD-1520 Approval - Garbage disposal 7 21-Nov-23 29-Nov-23 26-Sep-24 04-Oct-24 221
Light fixture 7 28-Nov-23 06-Dec-23 07-Oct-24 16-Oct-24 224
PS-SD-1530 Approval - Light Fixture 7 28-Nov-23 06-Dec-23 07-Oct-24 16-Oct-24 224

Page 4 of 6 TASK filter: All Activities


© Oracle Corporation
G+P+6 residential and Retail building (Update in Progress) Classic Schedule Layout 22-Jan-24 15:03
Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float

Kitchen Cabinet 7 05-Dec-23 13-Dec-23 22-Aug-24 30-Aug-24 186


PS-SD-1550 Approval- All Floors 7 05-Dec-23 13-Dec-23 22-Aug-24 30-Aug-24 186
Wardrobes 7 12-Dec-23 20-Dec-23 05-Aug-24 14-Aug-24 168
PS-SD-1610 Approval- All Floors 7 12-Dec-23 20-Dec-23 05-Aug-24 14-Aug-24 168
Sanitarywares 7 19-Dec-23 27-Dec-23 30-Oct-24 08-Nov-24 226
PS-SD-1670 Approval - Sanitarywares 7 19-Dec-23 27-Dec-23 30-Oct-24 08-Nov-24 226
Gym and Kid area Equipment 7 26-Dec-23 03-Jan-24 12-Feb-25 21-Feb-25 293
PS-SD-1680 Approval - Gym and Kid area equipment 7 26-Dec-23 03-Jan-24 12-Feb-25 21-Feb-25 293
Landscaping 7 03-Jan-24 11-Jan-24 28-Mar-25 08-Apr-25 319
PS-SD-1690 Approval - Landscaping 7 03-Jan-24 11-Jan-24 28-Mar-25 08-Apr-25 319
Swimming Pool 7 09-Jan-24 17-Jan-24 04-Jul-24 15-Jul-24 127
PS-SD-1700 Approval - Swimming Pool 7 09-Jan-24 17-Jan-24 04-Jul-24 15-Jul-24 127
Plunge pool 7 16-Jan-24 24-Jan-24 16-May-24 24-May-24 86
PS-SD-1710 Approval - Plunge pool 7 16-Jan-24 24-Jan-24 16-May-24 24-May-24 86
Signages 7 23-Jan-24 31-Jan-24 02-Jan-25 13-Jan-25 244
PS-SD-1720 Approval - Signages 7 23-Jan-24 31-Jan-24 02-Jan-25 13-Jan-25 244
Column Guards 7 30-Jan-24 07-Feb-24 10-Sep-24 19-Sep-24 159
PS-SD-1730 Approval - Column Guards 7 30-Jan-24 07-Feb-24 10-Sep-24 19-Sep-24 159
Lifts 7 06-Feb-24 14-Feb-24 26-Jul-24 06-Aug-24 122
PS-SD-1740 Approval - Lift 7 06-Feb-24 14-Feb-24 26-Jul-24 06-Aug-24 122
Mirrors 7 13-Feb-24 21-Feb-24 18-Jul-24 29-Jul-24 111
PS-SD-1750 Approval - Mirroe 7 13-Feb-24 21-Feb-24 18-Jul-24 29-Jul-24 111
Aluminum, Glazing and Metal Works 7 22-Feb-24 01-Mar-24 29-Jul-24 07-Aug-24 111
PS-SD-1760 Approval - All floors 7 22-Feb-24 01-Mar-24 29-Jul-24 07-Aug-24 111
Sauna & Steam 7 27-Feb-24 06-Mar-24 07-Nov-24 18-Nov-24 182
PS-SD-1820 Approval - Sauna & Steam 7 27-Feb-24 06-Mar-24 07-Nov-24 18-Nov-24 182
Facade Lighting 7 06-Mar-24 15-Mar-24 25-Sep-24 04-Oct-24 145
PS-SD-1830 Approval - Facade Lighting 7 06-Mar-24 15-Mar-24 25-Sep-24 04-Oct-24 145
Facede Signage 7 14-Mar-24 22-Mar-24 13-Jan-25 22-Jan-25 215
PS-SD-1840 Approval - Facade Signage 7 14-Mar-24 22-Mar-24 13-Jan-25 22-Jan-25 215
Screening in roof 7 03-Apr-24 11-Apr-24 03-Oct-24 14-Oct-24 132
PS-SD-1850 Approval - Screening in Roof 7 03-Apr-24 11-Apr-24 03-Oct-24 14-Oct-24 132
Procurement 220 30-Nov-23 06-Jul-24 26-May-24 15-May-25 314
PS-1720 Garbage Disposal 38 30-Nov-23 06-Jan-24 05-Oct-24 11-Nov-24 311
PS-1730 Light Fixture 113 07-Dec-23 28-Mar-24 16-Oct-24 05-Feb-25 315

