You are on page 1of 3

 

(Daily Report)

Project's Name : Private Villa At Al-Bahia Farm


Client: : Sheikh Hamed Bin Mhamad Bin Butti Al-Hamed
Consultant : Al-Amir Engineering Consultancy Date : 17/12/2020
Contractor : Masri Engineering & Contracting – MEC SAL

Working Hours : From : 7:00 To: 12:00

From : 13:00 To: 17:00

STAFF MACHINES, EQUIPMENT AND TOOLS


Project Manager 1 Concrete Cutting 0 Mobile Crane
Site Engineer 1 Steel Structure 0 JCB 1
Electrical Engineer 0 GRP works 0 Drill Hilti 3
Draftsman 0 Electrical works 0 Compressor Hilti 1
Planner 0 Grinders 3
Surveyor 0 Roller Compactor 1
Foreman 1 Plate Compactor 1
MEC labors 5 Wood Cutter 2
Drivers & operators 2
Watchman 1

Works executed during the day:


1- Service Preparation for Retaining Wall after the completion of Retaining wall concrete casting.
2- Waterproofing for Retaining Wall.
3- Backfilling & Compaction inside the Retaining Wall for the Third layer

Next day Expected Activities:


1- Service Preparation for Retaining Wall.
2- Waterproofing for Retaining Wall (External Side)
3- Backfilling & Compaction inside the Retaining Wall for the Forth layer
 



(Daily Report)
Date: 17/12/2020

Materials on site:
-

Tests performed on the site:


-

Works delayed beyond our control: Boundary wall and Service blocks

Cause of the delay: - Change the Boundary wall and service blocks foundations type to Piles, (ADM
approval is pending)

General comments: -

Consultant's Representative Contractor's Representative

Signature Signature
* Applying waterproofing for the external side of Ret wall

*Backfilling and Compaction works for the third layer

You might also like