CLIENT: CONSULTANT: CONTRACTOR:

DAILY REPORT
Report No. J220/RC/DR/275

Project: Samana Miami-1 Date: 1-May-24

Client SAMANA SIA HOLDINGS LIMITED Weather : Sunny Cloudy Rainy


Consultant AREC ENGINEERING Temperature: Max: 29° Min: 20°
Main Contractor Reliant Contracting LLC Humidity: High Medium Low

Manpower Equipment
Office Staff No. Production Workers No. Type Qty Manpower Hours Worked
GENERAL Manager 1 Carpenter 34 Power Generator 1
PROJECT Manager 1 Steel Fixer 21 Bobcat 1
Site Engineer 2 Mason 7 Welding Machine 1
Asst. Const. Manager - Labor/Helper 7 Tower Crane 1
Planning Engineer 1 Electrician 4 Bar bending Machine 1
MEP Coordinator 1 Painter 4 Vibrator 1
QA/QC Engineer 1 Mechanic Compactor 1
Safety Officer. 1 Plumber 1 Boom Loader 1
Civil Forman 2 Crane Operator 1 Bar Cutting Machine 1
Electrical Forman 1 Rigger 1 1 ton Roller
Plumb. Forman - 6 ton Roller
Driver 4 Excavator
Sub-Contractors:
Office Boy/Cleaner 1 Shovel
Security/Watchman 1 PT Anglo East
Store/Time Keeper 1 Najam Al Simal 4
Almamr Alnader Technical Works
HR/Document Controller 1 L.L.C 11
Safety Officer.Asst.. AK Building Contracting 23
Surveyor 1 Swad Allail General Contracting 4
Surveyor Asst. 1 Jehanzeb Technical Service 3
Trade Foreman -

Total 21 125 9 146 Total= 1564

Work Target for Today:


1. Backwash Tank Excavation work G- Floor
2. Substation Door Fixing & I.R Submission G- Floor
3. Ground Floor Fare face Ceiling Podium
4. Podium Rush Coat Podium
5. 1st Floor Cutting & Chasing Completed 1st Floor
6. 1st Floor MEP 1st Fix Kitchen Area 1st Floor
7. 1st Floor Plaster Preparation and Corner Fixing 1st Floor
8. 2nd Floor Cutting & Chasing Kitchen Area 2nd Floor
9. 2nd Floor MEP 1st Fix 2nd Floor
10. 3rd Floor Cutting & Chasing 3rd Floor
11. 3rd Floor MEP 1st Fix 3rd Floor
13. 5th Floor Block Work Fixing & Curing 5th Floor
14. 6th Floor Block work Fixing & Curing 6th Floor
15. Roof Floor Cleaning Roof
16. Roof to Upper Roof Core wall-1 Curing Casting date: 27/04/24 Upper Roof
17. Safety & Site Cleaning work in progress
Work Target for Next day:
1. Backwash Tank Excavation work G- Floor
2. Substation Door Fixing & I.R Submission G- Floor
3. Podium Rush Coat Podium
4. Fare face for Ground Floor Ceiling Podium
5. Fare face for Podium Ceiling 1st Floor
6. 1st Floor MEP 1st Fix 1st Floor
7. 1st Floor Plaster Preparation and Corner Fixing 1st Floor
8. 2nd Floor Cutting & Chasing 2nd Floor
9. 2nd Floor MEP 1st Fix 2nd Floor
10. 3rd Floor Cutting & Chasing 3rd Floor
11. 3rd Floor MEP 1st Fix 3rd Floor
13. 4th Floor Cutting & Chasing 4th Floor
14. 4th Floor MEP 1st Fix 4th Floor
15. 5th Floor Block Work Fixing & Curing 5th Floor
16. 6th Floor Block work Fixing & Curing 6th Floor
17. Roof Floor Cleaning Roof
18. Roof to Upper Roof Core wall-1 Curing Casting date: 27/04/24 Upper Roof
19. Safety & Site Cleaning work in progress
Material at Site
1. Plywood
2. Scaffolding
3. 3"x3" Timber
4. Blocks
5. Sikanjas.
6. Post Tension Cables
7. Reinforcement Steel
8. Cement
9. Tower crane sections.
Note:
Consultant Eng.: Cont. Engineer: Eng. Sameer Alzebdeh