Page 5 of 6 TASK filter: All Activities


© Oracle Corporation
G+P+6 residential and Retail building (Update in Progress) Classic Schedule Layout 22-Jan-24 15:03
Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float

PS-1740 Kitchen Cabinet 75 14-Dec-23 26-Feb-24 01-Sep-24 14-Nov-24 262


PS-1750 Wardrobes 75 21-Dec-23 04-Mar-24 14-Aug-24 27-Oct-24 237
PS-1760 Sanitarywares 113 28-Dec-23 18-Apr-24 08-Nov-24 28-Feb-25 317
PS-1770 Gym and Kid Area Equipment 38 04-Jan-24 10-Feb-24 21-Feb-25 30-Mar-25 415
PS-1780 Landscaping 38 12-Jan-24 18-Feb-24 08-Apr-25 15-May-25 453
PS-1790 Swimming Pool 56 18-Jan-24 14-Mar-24 15-Jul-24 09-Sep-24 180
PS-1800 Plunge Pool 56 25-Jan-24 21-Mar-24 26-May-24 21-Jul-24 123
PS-1810 Signage 38 01-Feb-24 09-Mar-24 13-Jan-25 19-Feb-25 348
PS-1820 Column Guards 19 08-Feb-24 26-Feb-24 19-Sep-24 07-Oct-24 224
PS-1830 Lifts 125 15-Feb-24 18-Jun-24 06-Aug-24 08-Dec-24 173
PS-1840 Mirrors 38 22-Feb-24 30-Mar-24 16-Mar-25 22-Apr-25 389
PS-1850 Aluminum, Glazing and Metal Works 75 02-Mar-24 15-May-24 07-Aug-24 20-Oct-24 158
PS-1860 Sauna & Steam 56 07-Mar-24 02-May-24 18-Nov-24 13-Jan-25 257
PS-1870 Facade Lighting 113 16-Mar-24 06-Jul-24 04-Oct-24 24-Jan-25 203
PS-1880 Facade signage 38 23-Mar-24 29-Apr-24 22-Jan-25 28-Feb-25 306
PS-1890 Screening in Roof 38 12-Apr-24 19-May-24 14-Oct-24 20-Nov-24 186
Mobilizatoin 83 24-May-23 30-Aug-23 08-Jul-23 28-Dec-24 412
Construction 508 30-Jun-23 18-Feb-25 12-Aug-23 23-May-25 81
Approvals and Erection of Tower Crane 30 30-Jun-23 03-Aug-23 27-Mar-25 30-Apr-25 539
Installation of Mockup 33 20-May-24 26-Jun-24 21-Nov-24 02-Jan-25 159
SubStructure 76 27-Jul-23 23-Oct-23 12-Aug-23 25-Oct-23 2
Superstructure 220 23-Oct-23 08-Jul-24 26-Oct-23 23-May-25 270
Mansonry & Finishes (Including staircase 382 17-Nov-23 12-Feb-25 22-Nov-23 23-May-25 86
MEP Works 368 09-Dec-23 18-Feb-25 14-Dec-23 21-Feb-25 3
Authority Inspection, Testing, Commissioning and Handover 295 06-Jun-24 20-May-25 08-Aug-24 23-May-25 3
Authority Insepection 248 06-Jun-24 26-Mar-25 08-Aug-24 24-Apr-25 25
Left out works 217 24-Jun-24 08-Mar-25 17-Sep-24 23-May-25 66
Testing and commissioning 109 10-Jan-25 17-May-25 20-Feb-25 23-May-25 5
Closing out 201 24-Sep-24 20-May-25 11-Dec-24 23-May-25 3

Page 6 of 6 TASK filter: All Activities


© Oracle Corporation

You might also like