(Daily Report)

Project's Name : Private Villa At Al-Bahia Farm


Client: : Sheikh Hamed Bin Mhamad Bin Butti Al-Hamed
Consultant : Al-Amir Engineering Consultancy Date : 24/12/2020
Contractor : Masri Engineering & Contracting – MEC SAL

Working Hours : From : 7:00 To: 12:00

From : 13:00 To: 17:00

STAFF MACHINES, EQUIPMENT AND TOOLS


Project Manager 1 Concrete Cutting 0 Mobile Crane
Site Engineer 1 Steel Structure 0 JCB 1
Electrical Engineer 0 GRP works 0 Drill Hilti 3
Draftsman 0 Electrical works 0 Compressor Hilti 1
Planner 0 Grinders 3
Surveyor 1 Roller Compactor 2
Foreman 1 Plate Compactor 1
MEC labors 10 Wood Cutter 2
Drivers & operators 2
Watchman 1

Works executed during the day:


1- Backfilling & Compaction inside the Retaining Wall for the 7th & 8th layer.
2- Demarcation and mark up the coordinates for Tie Beams, Ground Beams, and the new pile.
3- Relocation for the water supply.

Next day Expected Activities:


1- Backfilling & Compaction inside the Retaining Wall for the 8th layer.
2- Blinding for Tie Beams and Ground Beams.
4- Demarcation and mark up the coordinates for Tie Beams, Ground Beams, and the new pile.
(Daily Report)
Date: 23/12/2020

Materials on site:
-

Tests performed on the site:


-

Works delayed beyond our control: Boundary wall and Service blocks

Cause of the delay:

General comments: -

Consultant's Representative Contractor's Representative

Signature Signature
*Compaction for the 8th layer.

*Relocation for the Water Supply.

*Relocation for the Water Supply.